WLCG Update

Ian Bird LHCC Referees Meeting; CERN, 12 th March 2013. WLCG Update. ASGC - Taipei. On Feb 21, Academia Sinica , Taipei informed CERN DG that they intended to withdraw support for CMS as a Tier 1 and as a Tier 2 at ASGC CMS have no physicists in Academia Sinica

lexine
Download Presentation

WLCG Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ian Bird LHCC Referees Meeting; CERN, 12thMarch 2013 WLCG Update Ian.Bird@cern.ch

  2. ASGC - Taipei Ian.Bird@cern.ch • On Feb 21, Academia Sinica, Taipei informed CERN DG that they intended to withdraw support for CMS as a Tier 1 and as a Tier 2 at ASGC • CMS have no physicists in Academia Sinica • ASGC has lost part of its funding from the National Science Council • Response sent March 6 • Asking for clarification of intended timescales and to inform WLCG OB and RRB

  3. Status of new Tier 1s Ian.Bird@cern.ch

  4. Update on KISTI-GSDC • 1512 cores (63 WNs) with 3GB memory/core • 1.042 PB Disks: old SE(100TB) will be removed; new storage will be delivered • 1 Gbps Network to be upgraded to 2Gbps in coming April • EMI-2 Migration done and on production (better behaviour than gLite-3.2) • Tape • 1 PB capacity (expandable up to 3 PB, 2GB/s throughput) with 200 TB xrootd pool + 275 TB tape buffer • Functional tests done, Policy tuning on-going for xrootd, GPFS • Periodic test by ALICE shows good -> p-Pb data transfer scheduled to start on 7th March

  5. JINR CMS Tier-1 progress • Disk & server installation and tests: done • Tape system installation: done • Organization of network infrastructure and connectivity to CERN via GEANT (2 Gbps):done • LHC OPN integration: postponed* • Registration in GOC DB and APEL: done • Tests of WLCG services via Nagios: done • CMS-specific tests: in process * restructurising local network to ease integration with LHC OPN

  6. RRC-KI Tier-1 progress • Disk & server installation and tests: done • Tape system installation: done • Network connectivity to CERN via GEANT (2 Gbit/sec): done • LHC OPN integration: postponed* • Registration in GOC DB and APEL: done • Tests of WLCG services via Nagios: done • ATLAS-specific tests: in process, have preliminary results that look good • * restructurising our network to ease integration with LHC OPN

  7. ATLAS-specific activity • Prepared services and data storage for the reprocessing of 2011 2.76 TeV reprocessing • Currently commissioning Tier-1 resource for ATLAS: • Stress tests via HammerCloud • Reconstruction tests submitted by ATLAS experts • Functional tests via Panda and DDM • Transferred 54 TB of input data to our storage element with transfer efficiency around 90%

  8. Overall status Ian.Bird@cern.ch

  9. Data accumulated Data written into Castor per week Volume of CERN archive Ian.Bird@cern.ch 2012/13 Data written 2012/13 Data read

  10. CPU usage Ian.Bird@cern.ch

  11. Operations Ian.Bird@cern.ch

  12. Resource requests 2013-15 Ian.Bird@cern.ch

  13. Preparation for April RRB Ian.Bird@cern.ch • Met with RSG chair + LHCC referees in February • Agreed an assumed running scenario for 2015, in order to produce requirements • 5.10^6 s of operation; less pileup in first part, increased in 2nd part of year • Discussed how to present 2015 needs • Potentially significantly increased trigger rates • Aggressive work during LS1 to enable the needs to be met with reasonable resource increases • The estimates for 2015 are now somewhat less than the x2 feared; except for tape needs; • Ramp-up during 2015 – clearly early in the year less will be needed • [Also agreed to set the disk usage “efficiency” to 1 to avoid confusion]

  14. 2013  2015 resources CPU Disk Tape 2013: pledge OR actual installed capacity if higher Ian.Bird@cern.ch

  15. Use of Tier 0 and HLT during LS1 Ian.Bird@cern.ch • During LS1; the Tier 0 resources will be used for analysis as well as re-processing • This is a different use pattern; requires more disk that Tier 0 functions • Also the HLT farms will be extensively used to supplement the grid resources

