Introduction to Materials Management. Chapter 3 – Master Scheduling. The Master Schedule is:. The formal link between production planning and actual production The basis for calculation of resources needed The driving force behind the material requirements plan

mahdis
Download Presentation

Introduction to Materials Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Introduction to Materials Management Chapter 3 – Master Scheduling

  2. The Master Schedule is: • The formal link between production planning and actual production • The basis for calculation of resources needed • The driving force behind the material requirements plan • The primary priority plan for manufacturing

  3. Information Needed to Develop an MPS • Production Plan data • Forecasts • Actual customer orders • Inventory levels • Capacity constraints

  4. Relationship to Production Plan

  5. Objectives and Steps for the MPS • Objectives – • Maintain good customer service • Make effective use of resources • Maintain effective levels of inventory • Accomplished by: • Develop a preliminary MPS • Check MPS against capacity and resources • Reconcile any differences

  6. MPS Example

  7. Rough-cut Capacity Planning • Establishes whether critical resources are available • Bottleneck operations • Critical labor resources • Critical material • Often uses a resource bill for a single product

  8. Example Resource Bill

  9. Master Schedule “Focal Points” • Make-to-Stock – Limited end products, many components • Make-to-Order – Many end products, fewer components • Assemble-to-Order Many end products, combination of components and subassemblies

  10. Example MPS Environments

  11. Final Assembly Schedule • Assembly according to customer schedule • Generally used in an Assemble-to-Order environment • Many options • Too many possible final configurations to forecast or master schedule • MPS usually done at the option level

  12. MPS, FAS and Other Planning Activities

  13. MPS Planning Horizon • Minimum time horizon over which the master schedule must extend to ensure complete planning • Calculated as the longest end-to-end lead time of the product structure

  14. EXAMPLE - Cumulative Planning Horizon • For this product – Minimum Planning Horizon 12 weeks

  15. Delivery Promises • MPS is a plan for what production can and will do • Sales delivery promises can be made from • “Consumption” of forecasts – Projected available balance • Available to Promise calculations • MPS values for a given time period left after actual customer orders are subtracted.

  16. Available to Promise Example

  17. Projected Available Balance • Within demand time fence (forecast not taken into account) • PAB = Prior period PAB + MPS – customer orders • Outside of demand time fence • PAB = Prior period PAB + MPS – greater of customer order or forecast

  18. Example of MPS with ATP and PAB (Demand time fence at end of week 3)

  19. Time Fences • Points in the planning horizon to define the flexibility allowed in the MPS • Frozen Zone (closest to current date) • Capacity and materials committed to customer orders, forecast generally ignored • Senior management approval for changes • Slushy Zone • Less commitment of materials and capacity • Tradeoffs negotiated between marketing and manufacturing • Liquid Zone – All changes allowed within limits of the Production Plan

  20. Time Fences