An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DEVELOPING CAPITAL INVESTMENT PLANS

  2. Outline • Identify Services and Needs • Asset Inventory • Gap Analysis and Project Selection • Project Substantiation • Project Prioritization • Capital and O&M Cost Estimating • Draft Capital Plan and Plan Approval

  3. What Is Capital Planning? The process will help communities…. • Understand and identify service related infrastructure needs… • Provide a clear vision for administration to follow • Allow greatest number of important needs to be met

  4. Identify Services • Good quality of life for citizens • What services to deliver? • Is the service affordable? • Infrastructure required to deliver services?

  5. Identify Services • Water and sewer delivery/pick-up, • Solid waste storage and pick-up, • Road maintenance, • Recreation program, etc…

  6. Identify Needs • What’s more important…good roads or recreation facilities? • What infrastructure is a must for communities? • Is it important to link infrastructure needs to community service?

  7. Identify Needs • Immediate Needs • Grader engine blows • Predictable Growth Need • Population results in lot development • Future Needs • Community interest in a new facility • Facility replacement requirements Identify Services and Needs

  8. Identify Existing Assets • Asset inventory should include: • Buildings & Contents • Mobile Equipment • Water/sewer/solid waste infrastructure • Roads/Bridges/Signs

  9. Identify Existing Assets Infrastructure Information Sources: • NORCIX Information (Bldg and ME) • Community Infrastructure Assessment • PW&S Water Systems Review Inventory

  10. Asset Useful Life • What is the remaining life of your: • arena? • office building? • mobile equipment ? • What affects the useful life of an asset?

  11. Identify Gaps ??

  12. Identify Gaps • Identify Infrastructure Gaps • Identify Projects Identify Projects

  13. Ensure Compatibility Consider… • How all projects are connected to existing infrastructure. • The O&M implications of new infrastructure or betterments.

  14. Ensure Compatibility • Consider affects of new infrastructure on old. • Will new water truck fit in garage? • Will granular stockpile be ready for lot development? • Can new pool use heating system from arena? • Do assets need to be disposed of?

  15. Project Substantiation • How Much • When Of your project…… Project Substantiation Documenting the: • What • Why • What • Why

  16. Project Prioritization What project outweighs another? • Health and Safety vs Community Development …balance • Water Plant or Youth Centre? • Road Development or Library?

  17. Project Prioritization Sample Criteria to assess projects… • Health and Sanitation • Wellness • Basic Safety Needs • Legal Requirements • Project Need/Urgency • Public Support Prioritize Projects

  18. Develop Capital Cost Estimates • Capital Infrastructure Cost Estimating • Several methodologies used • Varying degrees of accuracy • Capital Equipment Cost Estimating • Use marketplace including factors such as: • Freight • Pre-delivery inspections • Custom Specifications, etc…

  19. Develop Capital Cost Estimates • General rule: • As project approaches implementation the accuracy of the estimate increases.

  20. Cost Estimating • A, B, C, D Class Cost Estimates • Class D: Accuracy 30-35% • Preliminary approval • Class C: Accuracy 20-25% • Planning, definition of project requirements, approval • Class B: Accuracy 10-20% • Approval,budgetary control, design cost control • Class A: Accuracy 5-20% • Evaluate tenders for cost control during construction

  21. Cost Information Resources • Capital, O&M, and Energy • GNWT - MACA and PWS • Engineering - Consultant or through planning study • Power - NWT Power Corp. • Construction - Historic values, NWT Construction Association. • Mechanical servicing/inspections - Past invoices • Tools/supplies - Catalogues/Internet

  22. Total Cost of Capital • Capital • Initial purchase or construction cost • Operations and Maintenance • Maintenance and repair (per yr) • Staff Time (per yr) • Fuel, Power costs (per yr)

  23. Cost Estimates (Capital & O&M) Example – Grader Capital Cost = 250 K (Initial Purchase) O&M Cost = 30 K (Annual) Energy Cost (Fuel) = 10 K (Annual) 6yrs of O&M = Initial Capital Cost example

  24. Project Substantiation Documenting the: • What • Why • How Much • When Of your project…… Project Substantiation

  25. Identify Funding Sources • New Deal provides opportunity for innovation. • Local property taxation revenue now an option. • Be aware of all of potential funding sources: • Territorial • Federal • Municipal – FCM

  26. Identify Funding Sources • Corporate Contributions • Green Project Grants • Identify Capital Reserve in Budget

  27. Feasibility Check • Are projects achievable considering all factors? • Is their enough O&M funding to sustain the asset? • Capital Policy includes section on Feasibility.

  28. Draft Capital Plan • Take the priority project list and fit into a plan. • May have to move/drop projects to future years. • Decisions will need to be made. • What needs to be done now and in the future?

  29. Cash Flow Projects • Fit projects into available budget. example

  30. Project Substantiation Documenting the: • What • Why • How Much • When Of your project…… Project Substantiation

  31. Plan Approval • Typically SAO presents to council for approval. • Consultant and other staff may assist if required. • Opportunity to discuss and address “minor” issues.

  32. Plan Approval • Consultation complete. • This is your approved working capital plan.

  33. Next Steps - 20 Year Forecast • Capital Plans - focus on 1 to 5 years. • Larger plans will include future years (up to 20) • Maps out longer term plan for community. • Delayed projects can be kept on plan.