Wireless Deployment : Site Survey Access Network SID ETP – Groupement Télécoms - 25 Mai 2005. OMC-R. BTS. BSC. TCU. MSC/HLR. Objectives. Survey of Candidate Site. 40 GHz. Site Engineering Solutions. Contract signature. Systems & Network Integration Plans.
E N D
Wireless Deployment : Site Survey Access NetworkSID ETP – Groupement Télécoms - 25 Mai 2005
OMC-R BTS BSC TCU MSC/HLR Objectives Survey of Candidate Site 40 GHz Site Engineering Solutions
Contract signature Systems & Network Integration Plans Project Management & Network Design Authority Preliminary Network Design Systems & Network Design Systems & Network Planning Test Plans Design Subscribers Forecast Detailed Engineering Contract Consolidation Detailed Consolidation Manufacturing & Delivery Microwave Clearing Radio & Site Survey Site Acquisition & Zoning Operations Site Construction and Preparation Installation & Commissioning Pilot Integration Testing Extension & Upgrade In Service Network Integration Systems Integration RF Verification Network Acceptance Project Management & Field System Engineering RF Optimization Network Optimization Performance Monitoring TAS Cellular Network Engineering Process
System Design Roll Out (VO, Instal.) Site Survey Field Tests Radio Freq. Qualif. Customer Info Gathering BTS SS and SE Activities in the Network Roll-out Network Design and implementation strategy Bid Project Detailed analysis and Field Preparation Roll out and in service Network Optimization Pilot Network Network Design Application Eng'g Cell Planning Network (VO, Network Optimization Site Eng'g Radio Survey Measuring Equipment Contract
Site Preparation Coordination Site Preparation Coordination Site Installation Acceptance RF Model Aerial Verification Local Tests Site Engineering Site Surveys + Reports Site Preparation Cabinet Installation Site Document Site Preparation Accepted As Built Document Commissioning The Site Installation Process
The Site Specifications • Scope and Goals BTS Cell Planning Zone of search
The Site Specifications • Collected Information • Ease of: • Handling • Installation • Commissioning • Equipment functioning • Maintenance
BTS ? BTS The Site Specifications • Constraints Site Investigation Constraints + • General access • Building access • Unloading requirements • BTS Room dimension requirements * x ?
The Site Specifications • Equipment Constraints • Cable trays • Equipment Power Supply • Lighting • Grounding System • Equipotentiality System • Connection Requirements (RF signals, PCM, and others) • Environmental constraints
Floor # 2 A U T H O R I Z A T I O N The Site Survey • Constraints AC DDF
Site ! The Site Survey • Process Overview Site Specifications Site Survey (questionnaire) ?! Site Survey Report
Depth Number of floors Heigth Access? The Site Survey • The Building Survey Width
The Site Survey • The Building Survey GPS
The Site Survey • The Building Survey Tower BTS location B T S DDF location AC Power Grounding System
The Site Survey • The BTS Room Survey • Dimensions (raised floor, false ceiling, etc.) • Location and dimensions of the existing equipment • Location of BTS cabinet • Location of power and grounding system • Location of the DDF • Location, dimensions, and availability of the cable trays • Location, dimensions, and availability of the feeder input
The Site Survey • The BTS Room Survey Weak current, feeder and alarm zone Strong current zone 14 11 9 13 10 10 15 1 6 7 2 8 3 4 12 5
The Site Survey • The Outdoor BTS Room Survey
The Site Survey • The Outdoor BTS Room Survey X + Y + Z = 2 meters
The Site Survey • The Outdoor BTS Room Survey
The Site Survey • The Aerial Survey • North direction in relation to the building and tower • Location and orientation of the existing antennas • Quantity, location and azimuth of the antennas • Sector/azimuth • Type of fixation • Lightning protection system, existing or not
Site Eng’g activities End of Presentation Site Engineering activities