1. 4. 7. 6. 5. 18. 19. 8. 2. 3. 13. 11. 9. 10. 20. 12. 14. 16. 15. 17. Unit 1 Lay down Areas. 1- Contactor Parking 2- Contactor Parking 3- Duke Energy Employee Parking 4- Turbine Crew Trailers and Equipment 5- Turbine Crews 6- Turbine Crew and AGT (Entire Turbine Deck)
E N D
1 4 7 6 5 18 19 8 2 3 13 11 9 10 20 12 14 16 15 17
Unit 1 Lay down Areas • 1- Contactor Parking • 2- Contactor Parking • 3- Duke Energy Employee Parking • 4- Turbine Crew Trailers and Equipment • 5- Turbine Crews • 6- Turbine Crew and AGT (Entire Turbine Deck) • 7- Mobile Crane and Chemical Cleaning Tanks • 8- Turbine Crew • 9- Scaffolding lay down area • 10- SCR Prep Area • 11- Crane for APH AND Economizer work • 12- IRWIN trailer • 13- Contractor Entrance
Unit 1 Lay down Areas • 14- Scrubber Scaffolding Lay down • 15- Scrubber Contractor Parking (Limited) • 16- Contractor Expansion Joints lay down • 17- Fuel handling Building (Turbine Crew) • 18- Lay Down area for APH and Economizer • 19- NDE Trailer • 20- NDE and EDDY Current trailers