Project: IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs) Submission Title: ULP TG Closing Report San Diego, CA, USA Date Submitted: July 2014 Source: SS Shahriar Emami , Samsung 75 W Plumeria Drive, San Jose, CA, USA
E N D
Project: IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs) • Submission Title: ULP TG Closing Report San Diego, CA, USA Date Submitted: July 2014 • Source:SS ShahriarEmami, Samsung 75 W Plumeria Drive, San Jose, CA, USA Abstract: Closing report for the ULP TG Session Purpose: Overview of activities during the meeting Notice: This document has been prepared to assist the IEEE P802.15. It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further stu dy. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein. Release: The contributor acknowledges and accepts that this contribution becomes the property of IEEE and may be made publicly available by P802.15. Shahriar Emami, Samsung
San Diego, CA July 2014 July 2014 ULP TG Closing Report Shahriar Emami, Samsung
July 2014 Sessions • Total of 5 time slots • - PM2 on Monday • - AM1 on Tuesday • - PM2 on Wednesday • - AM1 and AM2 on Thursday Shahriar Emami, Samsung
Achievements • Sought and received comments in reference to the draft • Reviewed all comments • Prepared comments/resolutions list • Planned for weekly conference calls Shahriar Emami Samsung
Work Plan • BRC will meet on a weekly basis • All the received comments to be addressed in the ballotable draft • Ballotable draft will be ready by early August Shahriar Emami, Samsung
Weekly Teleconferences • Every Wednesday until end of 2014 • 8:00AM PDT, 20:30 PM IST, 17:00 PM CET, 12:00 AM KST Shahriar Emami, Samsung
WG Motion • Move that 802.15 WG approve the formation of a Ballot Resolution Committee (BRC) for the WG balloting of the 802.15.4q draft standard with the following membership: Shahriar Emami, Allan Zhu, Frederik Beer, Hendricus De Ruijter, CHANDRASHEKHAR THEJASWI PS, Kiran Bynam and Youngsoo Kim. The 802.15.4q BRC is authorized to approve comment resolutions on behalf of the 802.15 WG. Comment resolution between sessions will be conducted via reflector email and via teleconferences announced to the reflector at least 30 days in advance. • Moved by: Shahriar Emami Seconded by:
July 2014 Timeline (1) • Preliminary work • - Call for applications Dec 2012 • - Applications presentations Jan 2013 • - TGD outline March 2013 • - TGD, applications and channel modeling contribution call March 2013 • - Review TGD contributions May 2013 • - TGD Ongoing & review application contributions July 2013 • Proposal effort • - Call for intent July 2013 • - TGD completed Sep 2013 • - Call for proposals Sep 2013 • - Proposal presentations Nov 2013 • Drafting • - First draft May 2014 Shahriar Emami, Samsung
Timeline (2) • Ballotable draft Aug 2014 • Balloting • - WG letter ballot Aug 2014 • - First recirculation Sep 2014 • - Conditional approval of sponsored ballot Nov 2014 • - Sponsor ballot Jan 2015 • - First recirculation March 2015 • - Conditional approval to submit to Revcom March 2015 Shahriar Emami, Samsung