1 / 45

2007 Downtime Readiness Review

2007 Downtime Readiness Review. Hamid Shoaee For LCLS Controls Group (in the following departments) Controls Power Conversion Klystron. Agenda. LCLS Control System Installation Readiness Objectives & Scope Schedule & the Process Cable Plant, racks and other infrastructure

leola
Download Presentation

2007 Downtime Readiness Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2007 Downtime Readiness Review Hamid Shoaee For LCLS Controls Group(in the following departments) Controls Power Conversion Klystron

  2. Agenda • LCLS Control System Installation Readiness • Objectives & Scope • Schedule & the Process • Cable Plant, racks and other infrastructure • I&C Systems status and schedule • Issues & Concerns

  3. LCLS Installation and Commissioning Time-Line Injector Controls Installation Complete LTU/und. Install LTU/und. hall “ready” First Spont. Light Controls Checkout A S O N D J F M A M J J A S O N D J F M A M J J 2006 2007 2008 Gun/Inj./BC1 Install (8/21 – 2/20) Gun/Inj./BC1 Commissioning Inj./Linac/BC2 Commissioning linac/BC2 Install LTU/und. Commissioning Oct. 19, 2006

  4. LCLS Accelerator Regions 250 MeV 4.30 GeV 13.6 GeV 6 MeV 135 MeV Linac-X L =0.6 m Linac-0 L =6 m rf gun L0-a,b Linac-1 L 9 m Linac-2 L 330 m Linac-3 L 550 m 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC2 L 22 m BC1 L 6 m ‘Wall region’ DL2 L =275 m Nov. 1, ’07 2007 down, Sept-Nov Commission now SLAC linac tunnel research yard Down: Sep., Oct., Nov. of 2007 Run: Dec. 2007 through ~Aug. 2008 To: SL2-stopper in BSY (just past linac sector-30)

  5. Modifications in Sector-24 for BC2 (Emma) • Remove 8 RF sections (24-7, 8) • Remove quad Q24801 • Add 4 new bends in sector-24 • Add 6 new quads (3 types) • Add 1 ‘wide’ BPM • Add 1 x-collimator • Add 1 OTR screen

  6. Linac Modifications (Fall ‘07) • Remove 8 RF sections (24-7, 8) • Remove quad Q24801 • Add 4 new bends in sector-24 • Add 6 new quads (3 types) • Add 1 ‘wide’ BPM • Add 1 x-collimator • Add 1 OTR screen

  7. Linac Modifications (continued) • Add 4 new wire scanners in sector-24 • Add 3 OTR screens (1 BC1, 2 in sec-25) • Move LOLA (trans. deflector) from sec-29 to 25-2 (powered by the 24-8 klystron) • Add pulsed horizontal dipole magnet in sec-25 (BXKIK) • Move 2 LI28 Wire Scanners, 44 & 544, by 20-30 meters • BPM electronics upgraded (resolution improved) • More feedback loops (energy & bunch length)

  8. Linac Modifications (continued) • Power Systems • BC2 racks & PS (install racks and PS at sector 24) • I&C Systems • I&C racks and systems (install racks at sector 24) • Cable Plant • Sector 24 ( install new trays and cable plant from sector 24 racks into Linac; terminate at racks and at loads) • BTH West (pull cables from B005, 105, 106 through BSY into BTH West and coil cables; no loads & no racks installed yet) • B136 through BSY to BTH West • Remove cut cables from FFTB

  9. Plans & Process for BC2 Controls System Installation • Controls installation takes place in several steps: • Design, procurement and Installation of the cable plant including trays, long haul DC and I&C cables • Cables Termination and connection to beam line components (Mechanical Systems) • Procurement & preparation of electronics racks • Installation of electronics chassis and modules including crates, IOCs, timing modules in the racks • Rack installation in the field, AC & cable plant connection

