Customer Survey Timeline for PHAs with Fiscal Year End 6/30/07. PHAs document & certify Implementation Plan activities via the Internet March 22 – April 12, 2007. PHAs update & certify public housing unit addresses in PIC via the Internet March 5 – March 21, 2007. PHAs access
E N D
Customer Survey Timelinefor PHAs with Fiscal Year End 6/30/07 PHAs document & certify Implementation Plan activities via the Internet March 22 – April 12, 2007 PHAs update & certify public housing unit addresses in PIC via the Internet March 5 – March 21, 2007 PHAs access survey results via the Internet July 26, 2007* PHAs promote the survey to Residents using the Media Plan Guidelines March 22 – April 12, 2007 PHA Residents surveyed May 1 - July 3, 2007* Required PHAs certify via the internet that a Follow-up Plan will be developed with next Annual Plan August1 – August 17, 2007* *Dates subject to change due to contract negotiation delays. Timeline updated 2/07/2007.