  16. Tier 0 Upgrades Ian.Bird@cern.ch

  17. WIGNER Data Center After full refurbishment, hosting CERN Tier-0 From 1 january 2013 IT Department Meeting

  18. Data Center Layout & ramp-up IT Department Meeting

  19. Connectivity (100 Gbps) IT Department Meeting

  20. 513 Consolidation Project: Goals IT Department Meeting • Solve the cooling issue for the critical UPS room • New UPS systems in a different location • Increase critical UPS capacity to 600kW • Restore N+1 redundancy for both critical and physics UPS systems • Secure cooling for critical equipment when running on UPS and extend stored cooling capacity for physics when on diesel • Decouple the A/C for CC from the adjacent office building • Increase overall power capacity to 3.5MW

  21. IT Department Meeting

  22. Planning for the future Ian.Bird@cern.ch

  23. EC projects Ian.Bird@cern.ch • EMI (middleware) ends April 2013 • EGI-SA3 (support for Heavy User communities) – ends April 2013 • Although EGI-Inspire continues for 1 more year • These have impact on CERN groups supporting the experiments, as well as NGI support • Consequences: • Re-prioritisation of functions is needed • Need to take action now if we anticipate attracting EC money in the future • But there is likely to be a gap of ~1 year or more

  24. Short term: Consolidation of activities at CERN • WLCG operations, service coordination, support • Consolidate related efforts (daily ops, integration, deployment, problem follow-up etc) • Broader than just CERN – encourage other labs to participate • Common solutions • Set of activities benefitting several experiments. Coordinates experiment work as well as IT-driven work. Experiments see this as strategic for the future; beneficial for long term sustainability • Grid monitoring • Must be consolidated (SAM/Dashboards). Infrastructure becoming more common; focus on commonalities, less on experiment-specifics • Grid swdevelopment+support • WLCG DM tools (FTS, DPM/LFC, Coral/COOL, etc), information system; Simplification of build, packaging, etc.  open source community processes; (See WLCG doc)

  25. Longer term Ian.Bird@cern.ch • Need to consider how to engage with EC and other potential funding sources • However, in future boundary conditions will be more complex: (e.g. for EC) • Must demonstrate how we benefit other sciences and society at large • Must engage with Industry (e.g. via PPP) • HEP-only proposals unlikely to succeed • Also it is essential that any future proposal is fully engaged in by CERN (IT+PH) and experiments and other partners

  26. Background Ian.Bird@cern.ch • Requested by the LHCC in December: need to see updated computing models before Run 2 starts • A single document to: • Describe changes since the original TDRs (2005) in • Assumptions, models, technology, etc. • Emphasise what is being done to adapt to new technologies, to improve efficiency, to be able to adapt to new architectures, etc. • Describe work that still needs to be done • Use common formats, tables, assumptions, etc • 1 document rather than 5

  27. Timescales Ian.Bird@cern.ch • Document should describe the period from LS1 – LS2 • Estimates of evolving resource needs • In order to prepare for 2015, a good draft needs to be available in time for the Autumn 2013 RRB, so needs to be discussed at the LHCC in September: • Solid draft by end of summer 2013 (!) • Work has started • Informed by all of the existing work from the last 2 years (Technical Evolution groups, Concurrency forum, Technology review of 2012)

  28. Opportunities Ian.Bird@cern.ch • This document gives a framework to: • Describe significant changes and improvements already made • Stress commonalities between experiments – and drive strongly in that direction • Significant willingness to do this • Describe the models in a common way – calling out differences • Make a statement about the needs of WLCG in the next 5 years (technical, infrastructure, resources) • Potentially review the organisational structure of the collaboration • Review the implementation: scale, quality of service of sites/Tiers; archiving vs processing vs analysis activities • Raise concerns: • E.g. staffing issues; missing skills;

  29. Draft ToC Ian.Bird@cern.ch Preamble/introduction Experiment computing models Technology review and outlook Challenges – the problem being addressed Distributed computing Computing services Software activities and strategies Resource needs and expected evolution Collaboration organisation and management

  30. Ian.Bird@cern.ch

  31. Summary Ian.Bird@cern.ch • WLCG operations in good shape, • Use of computing system by experiments regularly fills available resources • Concern over resources vs requirements in the future • Tier 0 consolidation work close to complete, deployment beginning • Important to take concrete steps now for future planning for support