Working package Port assembly Uwe Schultz (in representation for Falk Kunkel). Port. Plasma vessel (PV). Outer vessel (OV). Standard Ports (267 pieces). Round Ports: 171 pieces in 13 sizes Oval Ports: 85 pieces in 10 sizes
E N D
Working package Port assembly Uwe Schultz (in representation for Falk Kunkel) Working package Port assembly
Port Plasma vessel (PV) Outer vessel (OV) Standard Ports (267 pieces) Round Ports: 171 pieces in 13 sizes Oval Ports: 85 pieces in 10 sizes Rectangular Ports: 11 pieces in 1 size Special Ports (32 pieces) - Complicated cross section or: - Port pipe irregularly shaped or: - Doubel port, combination of two individual ports (10 pieces) 299 Ports on W7-X Working package Port assembly
Port- Position on W7-X - Ca. 20% of Ports are to be assembled from bottom - Ca. 20% of Ports are to be assembled from top - Ca. 20% of Ports are to be assembled from the inner side - Ca. 40% of Ports are to be assembled from the outer side 600kg 400kg 1000kg to 600kg Working package Port assembly
Cross-beam,frame Port-Assembly Ramp Port Assembly Bridge KS I x; y; z Cross-beam, Platformin maximum position Vertical y-z-plane Theoreticalport vector +/-1° Rotation basic component Rotation shaft 360° Translatory movement of trajectory +/- X mm Translatory movement of carrier 2400mm Rotation trajectory 120° +/-5° Base assembly group function IV +/- 140mm Base assembly group functions I-III Horizontal plane KS II x‘; y‘; z‘ External tower,frame Rail system Internal tower, frame Internal tower, Platformin maximum position External tower, Platformin maximum position Working package Port assembly
Contour pick-up port assembly with dummy Step I Step II Step III - Set up port vector from CAD data - Configuration check with PV hole - Final 3D measurement of flange plate - Marking of laser references in torus hall an PV - Scribing of hole contour on dummy head - Disassembly of dummy - Disassembly of dummy head Step IV • 3D Measurement of PV hole contour • on paper from dummy head • Production of CAM data to cut 3D contour • halfway inside wall of PV (-8.5mm contour shift) • - 3D cut to required length for port Dummy head with 3D cut contour Uncut port 3D cut port Step V Step VI Step VII - Assembly of port in same mounting position as used for dummy - Check of port vector after assembly using laser references of torus hall and PV - Place port in final position - Measure this position - Tack weld port on PV and OV - Full penetration welds - Final measurement of port position Working package Port assembly
Module 5 on Assembly stand (AST) with travelling Port Assembly Bridge inside Torus hall • Port Assembly Bridge: • Engineering structure consisting of Internal tower, External tower and Cross-beam • Particular Platform (travelling and lockable) • Bridge travels on Rail system, can be moved over module • Track curve segments of Rail system are dismountable • Rotational axis runs through Machine centre point Machine fundament (MF) Track curve segments on floor ceiling and base platform (inside MF) Module 5 Ceiling Base platform Working package Port assembly
Status of Port- Assembly Ramp by AN/ Fantini (Okt. 2007) Working package Port assembly