Infrastructure and Provisioning at the Fermilab High Density Computing Facility Steven C. Timm Fermilab HEPiX conference May 24-26, 2004 Outline Current Fermilab facilities Expected need for future Fermilab facilities Construction activity at High Density Computing Facility
E N D
Infrastructure and Provisioning at the Fermilab High Density Computing Facility Steven C. Timm Fermilab HEPiX conference May 24-26, 2004 S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Outline • Current Fermilab facilities • Expected need for future Fermilab facilities • Construction activity at High Density Computing Facility • Networking and power infrastructure • Provisioning and management at remote location S. Timm--Infrastructure and Provisioning at Fermilab HDCF
A cast of thousands…. • HDCF design done by Fermilab Facilities Engineering, • Construction by outside contractor • Managed by CD Operations (G. Bellendir et al) • Requirements planning by taskforce of Computing Division personnel including system administrators, department heads, networking, facilities people. • Rocks development work by S. Timm, M. Greaney, J. Kaiser S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Current Fermilab facilities • Feynman Computing Center built in 1988 (to house large IBM-compatible mainframe). • ~18000 square feet of computer rooms • ~200 tons of cooling • Maximum input current 1800A • Computer rooms backed up with UPS • Full building backed up with generator • ~1850 dual-CPU compute servers, ~200 multi-TB IDE RAID servers in FCC right now • Many other general-purpose servers, file servers, tape robots. S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Current facilities continued • Satellite computing facility in former experimental hall “New Muon Lab” • Historically for Lattice QCD clusters (208512) • Now contains >320 other nodes waiting for construction of new facility S. Timm--Infrastructure and Provisioning at Fermilab HDCF
The long hot summer • In summer it takes considerably more energy to run the air conditioning. • Dependent on shallow pond for cooling water. • In May building has already come within 25A (out of 1800) from having to shut down equipment to shed power load and avoid brownout. • Current equipment exhausts the cooling capacity of Feynman computing center as well as the electric • No way to increase either in existing building without long service outages. S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Computers just keep getting hotter • Anticipate that in fall ’04 we can buy dual Intel 3.6 GHz “Nocona” chip, ~105W apiece • Expect at least 2.5A current draw per node, maybe more, 12-13 kVA per rack of 40 nodes. • In FCC we have 32 computers per rack, 8-9 kVA • Have problems cooling the top nodes even now. • New facility will have 5x more cooling, 270 tons for 2000 square feet • New facility will have up to 3000A of electrical current available. S. Timm--Infrastructure and Provisioning at Fermilab HDCF
We keep needing more computers • Moore’s law doubling time isn’t holding true in commodity market • Computing needs are growing faster than Moore’s law and must be met with more computers • 5 year projections are based on plans from experiments. S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Fermi Cycles as a function of time Y=R*2^(X/F): Moore’s law says F=1.5 years, F=2.02 years and growing. 1000 Fermi Cycles PIII 1 GHz S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Fermi Cycles per ampere as function of time S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Fermi cycles per dollar as function of time S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Strategy: • Feynman center will be UPS and generator-backed facility for important servers • New HDCF will have UPS for graceful shutdown but no generator backup. Designed for high-density compute nodes (plus a few tape robots). • 10-20 racks of existing 1U will be moved to new facility and reracked • Anticipate10-15 racks of new purchase this fall also in new building S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Location ofHDCF 1.5 miles away from FCC No administrators will be housed there—will manage “lights out” S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Floor plan of HDCF Room for 72 racks in each of 2 computer rooms. S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Cabling plan Network Infrastructure Will use bundles of individual Cat-6 cables S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Current status • Construction began early May • Occupancy Nov/Dec 2004 (est). • Phase I+II, space for 56 racks at that time. • Expected cost: US$2.8M. S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Power/console infrastructure • Cyclades AlterPath series • Includes console servers, network-based KVM adapters, and power strips • Alterpath ACS48 runs PPC Linux • Supports Kerberos 5 authentication • Access control can be divided by each port • Any number of power strip outlets can be associated with each machine on each console port. • All configurable via command line or Java-based GUI S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Power/console infrastructure PM-10 Power strip 120VAC 30A 10 nodes/circuit Four units/rack S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Installation with NPACI-Rocks • NPACI (National Partnership for Advanced Computational Infrastructure), lead institution is San Diego Supercomputing Center • Rocks—”ultimate cluster-in-a-box tool.” Combines Linux distribution, database, highly modified installer, and a large amount of parallel computing applications such as PBS, Maui, SGE, MPICH, Atlas, PVFS. • Rocks 3.0 based on Red Hat Linux 7.3 • Rocks 3.1 and greater based on SRPMS of Red Hat Enterprise Linux 3.0. S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Rocks vs. Fermi Linux comparison Fermi Linux REDHAT Rocks 3.0 R E D H A T 7. 3 Adds: Workgroups Yum OpenAFS Fermi Kerberos/ OpenSSH Adds: Extended kickstart HPC applications MySQL database S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Expects all compute nodes on private net behind a firewall Reinstall node if any changes All network services (DHCP, DNS, NIS) supplied by the frontend. Nodes on public net Users won’t allow downtime for frequent reinstall Use yum and other Fermi Linux tools for security updates Configure ROCKS to use our external network services Rocks Fermiarchitecture Application S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Fermi extensions to Rocks • Fermi production farms currently have 752 nodes all installed with Rocks • This Rocks cluster has the most CPU’s registered of any cluster at rocksclusters.org • Added extra tables to database for customizing kickstart configuration (we have 14 different disk configurations) • Added Fermi Linux comps files to have all Fermi workgroups available in installs, and all added Fermi RPMS • Made slave frontend install servers during mass reinstall phases. During normal operation one install server is enough. • Added logic to recreate kerberos keytabs S. Timm--Infrastructure and Provisioning at Fermilab HDCF
S.M.A.R.T Monitoring • “smartd” daemon from smartmontools package gives early warning of disk failures • Disk failures are ~70% of all hardware failures in our farms over last 5 years. • Run short self-test on all disks every day S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Temperature/power monitoring • Wrappers for lm_sensors feed NGOP and Ganglia. • Measure average temperature of nodes over a month • Alarm when 5C or 10C above average • Page when 50% of any group at 10C above average • Automated shutdown script activates when any single node is over emergency temperature. • Building-wide signal will provide notice that we are on UPS power and have 5 minutes to shut down. • Automated OS shutdown and SNMP poweroff scripts S. Timm--Infrastructure and Provisioning at Fermilab HDCF
Reliability is key • Can only successfully manage remote clusters if hardware is reliable • All new contracts are written with vendor providing 3 year warranty parts and labor…they only make money if they build good hardware • 30-day acceptance test is critical to identify hardware problems and fix them before production begins. • With 750 nodes and 99% reliability, still 8 nodes would be down a day. • Historically reliability is closer to 96% but new Intel-based Xeon nodes are much better. S. Timm--Infrastructure and Provisioning at Fermilab HDCF