1 / 13

TS#5-2011 & Xmas break Activities foreseen

TS#5-2011 & Xmas break Activities foreseen. K. Foraz October 25 th , 2011 Go- nogo / LMC from LBOC. . TS#5-2011 (1/3). BE-ABP : Visit, preparation for Xmas, Scans BE-BI BTV - Matching monitors modification, if required following next MD results. For now nothing is planned.

lona
Download Presentation

TS#5-2011 & Xmas break Activities foreseen

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TS#5-2011 & Xmas breakActivitiesforeseen K. Foraz October 25th, 2011 Go-nogo / LMC from LBOC  LBOC - K. Foraz

  2. TS#5-2011 (1/3) • BE-ABP : Visit, preparation for Xmas, Scans • BE-BI • BTV - Matching monitors modification, if required following next MD results. For now nothing is planned. • BSRT - Remove Fast camera beam splitters on B1 and B2 • Maintenance and visit • BLM – diamond installation at points 1, 2 4 and 5 • BCT –Didt - Installation of new 2 channel hardware module. • LHC-BCTDC: Install new 24bits ADC on system A monitors. Check Set-up Beam Flag correct transmission at start-up • BE-OP • Quench propagation test – TBC • Measurements of Q7R3 • BE-RF : inspection and maintenance • EN-CV: Cooling tower maintenance, Chilled water for AHGU modification in RR5, Eletta exchange at point 8 • EN-EL : • OF - Campaign of measurements • UPS maintenance and battery exchange • OF - R2E P8 blowfibbers • OF - BIS P6 : repair • Cabling: FIP RADMON, R2E preparation, thermoswitchat point 5, BLM      LBOC - K. Foraz

  3. TS#5-2011 (2/3) • EN-HE: lift maintenance, PM45 HS from TS5 to mid dec., corrective maintenance on crane • EN-MME: Tomography in sector 34, Xrays • GS-ASE: new biometry at point 1 , safety and access system maintenance • IT • Modification of the power supply of BTS • Tests TETRA – SD8 • Foward detector: maintenance and checks • TE-ABT • Preventive maintenance • Corrective maintenance: TCDQ:  Bug fix, TMR exchange • Modification:  MKI - POC &SbS triggering logic •  MKI8 –FSC parallel bus driver circuit. •  LBDS -  Replacement 4 PNCcap35000-10pos • XPOC release in order to includes more detailed analysis on TSU Pt 2 en UA 23      LBOC - K. Foraz

  4. TS#5-2011 (3/3) • TE-CRG • Cryo valves consolidation • Cryo plant maintenance : Pt8 back on Friday & Pt 44 back on Thursday • TE-EPC: Corrective maintenance • TE-MPE • Upgrade of the DQAMC firmware for mitigation of SEU events. Locations: Cells from 23 to 34 • Replacement of power input switches on 308 further DQHDS Quench Heater Power Supplies • Replacement of thermostats on DQRB dump resistors • Adjustment / replacement of 600 A Energy Extraction Switches. • Removal of the remaining components used in the now obsolete Global Busbar Detectors • RQ4R6 – investigation on « potentiel » • TS-VSC • Visit, Xrays & maintenance • Remove thermocouple TDI.8R • Connectionof thermoswitchen 7L5     LBOC - K. Foraz

  5. Xmas - Schedule • Draft constraints schedule (available here) • Organization • WAT  IMPACT • General mode except at points 3 & 7 from Dec. 9th to beg. of February LBOC - K. Foraz

  6. Xmas – BE (1/2) • ABP • Installation of force gauges on IT motorized jacks LMC sep.14th • Deep reference measurements • Sector 78: measurement and alignment  LMC to come • Polygon connection @ pt1 and pt8 (or integration scan) • R2E (LS1): GGPSI installation in pt5 bypass • Linked to other activities: ZDC, BGI • BI (1/2) • Wire scanner repair @ point 4 • BSRT upgrade (beams 1&2): • Modifications of the optics • Installation of new shielding • BRAN:Remove BRAN scintillator (RP) • BTV: • Change cameras RAD • Replacement of dosimeters on BTV • Installation of new matching monitor on beam 2 • Rack migration towards UPS to prevent access and front end software configuration after a power glitch • Installation of injection matching detectors      LBOC - K. Foraz

