An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TEAM: From Application to Obligation Entering your project application and getting all the right approvals

  2. TEAM:Tracks FTA program funds (non-administrative) • Where they come from (operating budgets) • Who they go to (recipients) • What they are used for (projects) • By Schedule (milestones) • By Activity (budgets) • Reservations & Obligations (promised & dedicated amounts) • Disbursements (payments)

  3. Project Types • Program Grants (Formula Program, New Starts, Capital Program) • Cooperative Agreements (Hire a contractor to do a project that has significant Federal Involvement) • Contracts/Procurements (Hire a contractor to do a project) • General Working Agreements (Volpe) • Inter-agency Agreements (Outside DOT) • Intra-agency Agreements (Within DOT)

  4. All FTA Projects Have… • A place on the FTA Program Plan or in a Concept Memo • An Approval Package (SOW, GCE, etc.) • A Project Record in TEAM (Application) • Project Information • Set of tasks to be performed • Budget • Schedule of activities

  5. Approval Package • Differ by project type (inter/intra agency, grant, procurement, etc) • Templates on FTANet/Electronic Forms/TEAM Forms • Includes: • Approval memo • Statement of Work • Government Cost Estimate

  6. TEAM Project Life Cycle TEAM Training: From Application to Obligation Project application created Project number assigned Signoffs and Approvals Operating budget money is reserved Project awarded Project award executed Project managed Project closed TEAM Training: Data Analysis TEAM Training: Project Management

  7. Creating the Project Application • Create New Application • Copy an existing project application • Amend an existing project application • Change in award or duration

  8. Parts of the Project Application • Project Information • program, costs, contact info, etc. • Budget • task details and their costs • Milestones • schedule of deliverables • Environmental Findings • required environmental classification • Fleet Status • discription of fleet changes

  9. Signoffs and Approvals • Assign Project Number • Review/Concur Dates • FTA Comments

  10. Submit the Application • “Paper” Application • FTA staff is entering the application in TEAM • “Electronic” Application • The recipient is entering the application in TEAM • “Signs” using a PIN

  11. Reserve the Funds • Find the right Account • Use oldest money first • Select Account Classification Code • Specify Financial Purpose Code

  12. Getting Help • TEAM Home Page • User’s Guide • Training Schedules • Activity Line Item Tree (ALI Codes) • TEAM Guidance-HQ • Approval Package Templates • FTANet/Electronic Forms/Team Forms (Linda Sorkin) • Team.HelpDesk@fta.dot.gov

More Related