1 / 14

14 th LIU-SPS Coordination Meeting

14 th LIU-SPS Coordination Meeting. Update on the renovation of the 200 MHz RF system . Cavities redistribution. 2011 : 4 cavities 2 x 4 sections 2 x 5 sections + 3 spare sections. 2018 : 6 cavities 2 x 4 sections 4 x 3 sections + 1 spare section.

maegan
Download Presentation

14 th LIU-SPS Coordination Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 14th LIU-SPSCoordination Meeting Update on the renovation of the 200 MHz RF system

  2. Cavities redistribution • 2011 : 4 cavities 2 x 4 sections 2 x 5 sections + 3 spare sections • 2018 : 6 cavities 2 x 4 sections 4 x 3 sections + 1 spare section Courtesy of Elena Shaposhnikova 14th LIU-SPS Coordination Meeting

  3. First upgrade: Present amplifiers Tetrodes: Present lifetime statistics, operating ~650 kW cw: RS2004 : 20’000 hrs : 6 tubes per year YL1530 : 25’000 hrs : 16 tubes per year HVPS need a full re-cabling and air cooling improvement to allow higher pulsed mode It is planned to do ‘pre-modifications’ during next Xmas stop and to test new configuration during a devoted MD in 2012 14th LIU-SPS Coordination Meeting

  4. New RF power plant • New RF Amplifier • New RF Building • LSS3 Tunnel integration New RF Building 1 mW 1.7 MW RF amplifier Coaxial transmission line 150 meters 1 mW 1.7 MW RF amplifier Accelerating cavity Accelerating cavity 14th LIU-SPS Coordination Meeting

  5. 1.7 MW amplifier, i.e 1.4 MW cavity • To have 1.4 MW available at the cavity input, 1.7 MW at the Final output are needed • A major improvement to present systems would be to have individual SSA drivers per PA • Taking advantage of the long experience we have with tetrodes and combiners, the solution will be 16 x PAs combined through 3 dB combiners • Four contracts : • Drivers (SSA) • Finals (SSA or Tetrodes) • Combiners (3 dB above 100 kW) • Transmission lines (coaxial, 345 mm outer) From Beam Control 1/16 splitter Drivers 16 SSA Final 16 PAs 1.7 MW -0.6 dB total 3 dB combiners and power loads 1.5 MW 120 m and 180 m Coaxial lines -0.2 dB 1.4 MW To cavity input 120 m away 14th LIU-SPS Coordination Meeting

  6. 2018 : two new power amplifiers • Pulse mode: 1.7 MW max (10 µs / 43 kHz) • Average: 850 kW (thermal limitation) • Must be reliable: • 24/24 hours • 300/365 days (2 months winter Technical stop AND a 1 day stop every 8 weeks) • Minimum 20 years of operation, (3 years of operation + 1 year off cycle) • Qualified solution must have demonstrated to be reliable underscientific operation (not only broadcast operation) • 2 x 1.7 MW Klystron • 2 x 4 x 450 kW Diacrodes • 2 x 8 x 225 kW IOTs • 2 x 8 x 225 kW tetrodes • Equivalent to ‘Siemens’ • 2 x 16 x 106 kW tetrodes • Equivalent to ‘Philips’ • 2 x 2048 x 830 W SSA • Equivalent to ‘SOLEIL’ 14th LIU-SPS Coordination Meeting

  7. 16 Tetrodesvs 2048 SSA • Tetrodes tube costs over 20 years will be added : • 20 years * 3/4 * 335 * 24 * 16 * 2 = 3’859’200 total hours • With 20’000 hours per tube = ~ 200 tubes • SSA : • + 20% to 25% additional transistors (not module) • Individual circulators are mandatory • Wall plug efficiency will be part of the adjudication • HVPS included (Tetrodes) • Losses in all SSA combiners, circulators and loads included 16 x 106 kW Tetrodes 16 x 128 x 830 W SSA 1.7 MW 14th LIU-SPS Coordination Meeting

  8. SSA vs Tetrodes • First contract : SSA Drivers • Two options : • 16 x 1.1 kW • 16 x 1.1 kW x 8 • Second contract : Finals • Two options : • 16 x 1.1 kW + SSA • 16 x 1.1 kW x 8 + Tubes • KT too difficult and too long to be involved • No SSA prototyping • DRs done (Drivers and Finals) • Two MS expected by end of 2011 • Drivers IT March 2012 • Finals IT September 2012 • Taking into account Drivers 14th LIU-SPS Coordination Meeting

  9. New RF building • Only possible location is between two existing buildings (BA3 and BB3) • Maximum ‘RF’ foot print will be 2x450m2 • Whatever the solution, SSA or Tetrodes, the same building • Some difficulties with BB3 transformers (Oil vs Cast resin; 12 Tons vs 24 Tons) • New place is being agreed • Distance between BA3 air ventilation and new building at its minimum 14th LIU-SPS Coordination Meeting

  10. Transport area 2011 2013 2360 LSS3 - LSS3 + 14th LIU-SPS Coordination Meeting

  11. LSS3 Tunnel integration : LS1 ? • Three new cavity sections : ~ 3 years • Measure • Build new devices • Proceed to power tests • New power couplers : ~ 4-5 years • More power and shorter -> new design • Prototyping and tests (resonant ring) • Series and pre-conditioning of 24 couplers + spares • New amplifiers : ~ 5 years • New building • Long duration tests • Impossible to re-arrange cavities within LS1 • Clean old cables in 314 and 321 • Move pickups in 314 and integrate new kicker in 321 • Install coaxial transmission lines 14th LIU-SPS Coordination Meeting

  12. Draft schedule Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 2011 2012 2013 2018 2014 2015 2016 2017 Cavities re-arrangement within a LS ( > 6 months) RF : Studies (amplifiers, couplers, cavities) Tendering MS Build new hardware Install Tunnel : Studies Commissioning Build New hardware Installation phase 2 (cavities + pickups + CV + EL + vacuum) Installation phase 1 (pickups + dampers + EL + coax lines …) Building: Studies Authorizations Building Services Services 14th LIU-SPS Coordination Meeting

More Related