  10. Controls Installation Schedule Overview

  11. Cable Plant Design & Installation Process • From the list of devices to be installed… • Develop racks layout & cable tray design • Generate rack profiles for electronics modules • Identify DC & I&C cabling requirements & document in CAPTAR • Produce installation bid package from CAPTAR and tray designs • Generate installation bid package & award contract • Procure trays, cables, connectors, etc. • Install cable plant and terminate to beam line components

  12. Typical Sector Cable List(Michael De salvo, Mario Ortega)

  13. Sector 24 Connector List First draft BC2 cable design • 13k feet • $245k (cable) • $10k (connectors)

  14. Racks will be pre-loaded in B24 before field installation

  15. BC2 Controls Sub-Systems • Cable plant • Racks, crates, IOC, etc. • Networks • Magnet power supply control • Vacuum control • Safety systems • PPS, MPS, BCS • Motion control • Wire scanners, Collimators, Chicane • Timing • Beam instrumentation and diagnostics • BPM, Toroid, OTR/YAG, Bunch length monitor • LLRF

  16. LCLS Controls systems • For each system… • Technical leads have developed a schedule covering all phases leading to installation and commissioning • The schedules include development of appropriate field documents (EI, WD), rack profile/cable plant design, procurement, installation and system checkout • Continue Interfacing with Mario Ortega, Bob Fuller, Mike DiSalvo to coordinate procurement and installation • We will be reviewing each schedule to identify bottlenecks, dependencies on other systems, resource availability

  17. Safety Systems for BC2,L2,L3 • PPS • The Linac PPS does not require modification to run LCLS beam to SL-2. • There is an AIP project to convert the Linac and BSY to the LCLS PLC-based system in 2008 • MPS • We will use the current (1553-based) MPS for BC2. • Two new ion chambers will be required • The system will include 10 LDIM inputs • OTR21 (2ea) • OTR22 (2ea) • OTR_CAV (2ea) • BC2 Mover (2ea) • CE21 (2ea) • We will need to commission AP25 (currently installed but powered down) to accommodate a new PICP module and an LDIM (already installed).

  18. BC2 MPS ScheduleCheck out 12/3

  19. Concurrently developing new LCLS MPS • Response time of less than one pulse at 120 Hz • Decoupling from Master Pattern Generator (MPG) • Fast communication and processing • Knowledge of beam rate • Integration of EVR to MPS and fault devices • New hardware extended 1.2 km past current MPS • Non-CAMAC • Ready for photon section

  20. LCLS MPS Features • Has response time low enough to protect the undulator (less than 8.3 ms) • Communicates with LCLS timing system (EVG) • Supports new beam loss monitoring hardware and rate limiting methods • Easily extendable and is designed around standards based COTS components • Flexible input and output methods

  21. Overview

  22. Core Hardware and Software Note: These are material costs only. Development labor, installation, etc. costs are not included.

  23. Other MPS Devices

  24. Milestones

  25. BCS (Beam Containment System) • We will use & extend the existing BCS for BC2 commissioning • Two possible configurations are being considered • New BCS PIC System installation in Sector-24 • A 50 conductor trunk from the Sector-28 BCS rack to a new rack in Sector-24. • Long hauls from Sector-24 BCS Rack to the beam line devices in Sector-24 (2 cables per PIC, 1 cable per LION, 1 cable per Flow Switch or Pressure Switch) • Use BCS PIC system in Sector-28(Depends on being able to drive PIC/LION HV and signal four sectors) • Long hauls from Sector-28 to the beam line devices in Sector-24 (2 cables per PIC, 1 cable per LION, 1 cable per Flow Switch or Pressure Switch) • For either configuration… • Install VME Crate and associated hardware/software/network • Install new LION Gas system. • AC Power to Sector-28 & Sector-24 racks.

