1 / 51

Buried Duct Network for Upgrading Utility Cables – Recent Field Trials

P. C. S. Outside Plant Consulting Services, Inc. Buried Duct Network for Upgrading Utility Cables – Recent Field Trials. 2009 AASHTO Right of Way & Utilities Subcommittee Conference Oklahoma City April 20, 2009. Dr. Lawrence M. Slavin Outside Plant Consulting Services, Inc.

madison
Download Presentation

Buried Duct Network for Upgrading Utility Cables – Recent Field Trials

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. P C S Outside Plant Consulting Services, Inc. Buried Duct Network for Upgrading Utility Cables – Recent Field Trials 2009 AASHTO Right of Way & Utilities Subcommittee Conference Oklahoma City April 20, 2009 Dr. Lawrence M. Slavin Outside Plant Consulting Services, Inc. 973-983-0813 lslavin@ieee.org www.outsideplantconsulting.com

  2. Sponsor • Funding: • US Department of Transportation • Technical Oversight: • FHWA Turner-Fairbank Highway Research Center

  3. Objectives & Goals • Short-Term: • Develop improved method of buried construction for utility cables (telecommunications, CATV, power) • Long-Term: • Avoid damage to roads and transportation systems • Minimize proliferation of utility poles

  4. Background

  5. P C S Cable Construction Methods • Overhead Utility Poles • Below ground • Underground conduit • Direct-Buried

  6. P C S cables placed directly in trench

  7. P C S Direct-Buried Philosophy • Cables directly placed in trench • Robust cable designs • electrically insulated (power, ...) • waterproof • mechanical protection (armor, …) • Sized for “ultimate” future needs

  8. Direct-Buried Philosophy • Typically, no convenient means of cable addition, replacement or upgrade* * Sometimes a duct is provided in trench by a utility, but is not a uniform practice across all utilities and regions, or necessarily done in the most cost-effective manner

  9. P C S Direct-Buried Philosophy • Does it usually work (successful) ? • Often (in use for several decades) • Does it always work ? • No • new technology • exhausted capacity • cable degradation or damage • new service providers

  10. P C S Direct-Buried Philosophy THUS • Cable additions require aggressive construction (open-cut trenching, directional drilling, …) • Possible damage to roads, property, utilities, ... • Safety hazards

  11. Buried Duct Network (BDN)

  12. P C S Benefits • For buried facilities (requiring future upgrades, maintenance, …), avoids • Road damage (road cuts, ...) • Corresponding traffic delays • Damage to buried lines (gas*, electric,…) • Damage to Intelligent Transportation System (cables, …) * e.g., US DOT - Office of Pipeline Safety

  13. Benefits • Consistent with AASHTO & FHWA Recommendations* • Belowground lines • Access and Upgradability • Joint Usage of Infrastructure & Facilities * A Policy for Accommodating Utilities Within Highway Right-of-Way, A Policy on the Accommodation of Utilities Within Freeway Right-of- Way, Guidance on Sharing Freeway and Highway Rights-of-Way for Telecommunications, Highway/Utility Guide.

  14. P C S BDN Concept/Design • Hybrid system; combines • Advantages of underground conduit (upgradability) • with • Advantages of direct-buried construction (low cost)

  15. BDN Concept/Design Specify standard, optimized, cost-effective Buried Duct Network: • Initially installed distribution cables are selected, sized and directly-buried in joint-use trench, following present recommended (cost-effective) practices • Two large diameter (e.g., 4-in.) main distribution ducts, initially vacant, accessed at common handholes, also placed as an overlay in the same joint-use trench

  16. P C S BDN Strategy* • Add minimum duct network for insurance for atypical (but not uncommon) cases when need upgrade • Consistent with shared/joint-usage philosophy • Space-efficient • Cost-effective • * Does not apply to applications that warrant full-scale underground conduit systems (e.g., banks of conduits, manholes, …)

  17. Note: for thoroughfare application, possibly omit service lines common (joint) service trench utility terminals/equipment/hardware (power, telephony, CATV) three individual service ducts power handhole tele CATV common (joint) main trench along ROW two vacant large (e.g., 4-in.) ducts through handhole initial distribution cables (direct-buried, w/o duct) initial primary power distribution cables (direct-buried, w/o duct) patent pending BDN Detail

