1 / 13

Planned HV Projects for the Amajuba District Municipality

Planned HV Projects for the Amajuba District Municipality. Simphiwe Ngwenya. Geographical Layout. Eskom’s HV Infrastructure Within The DM. HV Projects. Kilbarchan 88kV Substation

maalik
Download Presentation

Planned HV Projects for the Amajuba District Municipality

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planned HV Projects for the Amajuba District Municipality Simphiwe Ngwenya

  2. Geographical Layout

  3. Eskom’s HV Infrastructure Within The DM

  4. HV Projects Kilbarchan 88kV Substation Due to long network lengths, voltage limits have been reached with very little ability to optimally distribute power. Studies done on the networks indicate the need to migrate from 11kV to 22kV distribution voltage. Project need date 2014-2015

  5. HV Projects Clontarf 88kV SS Clontarf SS is an 88/11/22 kV Substation. It has one 7.5MVA 88/11kV transformer and one 2.5MVA 11/22kV transformer. The original station was built in 1974 and is now 34 years old. Project need date 2015-2016

  6. HV Projects Rutland 33kV SS Rutland SS will experience loading constraints on the 33kV in feed. This substation has undergone a capacity upgrade to 2X10MVA 33/11kV transformers. Plans to convert Rutland to an 88kV SS are being investigated. Mining supply will be used as the trigger for the HV voltage upgrade. Ikwezi Mine project need date 2014-2015 Slater Coal project need date 2014-2015 Ikwezi Slater Coal

  7. HV Projects Madadeni 132kV Conversion Madadeni/Osizweni township is supplied from Ingagane substation. Need date 2012-2013 Madadeni SS to supply Mabuya Mall Need Date 2015-2016 Matsheketsheni SS Est(deload Blaauwbosch and Vlaklaagte) Need Date 2015-2016 Blaauwbosch SS increase Capacity from 2*10MVA to 2*20MVA Need Date 2012-2013 Parklands SS 132/11kV injection to supply 5.5MVA(Meadowlands Development) Complete

  8. HV Projects Kipspruit SS relocation Project need date 2013-2014 Ingagane Utrecht 88kV Line Conductor Upgrade

  9. HV Projects Ruston 88kV Substation Reliability project raised to increase capacity at the Sub. Project need date: 2014-2015

  10. Summary Of Projects

  11. Electrication(Madlangeni and Newcastle)

  12. Cont’d…Electrification(Danhauser)

  13. THANK YOU

More Related