  7. Xmas – BE (2/2) • BI (2/2) • BLM: • Tunnel crate backplane replacement to improve stability and remote control • Diamond installation at points 1,2,4 and 5 to measure beam losses • Replacement of signal cable to improve EMI • BPM: install cable adaptators where needed • BGI: replacement of the image intensifier • Maintenance: BPM, BTV. BPF, BLM • Linked to other activities: ZDC • OP • CSCM – TBC • Powering tests • RF • Maintenance • Klystron replacement     LBOC - K. Foraz

  8. Xmas – EN (1/2) • CV • Preventive maintenance • Ventilation measurements • EL • Cabling … a lot !!! • Motorized jacks, thermoswitch, R2E, BLM. Level 3 alarms, evcautaion. Collimation… • Water cooled cables control • Optic al fibers • Measurement campaign • Maintenance: UPS, 48V, 24V, lights • AUG • Point 2 consolidation: 48V and lift powering system • Transformer at point 8 for LHCb LBOC - K. Foraz

  9. Xmas- EN (2/2) • HE • Tests of the survey TIM • Maintenance: lift, crane, mobile shieldings… • PM45 lift • R2E: RB shiledingat point 1 • New shieldingaroubd QPS crate – TBC • MME • Tomograph (TBC) LBOC - K. Foraz

  10. Xmas - GS - IT • ASE • Maintenance: safety alarms, sniffers, EIS, ODH, access • New keys in Ujs • R2E: fire detection modification • Modification of the supports of ODH sensors (no stop) • Evacuation matrix • BIW modification (alim. 24V – temporized relays) • Consolidation at point 2 • Fire Brigade • Civil engineering • R2E at point 5 : drillings • IS: cleaning and organization • IT • R2E: displacement for RB shielding  LBOC - K. Foraz

  11. Xmas – TE (1/3) • ABT • For time being no MKI replacement at point 2 • Maintenance • CRG • Maintenance • R2E @ point 8: cryogenic power supply 230/24VDC • Cryo instrumentation: 2’000 cards to be exchanged – under discussion with powering tests • EPC • Maintenance • Replacement of 60A in sectors 78 and 81 • MPE (1/2) • ELQA (monitoring if possible) • Maintenance – tuning - operation • 13kA extraction switches • Adjustment/ Tuning of 600 A EE Switches • Removal from the Tunnel of Obsolete QPS Equipment LBOC - K. Foraz

  12. Xmas – TE (2/3) • MPE (2/2) • Replacement of the Power Input Switches on the Remaining DQHDS Quench Heater Power Supplies • Replacement of Thermostats on DQRB’s • Installation and Type Tests of the QPS Voltage-to-Ground Monitoring System • Firmware Updates: • DQAMS (600A EE)Uploading in the tunnel of the latest version of software for a number (200). • DQQDI and DQQBS Detectors • DQQDC and its associated DQAMG controllers • DQQDG-type A controllers for 600 A circuits • Installation of Radiation-Tolerant nDQQDI Detector Boards • Replacement of the Arc Chambers: Removal of the existing 240 V arc chambers on the 128 Extraction Breakers of the RQF / RQD circuits. Mounting and grounding of the new 1050 V chambers • MSC • Diode exchange in sector 56 • Thermoswitch – connectionunder discussion, but probably not      LBOC - K. Foraz

  13. Xmas – TE (3/3) • VSC • Beam vacuum: • Operation: ZDC, BGI, wire scanner, MKB, BWS • Inner triplet pumping LMC to come • pumping in one arc • Maintenance • Insulation vacuum: • New mobile pumping group in arcs • Primary pump replacement @ point 2 • Replacement of turbo pump at point 3 (DSL) – OK • Leak test on several sub-sectors (T>20K) • Auto-restart test LBOC - K. Foraz