An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COAL FIRED POWER PLANT TRAINING JAPAN INTERNATIONAL COOPERATION AGENCY (JICA)2007 DIRECTORATE GENERAL FOR ELECTRICITY AND ENERGY UTILIZATION 2007

  2. THE TRIP

  3. ABOUT THE TRAINING Carried Out By : - Japan International Cooperation Agency (JICA) - Japan International Cooperation Center (JICE) - Japan Electric Power Information Center (JEPIC) - Hiroshima International Centre (HIP)Sponsored By :- Chugoku Power Electric Company (CEPCO) - Mitsubishi Heavy Industries (MHI)Training Centre :- The Power Enegineering & Training Service Co.Ltd (PET)Location : - Hiroshima - Tokyo - Nagasaki - Ube

  4. JAPAN HISTORY Ashikaga Bakufu Ashma Desease Tokugawa-Meiji transition Minamata Desease World War I 1945 2007 1960 1995 World War II Miracle Periode Decline of the Tokugawa 500 % of Economic Growth Selama periode 30 tahun

  5. JAPAN ELECTRIC POWER SECTOR HISTORY First Japan’s Boiler 0% Economic Growth 300 Electric Company 10 Electric Company 2005 2000 2007 World War II Miracle Period Beginning of Power Electric Sector Resrtructurization First Mitsubishi Steam Turbine Generation to Distribution Deregulated ( ≥ 500KW) 100 % Deregulated Free Electric Market MBMS

  6. ELECTRIC POWER SECTOR INDUSTRY

  7. INSTALLED CAPACITY 2007

  8. THERE ARE 10 ELECTRIC POWER COMPANY (ALL PRIVATE SECTOR) 60 Hz 50 Hz

  9. JAPAN NATIONAL • GRID CONNECTION • 500 KV • 275 KV • DC 1000 KV • (TODAY IT USED FOR 500 KV) Training Location

  10. ELECTRICITY DEMAND OUT LOOK • Year 2007 : • Installed Capacity : GW • -Available Capacity : GW • Peak Load : GW

  11. Base Cost Production USD 5 Cent ENERGY BEST MIX 2007 USD 5 Cent USD 5 Cent USD 5 Cent USD 5 Cent

  12. DAILY LOAD CURVE DSS Daily Start Up-Shut Down Non DSS Daily Start Up-Shut Down

  13. POWER ELECTRIC SECTOR REGULATION • The Electric Utilities Industry Law (Law N0. , 1990) • (Undang-undang Ketenagalistrikan) • Pneumoconiosis Law (Law No. 30 of March 31, 1960) • (Undang Undang tentang kesehatan buruh) • Labour Standards Law (Law No. 49 of April 7, 1947) • (Undang-undang Ketenagakerjaan) • - Industrial Safety and Health Law (Law No. 57 of June 8, 1972) • (Undang-undang tentang Keselamatan Kerja) • - Working Environment Measurement Law (Law No. 28 of May 1, 1975) • (Undang-undang tentang Lingkungan Kerja) • - Industrial Accident Prevention Organization Law • (Ministry of Labour Ordinance No. 118 of June 29, 1964) • (Peraturan Menteri tentang Kecelakaan Kerja) • Law concerning the Rational Use of Energy (Law No.49 22 June 1979) • Undang-undang tentang pemanfaatan energi

  14. REGULATION ON ENVIRONMENTAL • - Environmental Impact Analysis (AMDAL) • - Noise (Undang-undang tersendiri) • NOx • SOx • Dust • Heavy Metal Environmental Standard value (Air)

  15. EMMISION STANDARD VALUE

  16. Outline of Selective Catalytic Reduction Atmosphere Dust collector NH3 injection nozzle Air preheater Boiler Desulphurization equipment Air Chimney Denitration reactor Gas, gas heater FDF Ammonia dilutor Liquidized NH3 reception unit Flash back inhibitor Carburetor Accumulator NH3 tank Steam Flue Gas Denitration System Flow Diagram

  17. REGULATION ON SAFETY • Safety Assesment • Licensed Auditor (pointed by METI) • The Electric Utility Industry Council

  18. REGULATION ON ENERGY CONSERVATION AND ENERGY EFFICINECY

  19. ENERGY SAVING LABELLING

  20. POWER ELECTRIC SECTOR RESTRUCTURIZATION (BY FY 1995)

  21. PARTIAL LIBERALIZATION BY (FY 2000)

  22. FULL LIBERALIZATION (BY FY 2007) • 100% market competition, every electricity company • effort the lowest rate ($/kWh) • Fixed Installation, change of electricity provider did not • replace the installation. • Fixed payment methode • Electricity Stock Exchange

  23. ELECTRICITY MARKET STRUCTURE

  24. TERIMA KASIH THANK YOU