1 / 6

SubjecTech: Optimizing Test Design for Future Projects

Learn from past issues in test PVSs to avoid delays in subjective testing labs. Detailed schedule for upcoming ITU meetings and data verification process by proponents.

lschwarz
Download Presentation

SubjecTech: Optimizing Test Design for Future Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RRNR-TV (September 2008 Ghent)

  2. Proponents • NEC • NTIA • KWILL • Yonsei

  3. ILG • CRC

  4. Subjective Test Design • Source selection: by CRC • Test design: by CRC • We had a number of unexpected problems with the test PVSs, resulting in substantial delays. Cares should be taken for future projects.

  5. Subjective Test Lab • NEC - 525 • NTIA - 625 • KWILL – 625 (NHK) • Yonsei - 525 • Each lab do the subjective test with exactly 16 evaluators (after screening) and the data from the same format will be combined. • Some screening procedures will be applied to the subjective data to exclude problematic evaluators.

  6. Schedule (tentative) • Finalization of the test PVSs: done • Subjective test: 15 Oct. • Objective data submission: 10 Oct. • Verification of objective data: 24 Oct. • Data analysis: 31 Oct. • Draft of the final report: 30 Nov • ITU meeting: ITU-R 6C (May 2009), ITU-T SG9 (Feb. 2009, tentative) • Note: the verification of objective data will be done by the proponents.

More Related