VANDER LAW FIRM “COMMITTED TO LEGAL EXCELLENCE AND CLIENT SATISFACTION”
The Two Sites Anaheim San Diego
Planning • There are four employees working for five days a week. All labor is paid by the hour on an eight hour a day work shift. The total amount of weeks on the project is ten weeks. The first two will be dedicated on gathering equipment and transportation that will be used in the following weeks. Any finalizations in planning and organization • After all necessary equipment and accessories are prepared; the next four weeks will be spent setting up the network at the Anaheim location. Then the last remaining four weeks will be dedicated on setting up and configuring the network at the San Diego site. • Transportation and Accommodation to Anaheim Holiday Inn and San Diego Holiday Inn will be $120/night per person for eight weeks.