An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UK Project Finance & Schedule

  2. Overview Finance • Budget Forecast Presented last OsC • August Finance – submitted in Report • Budget for FY 2013/14 • Forward look to complete step VI – flat cash • Resource loaded forward look to complete step VI Schedule • Installation to step IV

  3. Budget Setting for FY 2013/14 • This budget has been revised downwards yet still allows delivery of all major items & infrastructure for step IV operation. • Staff costs have been reduced in the following work packages: • Project management office • Hydrogen system • Operations & Analysis – management and systems experts • Fixed costs reduced in the following:- • Hydrogen System • Operations & Analysis • Options are being considered to reduce this overspend of 7.4%

  4. Options Considered to Reduce Overspend • Saving Option 1 • Don’t build the new rack and control room • Disadvantages • Worked for some considerably time to get agreement from ISIS for this not to go forward this yr • Cooling Channel Control Racks will have to go behind North wall for step IV then re-routed to the new rack room for step VI. Effectively doing the electrical installation twice • Staff morale will be low • Staff costs have been reduced further in the following work packages: • Project management office • Hydrogen system • This option reduces overspend to 1.9% • OsC advised that agreement with ISIS for this space was a priority • Saving Option 2 • Cease work on RF work package – Plan to miss the TIARA milestone • Disadvantages • TIARA income of £35k this yr until end December to demonstrate RF power operational in MICE hall. Would not be able to use this income. • Damaged reputation of STFC • Staff costs have been reduced further in the following work packages: • Project management office • Hydrogen system • This option reduces overspend to 4.7% • OsC last advised that project item discuss with STFC to see whether there could be any flexibility • Project Sponsor agreed that MICE can run with ~8% overspend – to be reviewed in September 2013.

  5. MICE Finances – August 2013 Income:- External Common Fund:- £88k TIARA - £33.75k EUCard:- Assumed same as last yr £34k Encumbrances:- £35k Negative Variance £86k – 5% • Encumbrances to be invoiced FY 2013/14 to avoid carry over. • Large order in place for infrastructure work £151k - Magnetic Field Mitigation wp. Due to be receipted in Feb 2014 – need to monitor. • Staff OTL bookings being monitored • There was an error in the finance report ....now fixed, above the updated figures

  6. MICE Finances – WP Spend Summary August 2013 • Work Package spend summary to date includes projected spend for FY13/14 • University staff allocation coast split between rolling grant & project – £823k • STFC staff allocation £639k • Non staff costs £1132k

  7. Submitted Capital Request At the request of STFC the project team have provided a list of capital items that could be advanced should resources become available.

  8. Forward Look Spend to Step VI • Assumes flat cash allocation • Some levelling still to do for 2017/18 onwards • Proposed delivery of RFCC#2 will means an allocation will be needed in 2019/20 Draft! Work in progress

  9. Forward Look Staff Costs to March 2016 Draft! Work in progress

  10. Forward Look Non-Staff Costs to March 2016 Draft! Work in progress

  11. Operations Management Structure Needs additional resources to deliver this structure

  12. Resource Loaded Forward Look Spend to Step VI • Assumes resource requirements positions are filled to deliver and operate MICE • Essential resources:- • Experimental Co-ordinator • Possibly jointly funded position with UK university • Integration Scientist • P. Hanlet (IIT) • Operations Team Leader • Lab staff … reporting line through Laboratory as safety critical • Cryo expert • Mark Tucker (PPD); presently 50%. Need 100% with full experiment • Magnet expert • Lab staff … reporting line through Laboratory as safety critical • Work in progress: • Full analysis includingexplicit WM and contingencyin preparation.

  13. Schedule Overview • Schedule now includes PRY following recommendations of the Magnetic Field Mitigation review panel. • All compressors will be installed on the West Wall. Compressors will not be installed until August 2014. • Magnet power supply and control racks will be installed in new rack room with full agreement of ISIS. • Schedule identifies tasks with risk element & associated risk delay. Work in progress!! • SS’s & Tracker’s assembled in R9 then moved to MICE Hall. • Spectrometer Solenoids & Trackers, installed in series due to limited resources. • Magnet training only begins after cooling channel and PRY is installed (this includes EMR, KL & TOF). • 15 weeks total for all magnet training after cooling channel is installed.

  14. Step IV schedule – Shipping • RF system - TIARA • RF distribution equipment delivered TH116 installed, outstanding item is the water panel • Upstream Spectrometer Solenoid - Delivery imminent • AFC #2 – Delivery imminent • EMR - Delivered (Risk)-(R1) 80day delay (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  15. Step IV schedule – R9 Pre Installation Work (Risk)-(R1) 80day delay (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  16. Mechanical Integration Work in Hall • Relocating compressors to West Wall involves a lot of work • Mezzanine structure, services, supports • Means we need to make other Hall modifications • South mezzanine air con, stairs, crane, existing west wall services • Includes New Rack Room – space agreed with ISIS

  17. Step IV Installation • Magnet training of SS begins after cooling channel is installed (this includes EMR, KL & TOF) • 15 weeks total for all magnet training after cooling channel is installed. • Step IV completion now -  end Jan 2015

  18. Step IV schedule – Critical Path (Risk)-(R2) 40day delay (Risk)-(R3) 20day delay (Risk)-(R4) 10day delay

  19. Step IV schedule – Critical Path 27/10/15 30/1/15 • Assumes South side PRY available mid April • Assumes North side PRY available mid July – but not installed until mid September • Critical path driven by West Mezzanine Wall and compressor installation • Magnets cooled in September 14 • Magnet training can only take place only after full PRY is installed

  20. Schedule Summary • Critical path driven by West Mezzanine Wall and compressor installation • Further work required to identify & quantify risks. • Initial estimated cost:- £372k • £500k & 5man yrs effort UK our estimate in risk register • Assumes delivery of South PRY mid April 14 and North PRY mid July 14 • North PRY not installed until September 14 • Risk Delay – assumes we incur all identified delays • Schedule & risks need to be monitored as these will change