Phase II – SHDH Air Handler #9 Town Hall Meeting - March 12, 2014. Phase II. Introduction/Explanation of project Review Scope of Project Construction Schedule/Impact to the SHDH building occupants - Hunter Roberts Construction Group Communication Plan – Wharton Operations Questions.
E N D
Phase II – SHDH Air Handler #9 Town Hall Meeting - March 12, 2014
Phase II • Introduction/Explanation of project • Review Scope of Project • Construction Schedule/Impact to the SHDH building occupants - Hunter Roberts Construction Group • Communication Plan – Wharton Operations • Questions
Explanation • Project Team – same project team that worked on Phase I • Why are we doing this project? • Continuation of the work that needs completed as part of the AHU # 9 installation that happened this past summer. • Historically, SHDH has had multiple HVAC issues, a common theme is problems maintaining a comfortable temperature in the building. • Too cold in the summer and too hot in the winter!! • Building systems will be more efficient and sustainable
Project Scope & Phasing • Phase 2 (April 2014 – August 2014) • Much more intensive than Phase I • Work will begin on the ground floor, and we will work our way up floor by floor. • All work will occur in the evening (11PM – 7AM) • Will need access to majority of rooms on the perimeter of the building. • Will be a coordinated effort between, contractor, security, operations and housekeeping • In selected rooms, we will be completing the following work • New thermostat installations “T” • Ceiling work – “C” • Radiator work – “R”
“T” - New Thermostat • Scope: • Installation of a new digital thermostat directly next to or below existing thermostat • Once new thermostat becomes operational, old t-stat to be removed, wall to be patch and painted • Prep work • None • Impact: • None • Schedule: • April – mid June
“C” – Ceiling Work • Scope: • Installation of a new equipment and associated duct work and piping • Prep work • Remove all personal and breakable items from your desktop and store in a safe location. Computer can remain on desk. • Remove all pictures from the walls • Remove all items from floor, so workmen can set up ladders • Protection will installed each night while work is occurring • Impact: • Will have access to office each day. But at times there will be ceilings out of place • Might be a period of temperature fluctuations while work is being completed. • Schedule • May – Mid August see attached spreadsheet for details. • Contractor will need access for 10 days depending on location
“R” – Radiator work • Scope: • Installation of new valves on existing radiators and bypass piping • Prep work • All furniture in front of the radiator must be relocated in the room while work occurs • Remove personal and breakable items from your desk • Remove all items from floor, so workmen can access space safely • Impact: • Will have access to office each day. But we will need to keep area clear while work is occurring. • Schedule • Work will be done in office groupings See attached spreadsheet for details. • Contractor will need access to office for 7 days
Floor Plans Department Name For latest floor plans see Wharton Operations’ project page.
Schedule Department Name For latest schedule see Wharton Operations’ project page.
Communication Plan Wharton Operations • Project website. • Daily site walk-throughs • Communication with business administrator • Weekly email updates to building occupants • Quarterly update meetings with building occupants