1 / 18

Desalination Becomes A Reality In Tampa Bay Florida

Desalination Becomes A Reality In Tampa Bay Florida. Jim Jensen Senior Project Manager PB Water Area Manager Parsons Brinckerhoff Quade & Douglas, Inc. San Diego NBWA Water Conference April 2, 2004. Institutional. Tampa Bay Water regional water wholesaler Owns all significant wellfields

maire
Download Presentation

Desalination Becomes A Reality In Tampa Bay Florida

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Desalination Becomes A Reality In Tampa Bay Florida Jim Jensen Senior Project ManagerPB Water Area Manager Parsons Brinckerhoff Quade & Douglas, Inc.San Diego NBWA Water Conference April 2, 2004

  2. Institutional • Tampa Bay Water regional water wholesaler • Owns all significant wellfields • Regional distribution system • New surface WTP • Member governments • Hillsborough, Pasco & Pinellas counties • New Port Richey, St. Petersburg & Tampa • Operate their own WTPs • Retail water distribution systems

  3. Why Desalination Is Needed In Southwest Florida • Years of drought • Overpumping from concentrated wellfields • Environmental stress to wetlands and lakes

  4. SWFWMD Required Reduction In Wellfield Withdrawals • Average of 158 MGD pumped in 1998 • Settlement required reduction in pumping to 121 MGD in 2003 • Further reduction in pumping to 90 MGD by 2008

  5. Master Water Plan • $610 million capital improvement plan • Aggressive water conservation program • Skimmed surface water stored in above ground reservoir • Desalinated seawater • Desalinated brackish water • Limited new groundwater sources

  6. Water Master Plan Requirements • Diversified and sustainable • Limited new groundwater ( reduced total groundwater withdrawal) • Drought resistant • Reasonably priced

  7. Seawater Desalination Procurement Process • Desalinated water supply 20-35 MGD • Board initially not fully committed • Tampa Bay Water did not own a site • Developer responsible for water delivery system to point of connection • Design, Build, Own, Operate, Transfer • Co-funded capital costs by SWFWMD

  8. PROPOSALS • All 5 Pre-Qualified Developers Submitted • Approximately 23 options and alternatives submitted • Three sites proposed • MED, MVC and RO process • Power plant intake and discharge canals used

  9. ANCLOTE POWER PLANT Florida Seawater Desaliantion Company Progress Energy/Ionics HIGGINS POWER PLANT1 Progress Energy Ionics BIG BEND POWER PLANT Enova/SSI2 Florida Water Partners Stone and Webster 1 Higgins Power Plant was eliminated from further consideration. 2 Enova/SSI was not selected for further evaluation. Proposed Desalination Site Locations

  10. Power Plant Co-Location • Shares intake and outfall with power plant once through cooling water system • Tie in to power plant discharge pipeline on land • Increase in temperature increases production of desalinated water • Bay water salinity less than open seawater

  11. Tampa Bay Desalination Facility

  12. Desalinated Water Quality • Meets all local, State and Federal drinking water standards • Chloride maximum 100 mg/L (partial second pass) • Lime added to prevent corrosion • Disinfectant added to prevent biological growth in delivery pipeline

  13. Seawater Concentrate Disposal • 16.7 MGD concentrate mixed with 1,350 MGD cooling water flow = 70:1 • Blended discharge increase ~2% at canal discharge point • NPDES Permit minimum blending ratio 20:1 (1 of 4 generators operating)

  14. Public Acceptance • Extensive public information and education program from proposal process through construction • Public Service Announcements • Editorial Board Presentations • Open House presentations/ Q&A • Focus Groups • Homeowner’s Associations, etc. • 70% Favorable for desalination • Concern about environmental impact • NIMBY

  15. Plant Operational Status • Began water production in March 2003 • Excessive fouling problems • Did not pass Acceptance Tests • Operational and other changes reduce fouling, operational costs still to high • Production averages 22.5 MGD in February 2004 before shutdown for repairs

  16. Plant Institutional Status • Covanta notified of termination of O&M contract in October 2003 • Covanta files for bankruptcy delaying repairs and termination • Board nominates Interim Operations, Maintenance and Management firms • American Water Services/Pridesa • Ionics/Montgomery Watson Harza • Veolia Water (USFilter Operating Services)

  17. Desalination Is A Reality In Tampa Bay • Pretreatment problems resulting in excessive fouling can be fixed • The Tampa facility meets all drinking water standards • The Tampa facility is capable of producing 25 MGD of potable water

  18. Questions?

More Related