PARS Activation Readiness Maintenance Mid-Florida P&DC. 237. Participate in Site Survey for CFPS/CFS. 238. Clear space for Scanner Installation for CFPS. CFS NE corner prepped and wired for new Scanner, OSW, and KFP workstation.
E N D
238. Clear space for Scanner Installation for CFPS CFS NE corner prepped and wired for new Scanner, OSW, and KFP workstation.
239. Make required changes at CFPS site: * Electrical Power - Relocate & move equipment as needed for timelines. Wire for CIOSS #1 & #2 * Mechanical - Base line equipment * Telecommunications. - MPI wiring, new FCS & Firewall
246. Develop plan for: Installation/Modification of electrical and mechanical in P&DC- CIOSS Power requirements- CIOSS Communication drops- Baseline MPE
242. Identify and Schedule target group of employees for specific Maint. - Training Trained Scheduled DBCS 12 3 DBCS/EC 3 5 DBCS/DIOSS 6 3 CIOSS - F.A.T. A+ Comp. Fund. 2 3 Network + 1 1 ? MPI Wiring 5 (on-site)
243. Determine Site Prep Funding Requiredfor P&DC- all FAT team items submitted & approved by HQ Finance for allocation of funds for CFD Admin Service procurements
PARS FAT Verification Items - HQ QA- Verif. Rm- Del. Ops- Siemens- Siemens- Visitors
243. Determine Site Prep Funding Required for P&DC-Additional P&DC site prep funding requested for: - Maintenance prep workhours 2,542 hours - Power and Communication drops - Materials for equipment moves $21,300
245. Place order for spare parts cabinets, if required. - Order stockroom cabinets as needed- Remote hot spares cabinet in CFS
247. Prepare / Update Maintenance Staffing Plan. -Change positions for PM window and tour. -Post ET job: 0500-1350 N/S: Sat/Fri-Will Complete Daily & Senior PM windows
249. Develop an SOP for updating PARS software / In MOS Cabinets. • All PARS software and directory updates will be setup in VMARS for Daily, Weekly, and Monthly routes. • Will follow RBCS procedures. • Assigned to T-2 ET positions. • Software will be stored in the Maintenance software cabinet and at the VMF according to the Crisis Management Plan.
Directory Updates • Local Updates From Plant’s RIC • Generated From CFPS Scanning of COA Cards • P&DC CARS Systems Only • Daily Updates From NCSC (Electronically) • All Local COA Updates Bundled Together • Updates on Universal Mailer File (UMF) • Directories • Bitmap Exclusion Table • Weekly Updates (DVD From NCSC) by an ET • National Change of Addresses • Directories
251. Develop a Process and Schedule for performing weekly PARS database updates. - During Daily PM window, 5:00 - 9:00- Senior PM Routes will be Sunday CIOSS#1 and Monday CIOSS#2
250. Develop an Escalation procedure for CFPS Scanner Mechanical / Electrical failures. -Call contractor Bell & Howell-24hr Warranty contract* OSW scanner requires optics cleaning
252. Identify any Article 32 issues and work with Labor Relations to resolve. -NONE-All MPE moves and Power/Comm drop nearly completed.
253. Coordinate maintenance schedules with new Processing Operations Operating Plan. -New ET Bid. BT: 0500-0150-N/S: Sat/Fri- CFS FFTs available: 01:00 - 12:30
254. Contractor finalizes asbestos disposal plans/activities with District Environmental compliance Coordinator and appropriate local landfill authorities, etc., as required by local, state, and or national codes.- NONE
255. Establish Stock-Rotation / climitization plan for CIOSS labels. -Will Follow existing procedure currently in place for CFS FFT labels
256. Develop SOP for Waste Mail. -Follow existing procedure currently in place with Custodial workforce.-Waste volumes still generated within CFS workroom-Waste containers staged in CFS/CIOSS verification area
259. Train Custodial workforce on new Waste Mail Procedures.- Completed as part of FAT operations(from CFS & CIOSS waste verification workarea)
257. Clear space in P&DC for equipment delivery and modification.-Complete and Ready for CIOSS Modification [ Ray Oakley ]
DBCS #11, ready for the CIOSS modification Workroom floor ready for 25’ addition
258. Receive install Team Tool Kits, sign receipt for them upon delivery, and place them in a secured maintenance area around PARS equipment location.- East end of CIOSS machine
Mail Processing Equipment modifications for PARS processing:AFC = Replace hardware STP with PC software STP- start Friday, Aug 22nd @ 06:00 (4)OCR = New computer software STP- start Saturday, Aug 23rd @ 06:00 (3)DBCS = Replace PC, monitor, cards and firmware- start Wednesday, Aug 20th, 07:00 (15)MPBCS = New software loaded- start Tuesday, Aug 19th @ 07:00 (6)Final Modification completed on Sept 6th for last DBCS (#12)
New CIOSS LAM Module • Two High Speed Label Applicators (HSLA) • One Label Verifier • Two Vacuum Turbine Units • One Doubles Detector (DD) • One Other Side Reader (OSR) • One Change Of Address Scitex Ink Jet Printer (COA IJP)
High Speed Label Applicators • Two HLSA Per CIOSS • Speed of Three Meters Per Second • Each HLSA Can Produce 15,000 Labels Per Hour • Provides Status • Almost Empty Indicator • Empty Status Indicator
Scitex Ink Jet Printer • Prints Up To Seven Lines of Information • Process 30,000 PPH • Expensive Ink Cartridge • Limited Life Span
PARS MAJOR COMPONENTS • Redirection Image Controller (RIC) • Advanced Forwarding Reader (AFR) • Change of Address Record Server (CARS) • Forwarding Storage Unit (FSU) • Change of Address Forms Processing System (CFPS) • Change of Address Reporting System (COARS) • PARS Video Coding Desks (VCD)
260. Provide or confirm the Transmission Control Protocol/Internet Protocol (TCP/IP) address for PARS equipment to the contractor install team (unless provided at Site Survey) * completed * MPI wiring * Firewall installation
261. Update VMARS to reflect changes due to PARS. -Develop routes for CIOSS.-Input Spare Parts into VMARS.
264. Complete inventory of spares kits and advise Site Coordinator of status. 265. Inform contractor of any missing spares parts.