  18. Not to Scale 6 knockouts (both sides) flared sides (avoid uplift -- frost, duct, …) lid mouseholes (e.g., 4-in. duct) bottomless patent pending (Nominal 2 ft. wide x 3 ft. long x 36+ inches deep)

  19. initial distribution cables (direct buried, w/o duct) e.g., communications (telephone, CATV) handhole two vacant main ducts (HDPE, PVC, …) (future distribution cables) e.g., power (primary and/or secondary) express duct (alternative) cut/sealed duct same (joint) trench patent pending Direct-Buried Initial Cables plus Vacant Main Ducts thru Handhole

  20. P C S BDN Concept/Design • Main distribution ducts are initially vacant • Future Use of main distribution ducts efficiently allocated, as necessary (telephone, CATV, power) • Individual, smaller diameter, service wire ducts are routed from terminals to residence or small business, to provide protection for initial service wires, and facilitate future upgrade or replacement

  21. P C S BDN Concept/Design • Handhole NOT intended for routine maintenance (no terminals, splices, ... ) -- avoids exposure of communications workers to high voltages • Accessed only if and when the need arises for future addition of cable(s)

  22. Alternatives

  23. P C S

  24. P C S

  25. P C S

  26. Phase I (Feasibility) 6 Months

  27. Phase II (R&D) 24 Months

  28. P C S Phase II Effort • Develop design, construction, maintenance, and management guidelines and practices • ASCE Pipeline Division • “ASCE Manual of Practice for Belowground Pipeline Networks for Utility Cables” • Anticipated availability Summer 2009

  29. P C S Phase II Effort • Ensure availability of prototype hardware for future applications, field trials, ... • Handholes (load ratings, ...) • Ducts, conduits • Security system (locks, …) • …..

  30. Handholes (TIER 15) Polymer Concrete (Quazite®)

  31. Handholes (“20K”) HDPE (Pencell Plastics)

  32. P C S Phase II Effort • Arrange appropriate full-scale field trials • Permanent installation • e.g., 1 kft • Road, highway, residential, … • Identify & address various issues • Leverage for future introduction into utility and transportation industry practices

  33. P C S Phase II Effort • Completed or planned field trials • Arlington, Texas – November 2008 • Monroe, NC – March 2009 • Danvers, MA – June 2009 • ........

  34. Monroe, NC • Road Widening SR1223 (NCDOT) • Moving Verizon and Time Warner Cable • Outer edge of ROW • Tier 15 handholes (NC DOT) • Open-cut trenching • Conventional PVC (adhesive joints) • 1 kft (<800 ft.) • Conduits (and innerduct) for future (and initial) cables

  35. Monroe, NC Thanks, Gus !

  36. Handhole Locations for Verizon BDN /Time Warner Installation (Monroe, NC) 30” x 48” x 36-in deep handholes (Quazite PG3048) 36” width trench Verizon equipment/pedestal  390 ft.  330 ft. two 4-in. conduits (e.g., Schedule 40 PVC) 2 Time Warner Cable innerducts (outside handholes) Time Warner Cable mini-vault increase trench width in vicinity of handholes initial Verizon cables through one conduit All conduits plugged at all exposed ends Not to Scale

  37. Trench Cross-Section for Verizon BDN /Time Warner Cable Installation (Monroe, NC) surface two 4” (Verizon) conduits pull rope  36” fiber cable + pull rope fiber cable + 600 pr copper cable (+ vacant path ?) 36”+ two 2” (Time Warner Cable) innerducts, including tracer wire Not to Scale

  38. Martin Luther King, Jr. Blvd (SR 1223)

  39. Trenching & Conduit/Handholes video

  40. Installed BDN Conduit & Handholes

  41. Time Warner Cable Direct-Buried Innerduct video

  42. Installed Innerduct

  43. Backfilling & Compacting video

  44. Backfilling & Compacting

  45. Finishing video

  46. Finishing

  47. P C S Phase II Effort • Implementation issues • Ownership • Joint-usage agreements (compensation, …) • Road and construction permits • ...

  48. HOW YOU CAN HELP

  49. P C S How You Can Help (Permits, ...) • Encourage (require ?) use of upgradable networks (BDN, other, ...) • Stricter specifications • Uniformity (across states, ...)

  50. P C S How You Can Help (Permits, ...) • Suggestions • Existing related efforts ? • Individual states ? • Nationally ? • How to proceed ? • .......

More Related