1 / 31

Context Alternative design of DS collimators Pre-design 1 Pre-design 2 Favorite option

DS Collimators at IR3: mechanical engineering and design LHC Collimation Upgrade Review 08.07.2010 Alessandro Bertarelli , Alessandro Dallocchio, Delio Duarte Ramos, Luca Gentini, Christophe Mucher, Thierry Renaglia, Marc Timmins (EN-MME). Outline. Context

Download Presentation

Context Alternative design of DS collimators Pre-design 1 Pre-design 2 Favorite option

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DS Collimatorsat IR3: mechanical engineering and designLHC Collimation Upgrade Review08.07.2010Alessandro Bertarelli, Alessandro Dallocchio, Delio Duarte Ramos, Luca Gentini, Christophe Mucher, Thierry Renaglia, Marc Timmins (EN-MME)

  2. Outline • Context • Alternative design of DS collimators • Pre-design 1 • Pre-design 2 • Favorite option • WP scope and deliverables • Schedule and ressources (tentative) • Conclusions

  3. Work-Package Context • Reminder of work-package breakdown proposed by R. Assmann for the upgrade of the Collimation System: • Overall 70 WPs for 61+ units to be installed between 2012 and 2014. • 14 Dispersion Suppressor Collimators in DS of IR3, IR7 and IR2. • 4 DS Collimators in IR3 required for 2012 shutdown. • 10Phase 1 Collimators (TCP, TCSG) to be installed in IR3 in 2012 (combined Betatron/Momentum cleaning). • This presentation focuses on the engineering, design and manufacturing of 4 DS Collimators for IR3 (Ralph’s WP 15 and 18) !

  4. Technical Working Group • Kick-off May 2010. All concerned groups represented/invited (BE/ABP, EN/MME, EN/STI, TE/CRG, TE/MSC, TE/VSC, ….) • Assess the possibility to have 4 collimators installed at the end of 2012 shutdown at point 3. • Ensure that all system engineering issues related to the integration of the collimators in the LHC dispersion suppressors (DS) at point 3 are addressed. • Issue specifications for all implied technical systems (collimation, cryogenics, SC lines, vacuum, motorization/controls, interfaces, RP …).

  5. DS collimators: Specification • Functional Specification (Excerpts) (See V. Parma’s talk) • Main goal: gain a factor ~10 in (peak) power deposition on DS magnets (SC coils) both for protons and ions  • 1m long movable Tungsten jaw • 200 W max (during 10 s) per jaw. • Two jaws per collimator (because of back-scattering and positive DP/P for ions)  Major complication for Collimator design

  6. DS collimators: Alternative approaches • In principle two different technical approaches are possible for the design of DS collimators • Warm collimator with cold-warm transitions and cryogenic by-pass. • Cold collimator: jaws at cryogenic temperature (at ~ 80 -130K).

  7. Technical solutions: Pre-Design 1 Collimator external support Warm Collimator Cryo by-pass Cryo by-passjack Collimatorjack

  8. Technical solutions: Pre-Design 1 Vacuum Gate Valves (2 per beam line) X line Collimator actuation system Sliding space for W-bellows Pre-installed collimator support Beam pipe 2 Collimator with vacuum equipment Th . Renaglia M. Timmins L. Gentini

  9. Technical solutions: Pre-Design 1 Bus-bar fixed point Pre-formed bus-bar end In-situ formed bus-bar end Cold-warm transition Th . Renaglia

  10. Technical solutions: Pre-Design 1 Off-set actuating bellows M. Timmins L. Gentini

  11. Technical solutions: Pre-Design 1 Tungsten Collimator jaws Quad + Dipole Bus-bars (M1+M3) Quad bus-bars (M2)

  12. Technical solutions: Pre-Design 2 Cold mass External actuation system D. Duarte Ramos Ch. Mucher

  13. Technical solutions: Pre-Design 2 Cu/W Collimator jaws with embedded cooling pipe He heater (from 55K to >80K) D. Duarte Ramos Ch. Mucher Jaw cooling hose (from E-line)

  14. Technical solutions: Pros and Cons • Warm pre-design • Pros: • Design inspired by FP420 project (TR). • Mainly standard and known solutions. • Warm collimators decoupled from cryogenic by-pass (can be independently installed/removed) • Cons: • Dimensions (up to 4.5 m). • Intricate cryo-lines rerouting • More complex manufacturing (two separate objects): higher costs and times • Harder to accommodate in IR7 and IR2 (lack of space): new cold design required in 1,5 yrs? • Possible showstoppers: • No showstoppers found so far … • Cold pre-design • Pros: • Compact and simpler cryostat (~3.2m vs. 4.5m), not affecting cryo-lines (no re-routing) • Less components, shorter manufacturing times(?), less expensive construction (??). • Synergy possible with GSI/FAIR project??? • Cons: • New concept (Cu jaw at >~80K?), requiring cryo-cooling. • New design validation requires lot of testing. • More engineering resources needed. • Non-accessible collimator jaws (no in-situ repair or easy replacement). • Additional constraints to cryogenic operation. • Cooling circuit derived from E-line with active controls in cold and vacuum: reliability? • Possible showstoppers: • Beam vacuum operation at 100K. • Tungsten brittleness at low temperature. • Possible additional heat from RF heating.

