Nodal Transition Plan Options

Nodal Transition Plan Options. Credit Work Group May 28, 2008 Cheryl Yager. Overview. Goals for determining exposure during transition Zonal settlement calendar Nodal calendar Components to consider Transition Options Considered Other transition options to consider?.

luella
Download Presentation

Nodal Transition Plan Options

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nodal Transition Plan Options Credit Work Group May 28, 2008 Cheryl Yager

  2. Overview • Goals for determining exposure during transition • Zonal settlement calendar • Nodal calendar • Components to consider • Transition Options Considered • Other transition options to consider?

  3. Goals for determining exposure during transition • Ensure that collateral held during transition matches risk • Not too much • Not too little • Use general rules that are understandable and reasonable to implement • Be adaptable • If the general rules don’t fit a company’s circumstances, use flexibility to ensure collateral held matches risk

  4. Zonal settlement calendar • Nov 20 (Thurs) – invoice with Oct 31 – Nov 6 initial data • Dec 1 (Mon due to Thanksgiving) invoice with Nov 7-13 initial data • Dec 4 (Thurs) – invoice with Nov 14-20 initial data • Dec 11 (Thurs) – invoice with Nov 21-27 initial data • Dec 18 (Thurs) – invoice with Nov 28-30 initial data - partial • EALs can be calculated at each of these dates

  5. Nodal calendar • Dec 1 (Mon) – RT market goes live • Dec 7 (Sun) – first DAM auction • Dec 9 (Tues) – first DAM settlement statement and invoice • Dec 11(Thurs) – first RT settlement statement • Dec 18 (Thurs) – first RT invoice with Dec 1–4 settlement statements - partial • Dec 29 (Mon due to Christmas) – second RT invoice with Dec 5-11 settlement statements • Jan 2 (Fri due to New Year’s) – third RT invoice with Dec 12-18 settlement statements It will be Dec 29th or Jan 2nd before ERCOT will have enough information to have a complete calculation for the CMM system • The transition period is effectively the month of December 2008

  6. Components to consider

  7. Transition Options Considered • 1 Import detailed invoice / settlement data from Zonal and calc collateral in CMM system Benefit • CMM system begins adding data as it is available • AIL calculates effectively with an ADTE Drawbacks • Don’t necessarily want zonal “data” in CMM system • Would have to “adjust” off activity since payments from Zonal invoices aren’t brought over to CMM system

  8. Transition Options Considered • 2 Use the IEL functionality in the new system • Calculate the EAL from Zonal invoices and enter in CMM system as IEL Benefit • Sets a “minimum” level of collateral through transition • Establishes an estimate of Zonal run-off liability • CMM system begins adding data as it is available Drawback AIL won’t have an ADTE, which may overstate liability unless manually adjusted

  9. Transition Options Considered • 3 Estimate Zonal “run off” liability (combo of EAL and NLRI, adapted – updated weekly) and have CPs estimate RT activity for Nodal to establish an ADTE Benefits • Establishes an estimate of Zonal run-off liability • CMM system begins adding data as it is available • AIL calculates effectively with an ADTE Drawback • Historically, actual use of BES in an initial period is generally higher than initial estimates of use of BES given to ERCOT

  10. Transition Options Considered • 4 Use ADTE and EAL/NLRI from Zonal Benefit • Zonal calculation is known and documented • CMM system begins adding data as it is available • AIL calculates effectively with an ADTE • Establishes an estimate of Zonal run-off liability Drawbacks ?

  11. Transition Options Considered • 5 Some combo of options 2 and 4- Use IEL as a minimum and ADTE for the AIL component Benefit • Sets a “minimum” level of collateral through transition • CMM system begins adding data as it is available • AIL calculates effectively with an ADTE • Establishes an estimate of Zonal run-off liability

  12. Other transition options to consider? • ERCOT staff is leaning toward something like Options 4 or 5, but is open to other ideas on how to handle the transition period and would like input from CWG. • Will work out a more detailed plan and timeline once we narrow down approaches • ERCOT staff recognizes that any particular method used for transition may not fit all Counter-Parties and that adjustments may need to be made.