530 likes | 972 Views
Lifting Operations on Construction Sites. A presentation to Merseyside & Cheshire Construction Safety Group on 12 th March 2018 by: John Ellis BSc(Eng),CMIOSH,CMaPS. Most common ways of lifting:. Mobile Cranes Telehandler Excavator Hiab. Types of Mobile Crane.
E N D
Lifting Operations on Construction Sites A presentation to Merseyside & Cheshire Construction Safety Group on 12th March 2018 by: John Ellis BSc(Eng),CMIOSH,CMaPS
Most common ways of lifting: • Mobile Cranes • Telehandler • Excavator • Hiab
Types of Mobile Crane • Truck-mounted crane • All-terrain crane • “City” crane • Self-erecting tower crane
Summary of suitability • Truck mounted-long wheelbase, large turning circle • All terrain-more compact, all wheel steer, highly manoeuvrable • City crane-compact, able to operate in limited headroom areas • Tower crane-large working radius directly adjacent to structures
What factors determine the size of crane needed ? • Maximum weight of load to be lifted (e.g. 3.7 tonnes @ 15m radius) • Maximum working radius (e.g.37m lifting 1.2 tonnes) • Angle of jib in restricted headroom locations
Imposed Loadings • Must be clearly shown on lifting plan as both point load and pressure(e.g. point load=25KN,pressure of 25KN/m2) • Should indicate size of pads being used(typically 1m diameter pads have an area of 0.7m2) • Tables can be used to get approx. loads, or crane hire company will be able to provide more precise detail
Ensure ground bearing pressures acceptable • Provided details of imposed loadings to the site (in writing) • Obtain written confirmation from the site that the ground is capable of withstanding the loads • May need CBR tests to be undertaken • May need additional measures to reduce pressures to an acceptable level e.g. steel plates,sleepers,mats
Lift plan should indicate: • Crane access and locations • Crane size and lifting equipment • Berthing study (rigger spread) • Imposed loadings • Position of delivery wagons • Directions of slew • Positions of new/existing buildings • Location of any specific hazards
Planning must be done by a competent person (appointedperson)
Supervision • Supervision done by the appointed person • Or, if not, then by a qualified crane supervisor • Directing the crane is done by a qualified banksman who agrees a means of communication with the crane driver • Slinging is undertaken by trained slingers • Crane driven by suitably competent operator
Summary • Select suitable type of crane • Select right size of crane for the job • Understand how a crane works • Ensure all involved in the planning and operation are competent
Don’t have the required Skills,Knowledge,Experience ? • You must arrange for a “Contract Lift” • A reputable crane hire company will visit the site and do all the necessary planning • They will provide relevant documentation for the lift including a lift plan • On the day they will provide crane driver and crane supervisor/banksman • They will also provide appropriate lifting tackle(chains,slings,etc.)
What can go wrong? • Crane exceeds safe working capacity • SWL of lifting accessories exceeded • Imposed rigger loadings exceed ground bearing capacity • Structural failure of crane and/or lifting accessories (due to lack of maintenance) • Operation in adverse weather conditions • Communication failures
Requirements • Driver must have appropriate skills, knowledge & experience(e.g. CPCS for type & size of telehandler) • Operate on firm & level ground when placing/removing loads (e.g. designated stoned up area) • Suitable reversing mirrors & cameras • Use of stabilizers when required
Types of excavator • Back-hoe excavator • Mini excavator • Tracked excavator
Requirements • Driver to have necessary skills, knowledge & experience for type & size of excavator • Driver to have suitable knowledge & training in attachments (e.g. manual quick hitch, semi-automatic quick hitch, automatic quick hitch • Suitable reversing mirrors and cameras to enable driver to see persons at rear
Requirements • Driver with suitable skills, knowledge & experience • Set up on firm & level ground capable of withstanding rigger loadings • All riggers to be fully extended
Statutory Requirements for Lifting Plant LOLER Regulations require that all plant used for lifting has undergone thorough examination & inspection by a competent person within previous 12 months …..but if being used for lifting persons (e.g. man-rider cage attached to forklift) then must be within previous 6 months
Lifting tackle • Chains (e.g. 2 legged 10mm chains,SWL 4.25 tonnes) • Web slings or wire slings • Grabs of lifting booms • Lifting clutches (e.g. modform lifters) All must be maintained in good condition and should be visually inspected each day before lifting operations commence
Requirements • Capacity of the choked chains must be downrated by 20% • i.e. 2 legged Chains with SWL of 4.25 tonnes can only be used to lift a maximum load of 3.4 tonnes
Statutory Requirements • All lifting accessories to have undergone thorough examination and inspection by competent person within the previous 6 months (as per LOLER Regulations)
Guidance • BS7121 Part 3:Code of Practice for Safe use of Cranes
HSE Guidance • L113 :Safe Use of Lifting Equipment ACOP • L22:Safe Use of Work Equipment • INDG290:Lifting Equipment at Work-a Brief Guide • INDG422:Thorough Examination of Lifting Equipment • HSG144:Safe Use of Vehicles on Construction Sites • HSG150:Health & Safety in Construction