Alpha Magnetic Spectrometer – 02 RID Overview & Disposition. Re-baselining Outbrief July 15, 2004 Trent Martin. Documents for Review. http://www4.jsc.nasa.gov/eaprojects/ea-projects/flightgfe/ams_02/html/ams_02.htm. Other Items for Review.
E N D
Alpha Magnetic Spectrometer – 02 RID Overview & Disposition Re-baselining Outbrief July 15, 2004 Trent Martin
Documents for Review http://www4.jsc.nasa.gov/eaprojects/ea-projects/flightgfe/ams_02/html/ams_02.htm AMS Re-Baselining RIDs 15-July-2004
Other Items for Review AMS Re-Baselining RIDs 15-July-2004
Review Team Status as of July 15, 2004 – 84 Total RIDs PA – Pending Action
RID Statistics Red – Open Yellow – Open pending document update Green - closed AMS Re-Baselining RIDs 15-July-2004
Major RID Findings • Project Plan editorial comments, clarifications and reorganization • PTRS editorial comments and clarifications • Major decision to pull verification matrix out of PTRS and write the V&VD now • ICD & SVP editorial comments and clarifications AMS Re-Baselining RIDs 15-July-2004
RID Statistics • 3 Open • RID 19 – Remove LMSO from all documents • RID 75 – Add 2nd ACOP • RID 77 – Modify AMS Payload Goals • 13 Open Pending Action • RIDs 1,52,53 – Updates to SVP • RIDs 3,66,67,68,78,79,81,82 – PIH to AMS ICD or VC ICD • RIDs 61,65 - New V&VD • 68 Closed • RID 76 – Many updates to Project Plan AMS Re-Baselining RIDs 15-July-2004
CDR RID Summary • Had 38 open RIDs at the start of the rebaselining review • 21 Open RIDs • Majority are open pending work that was either delayed due to lack of funding or are part of the standard process for later reviews (FSR II and III) • 17 Closed RIDs • Mostly duplicated by Rebaselining RIDs or superceded by new document revisions • Will bring closure plan back to first CCB (August) AMS Re-Baselining RIDs 15-July-2004