1 / 14

Evanston Slow Zone Remediation

Evanston Slow Zone Remediation. CTA Track Maintenance April 22, 2013. Today’s Presentation. Background Project Scope and Benefits What to Expect Tentative Project Schedule Track Renewal Process Efforts to Lessen Community Impact. Background. Originally constructed in 1908-12

maili
Download Presentation

Evanston Slow Zone Remediation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Evanston Slow Zone Remediation CTA Track Maintenance April 22, 2013

  2. Today’s Presentation • Background • Project Scope and Benefits • What to Expect • Tentative Project Schedule • Track Renewal Process • Efforts to Lessen Community Impact

  3. Background • Originally constructed in 1908-12 • Track last renewed in 1976 • Typical useful life of 25 years • Currently over 6,700 feet (16%) of track-related slow zones

  4. Project Scope & Benefits • Goal to mitigate slow zones until a major renewal is funded • Selective track & spot tie renewal • Project Duration: 7 Months • Work will occur under single tracks on nights and weekends • Over 6000 ties replaced • Customers will experience a smoother, faster ride

  5. Project Scope & Benefits

  6. What to Expect • Sunday through Thursday night work occurring between 9PM and 4:30AM • Weekend daytime work between 7AM and 7PM • Noise as work occurs • Work zone lighting • Minor delays to service and boarding changes during single track operation • Regular track maintenance will continue weekdays 9AM – 2:30PM

  7. Tentative Project Schedule Construction Notices will be distributed to adjacent properties before work begins in each area.

  8. Track Renewal Process • Tie handler • distributes new ties • cleans up old ties

  9. Track Renewal Process • Tie inserter • Removes old ties • Inserts new ties

  10. Track Renewal Process • Production Spiker • Drives spikes into ties

  11. Track Renewal Process • Ballast cars • Drops new stone ballast to fill in the track

  12. Track Renewal Process • Ballast Regulator • Distributes and shapes new stone ballast

  13. Track Renewal Process • Production Tamper • Sets track alignment • Tamps (compacts) stone ballast • Creates a solid, smooth ride

  14. Efforts to Lessen Community Impact • Pre-construction coordination meetings with Evanston city officials • Biggest, most disruptive work will occur in spring and fall • Structured work shift so that loudest work occurs before midnight • Biggest production will occur on weekends during the day • Presentation to City Council members outlining project scope and schedule • Distribution of construction activity notices prior to beginning work in a given area • CTA Contact: Ryan Mouw, rmouw@transitchicago.com

More Related