St. John’s Hospital. Welcome to the Project Launch of the Short Stay Elective Surgical Centre. SSESC Project Launch Agenda:. Clinical drivers (Didi Welsh) Project Infrastructure (Gordon Reid) Project delivery (Doug Keillor, BAM).
E N D
St. John’s Hospital Welcome to the Project Launch of the Short Stay Elective Surgical Centre
SSESC Project LaunchAgenda: • Clinical drivers (Didi Welsh) • Project Infrastructure (Gordon Reid) • Project delivery (Doug Keillor, BAM)
Short Stay Elective Surgical CentreMrs Didi Welsh Project Sponsor
Short Stay Elective Surgical Centre Day Case Pathway GP OPD Hospital Doctor Pre Admission Admission Theatre Recovery Discharge Home
Short Stay Elective Surgical Centre Total Day Case Elective Admission Cases April 2007/March 2008 (RIE/WGH/St John’s) 51485 (61% overall elective activity)
1 entry point Pre assessment for all patients Universal streamline pathway Robust administration system based on PFB Reduction of DNA rate Improved Theatre utilisation 3 Session Days/weekends Flexibility Extended Roles Short Stay Elective Surgical CentreFuture Service:
Short Stay Elective Surgical Centre Head and Neck Respiratory Physicians SSESC General Surgery Musculoskeletal Women & Children
Short Stay Elective Surgical Centre By Providing a redesigned /new SSECS • Optimise pre op assessment • Optimise Bed numbers • Optimise Theatre Utilisation • Optimise Recovery Room
Anticipated New Cases 3000 Short Stay Elective Surgical Centre
ST JOHNS: SHORT STAY ELECTIVE SURGICAL CENTRE & THEATRES UPGRADE PROJECT LAUNCH GORDON REID, PROJECT DIRECTOR
SSESC PROJECT LAUNCH • Ward 25 • Ward 19a • Residencies • Wards 5, 6 & 7 • Theatres
Communicating With St Johns Phasing Plans Weekly Liaison Progress Meetings NHS Lothian Daily Liaison
Phase 2 Contractor’s Work Area Site Set Up – 22nd March 2010 Start Works – 12th April Completed - 13th Dec 2010 Overall Duration 38 weeks Phasing and Segregation Existing Dry Riser Emergency Access to Dry Riser + Staff Fire Escape Routes Phase of future car parking Temporary Disabled Parking Phase 1 Contractor’s Work Area Heras Fencing Pedestrian Barriers Access Route Ward 25 Compound Compound And Work Area
Ground Floor Phase 1 Ward 2 Patients Move to Residents Block Ward 2 Move to Residents Block 12th April Construction Works Zone
Ground Floor Phase 1 – Ward 7 + Ward 6 Start: 12th AprilDuration: 35 weeks Complete: 13th December Existing Partitions to be Sealed Perimeter Scaffold Construction Works Zone Temporary Sealed Partition Bridging Scaffold Access Routes Access Stair Electric Hoist
Lower Ground Floor Phase 1- Ward 2 Works Start: 12th AprilDuration: 11 weeksComplete: 28th June Access Routes Construction Works Zone Existing Partitions to be Sealed Temporary Sealed Partition
First Floor Phase 1- Ward 15 Works Start: 12th AprilDuration: 11 WeeksComplete: 28th June Construction Works Zone
Lower Ground Floor Phase 1 - Ward 2 Upgrade Works Ward 2 Upgrade Works Start:7th June Complete: 28th June Duration: 3 Weeks Construction Works Zone
Lower Ground Floor Phase 1 Existing Ward 1 Moves into Existing Ward 2 Ward 1 moves to Ward 2 5th – 12th July Ward One Moves Into Ward Two Ward One Moves Into Ward Two