  26. BC2 BCS ScheduleCheck out 11/23

  27. Magnet Power Supply Control • The software design is mature and will require little if any changes for BC2 • Procurements are well under way and orders have been placed for power supplies, racks, etc. • There is a detailed schedule covering bench testing, rack loading, wiring, pre-installation checkout, through field installation • The system will be ready 11/30

  28. 11/30/07

  29. Vacuum controls uses BC1 design, with detailed procurement list in place

  30. Vacuum controls check out by 11/20/07

  31. Wire scanners, Collimators and BC2 motion control use the same design as BC1, and will be available 11/20/07

  32. Networks will be ready early in October to allow Controls checkout

  33. Timing System • The scope is to deliver triggers and timestamp data to all subsystems requiring such. • The system can be split into two parts • Long-haul distribution of triggers from the EVG to EVRs in Linac and beyond • Short-haul back end consisting of the HW & SW to receive the EVG timing signal and generate triggers. This is well-understood and defined. • Part 1 requires some engineering development as the event system can only have a maximum link length of 300 meters. We can daisy-chain, but only for 3 hops before exceeding the jitter budget. We need a better solution • This is a tractable item and should not have a high level of risk. • Another item of concern with the long-haul distribution is timing phase error due to temperature drift – a mechanism is needed to correct for this. • This will need some R&D and we need to decide based on short- versus long-term requirements if users can live with this for now. We have to anyway since time is short • We have a procurement for the "back end" of the timing system consisting of all the HW (fan-outs, EVRs, crates, cables) to deliver triggers to the end subsystem. • The long haul procurement list is pending a design decision

  34. Timing System Schedule

  35. Beam Instrumentation & Diagnostics • Profile Monitors • There are 3 OTRs in the LINAC: OTR21, OTR22, OTR_TCAV – These use BC1 designs and electronics • Design in April, procurement in May, system test July ~ August. • Toroids • There are two toroids in linac: IMBC2I and IMBC2O • We need to re-spin the data acquisition board for small revisions to the artwork • Electronics will be ready in August for system testing • Bunch Length Monitor • BL21 and BL22, similar to BL11 and BL12 in BC1 • Procurement in April and test in May ~ June. • Dumps and Stoppers • SL2 might need some new data monitoring.

  36. Beam Position Monitors • The linac BPMs have to be upgraded for better resolution for undulator commissioning in May-June ‘08 • Do we need to upgrade for the BC2,L2,L3 commissioning? • Do the existing BPM electronics work at 200 pC? • Do they trigger reliably at low charge? • What resolution do they provide? • Test next week with A-Line beam • If we need the linac BPM upgrade • Install 20 racks • Design and install cable plant for 79 BPMs • Re-spin BPM analog front-end design • Fabricate and test 120 BPM chassis • Install 79 BPM chassis • If we can defer the upgrade • We still have to install the cable plant for all of the linac BPMs in this down time • Of the 17 BPMs in switchyard we will connect to only 2 • And one BPM in BC2

  37. LLRF Schedule

  38. BC2 Controls Risk Matrix

  39. Testing & Checkout Strategies • For each subsystem, we will use test stands to verify the complete system • Test stands currently in place include: • Timing • Vacuum • Magnet power supplies • Motion control – wire scanners, collimator, etc. • Rack loading & testing • Need to accomplish as much as possible in B024 prior to Sept. transport to field site. • In-field loading (Davis-Bacon) and intra-rack cabling is less efficient.

  40. Rack Assembly Area

  41. Issues & Concerns • Schedule & Resources • Schedule is very tight, just fits in down time • Controls is the systems “integrator” – delays in other systems directly impact our installation • Cable Plant Installation • Coordination of activities with other installation groups is very important and could jeopardize schedule • Linac BPM upgrade could be an added challenge • System Functionality • Timing System – small concern • BPM, Toroid – need verification of design

  42. Summary • Controls in general is in good shape for 2007 installation • No major design or production issues dominate the plan • The schedule is challenging with little float • While a large number of sub-systems will be installed on time, some will need attention to stay on schedule

More Related