Water Plant #3 Concentrate Pre-treatment Project. Regulatory Requirements: Wtp#3 has a discharge permit limit for iron of 0.3 mg/L Wtp#3 Concentrate is greater than 0.3 mg/L FLDEP AO 154NE provides a schedule to meet the iron discharge limitation
E N D
Regulatory Requirements: • Wtp#3 has a discharge permit limit for iron of 0.3 mg/L • Wtp#3 Concentrate is greater than 0.3 mg/L • FLDEP AO 154NE provides a schedule to meet the iron discharge limitation • Concentrate is permitted as a source water at Wtp#1 • Color compliance at Wtp#1 is dependent on color reduction treatment by ozone treatment at Wtp#3 Water Plant #3 Concentrate Pre-treatment Project
Process Components: Primary System • Ozone system for color reduction • Recovers up to750,ooo gals/day Secondary System • Cartridge filtration system for iron reduction Water Plant #3 Concentrate Pre-treatment Project
Water Plant #3 Concentrate Pre-treatment Project Funding: • Total Project Cost - $1,580,000 • Design & Permitting - $162,345 • Construction Cost including contingency - $1,407,680 • Source of Funds: 5 Year CIP bond funds • SJRWMD Cooperative Cost Share Grant - $494,800 • Florida Legislative Funding Grant - $375,000 (waiting for Governor’s signature)