  15. Technical solutions: Favorite option • In view of risk assessment, the favorite option is clearly pre-design 1 (warm collimator) • Main features and issues: • Up to 4.5 m long between interconnection planes • Vacuum equipment required (per beam line): sector valves, ion pump, vacuum gauges… • Bus-bar routing concept agreed with TE-MSC (complete on-site forming). • W-type bellows can be used as-is provided sector valves are partially dismountable. • Special cryostat and X-Line are non-dismountable. • Warm collimator can be installed and removed independently from cryogenic by-pass. • Lateral displacement (up to ~4.5 cm) (to be further verified for transport, integration etc.)

  16. EN-MME WP Scope and deliverables • Work-package for the engineering, design, manufacturing and assembly of 4 integrated DS Collimators (WP 15 + 18 from Ralph’s breakdown list) – Pre-design 1 • Starting date: July 2010 • Required inputs: • Successfully completed pre-study (no major showstoppers identified). • Go-ahead by this Technical Review. • Approved functional specification (BE-ABP, TE-MSC, TE-VSC, TE-CRG, EN-STI …) • WP deliverables: 5 (including 1 spare) complete units assembled and pre-tested (pressure, leak, torque, metrology …). • Not included in WP: • Supply of bus-bars and splices, motors, sensors, vacuum equipment, cables … • Final collimator assembly (motors, cables, sensors, supports – WP26 EN-STI), electric tests, cold tests (TE-MSC), transport and installation.

  17. TCRYO wp1: Tentative SCHEDULE • Schedule assumptions (pre-requisites) • Functional specification is frozen in July and no modifications occur afterwards. • All required resources are available. • Material procurement starts immediately after review go-ahead. • Externally manufactured components (in particular bus-bars and BB ancillaries) are made available on time (~May 2011). • Collimator production and test facilities at b.100 and b.112 are set up on time (Is b. 252 lab really lost for good?) • Reliability of all workshop production machines is assured. • Test equipment not owned by EN-MME (e.g. motor torque-meters) are made available. • … No unexpected showstoppers are found on the way …(this is still pre-design!)

  18. TCRYO wp1: Tentative SCHEDULE • Preliminary planning (no safety margin)

  19. TCRYO wp1: Estimated ressources • Estimated Personnel for TCRYO WP1: 36 FTE (14 Eng&Des, 22 Prod), including staff, FSU and outsourced personnel (mainly for Production, partly for Drafting).

  20. TCRYO wp1: Tentative SCHEDULE • Some considerations • The planning does not take into account final assembly and tests (EN-STI, TE-MSC, TE-VSC) (experience with Phase 1 Collimators is 1 month EN-STI plus 1 week TE-VSC)  ready for installation ~2 months after ex-works. • A production readiness review is to take place in June 2011 to give green light to installation in late 2012 / early 2013. • Work sharing with other groups to be fine-tuned (ex. measurements with EN-STI, bus-bar tooling with TE-MSC ….) • Additional Phase 1 collimators (6 units) and components for other Phase 2 WPs to be produced in parallel by EN-MME.

  21. Conclusions • Two alternative solutions (cold and warm) were pre-studied by TCRYO WG: best option is the warm solution. • No major technical showstoppers were identified for warm solution. • EN-MME WP scope is to manufacture 5 complete units (final assembly and cold tests excluded). • Manufacturing of 4 complete units seem feasible by end of 2012 (with no contingency), provided specification is frozen and procurement starts now. • Production Readiness Review to be held in June 2011. • Estimated Personnel for TCRYO WP1: 36 FTE, including staff, contract personnel and outsourced personnel.

  22. Thank you for your attention!

  23. Bonus Slides!

  24. Cryo-collimators: Pre-Design 1

  25. Cryo-collimators: Pre-Design 1

  26. PHASe2:EN-MME Probable Contribution

  27. WP Context: EN-MME required contribution • EN-MME as WP owner

  28. TCRYO wp1: Material procurement • Preliminary list (non exhaustive) of components to be urgently procured

More Related