An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Substation L1/ Booster Substation Y-BE2Update #3 August 15,2012

  2. Status of Procurement • Substation L1 • Transformer fully tested • Delivery expected in 1-2 weeks • Pictures of completed substation will be sent prior to shipment • Booster Transformer Y-BE2 • RFP placed early August • All proposals due by 8/31/2012 • Temporary Wiring • 350 MCM cable is hung and wired for temporary panel board • Other temporary wiring will begin towards the end of August • Panelboard • 1 assembled • 1 needs to be assembled

  3. Status of Procurement (Cont.) • Safety Switches • Delivered • Temporary installation will begin late August • Cable Supports • Delivered • Installation will occur late August to early September • Junction Box • Built • Will be shipped with substation

  4. Substation Pictures

  5. Substation Enclosure

  6. Project Schedule • September 17-28 • General Cleanup 2-3 weeks prior to shutdown of substation • Temporary electrical power will be completed the weekend prior (September 15th) • It could take riggers several days to remove and install substations • Small clearances • Large weights • Discussions are underway to move forward with cutting a hole in LINAC’s roof • Contractors will be in this week to give a cost estimate

  7. Temporary Power Plan • “Siphon” power from panel DHP-L2-2 Circuit #1 • Cable will be run on temporary supports • 4 conductor 350 mcm cable is heavy (~7 lbs./ft.) and will need an open area to lay • Some cable will be put on the floor but will be covered by a cable bridge • Setup 2 temporary panel board(s) • Run cable to individual loads • DHP panels, MCC loads • DHP panels will have potentialhazards removed (mains, MCC, etc.) • 13.8 kV lines will be disconnected • MCC loads will have configuration control locks • We will check current prior to using any MCC loads to ensure they will not trip off during operation • Power will be provided 24 hours a day

  8. Installation Costs • 1 Crew of Riggers (4-6 men) • Could be as much as $30k • Will remain unknown until a finalized roof plan is put in place • 2 Week of Electricians • $100/manhour x 2 electricians x 80 hours = $16,000 • Cable • 2/0 - $3,500 • 2 – $3,700 • House Power • $4,200 for panelboard • $2,000 for assembly • Miscellaneous Stock purchases • $2,100 Total Cost : $31,500 -> excluding rigging and roof Previous Estimate: $23,000 -> excluding rigging and roof Increase can be attributed to increased electrician time and panelboard cost

  9. Future PIP Project ???? • Create Site Wide Monitoring Network PIP Project PIP Project HQ Note: CG-1 has been moved from PIP schedule, and will now be handled by headquarters

  10. Booster Y-BE2 Update • Replaced bad transformer • Working well • Decreased noise • Less heat • New transformer RFP • Estimated cost of $150k • Expect bids by end of August • Procurement will begin within 30 days of receiving bids • Will likely be much quicker • Install • Early next year • Several days