1 / 19

Stage 4: Termination and Closure

Stage 4: Termination and Closure. April 30, 2003. Complete Testing. Testing should constitute 30-45% of any new product development project Module and regression testing were completed in the previous stage Just the final system test and acceptance testing is done here.

louise
Download Presentation

Stage 4: Termination and Closure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Stage 4: Termination and Closure April 30, 2003

  2. Complete Testing • Testing should constitute 30-45% of any new product development project • Module and regression testing were completed in the previous stage • Just the final system test and acceptance testing is done here

  3. Obtain signature Signoffs • From customer • From stakeholders

  4. Get paid • Contractually, you need some legally binding arrangement that legally obligates the customer to pay

  5. Contract types • Fixed price • Contractor assumes all of the risk • Contract must produce a specific deliverable within a specific time for a specific price • Cost Reimbursement • Also known as “Cost Plus” • These are the extremes • There are many possibilities between these two

  6. Cost Reimbursable Contracts • Cost plus incentive fee (CPIF): the buyer pays the seller for allowable performance costs plus a predetermined fee and an incentive bonus • Cost plus fixed fee (CPFF): the buyer pays the seller for allowable performance costs plus a fixed fee payment usually based on a percentage of estimated costs

  7. Cost Reimbursable Contracts • Cost plus percentage of costs (CPPC): the buyer pays the seller for allowable performance costs plus a predetermined percentage based on total costs

  8. Time and Material Contracts • Commonplace in information technology • Are a hybrid of fixed price and cost reimbursable contracts • Contractor is reimbursed for specific performance (time), and for his material costs

  9. Contract Types Versus Risk

  10. Statement of Work (SOW) • A statement of work is a description of the work required for the procurement • Many contracts, or other mutually binding agreements, include SOWs • A good SOW gives bidders a better understanding of the buyer’s expectations

  11. Statement of Work (SOW) Template

  12. Sell the next project to the Customer • Especially if the previous contract was a fixed price one • And, there was a lot of “Wouldn’t it be really neat ifs…” after the project began execution

  13. Hold formal-post project meeting (Post-Mortem) • Discuss what went well • Discuss what went not so well • Discuss what could be improved

  14. Document Lessons Learned • How could we have managed better? • What would we do next time?

  15. Populate history database • For task durations, especially • Or, to be used to verify task durations

  16. Notes on shortening project durations • This must be done in the Planning and Budgeting stage • Crashing • Reducing the duration of tasks on the critical path • Fast-tracking • Starting tasks sooner • Adding resources • Checking for parallelism opportunities in the schedule • Removing Safety

  17. More techniques for shortening projects • Scrub the requirements • Remove from the requirements those items that add little or no value • Remember the Pareto principle—80% of the value comes from 20% of the functionality

  18. That’s IT folks!!

More Related