320 likes | 536 Views
VelociRFTA CCA Presentation Roaring Fork Transportation Authority - RFTA November 8, 2010. Today’s Meeting Agenda.
E N D
VelociRFTA CCA Presentation Roaring Fork Transportation Authority - RFTA November 8, 2010
Today’s Meeting Agenda • The purpose of this meeting is to introduce the VelociRFTA BRT Project to the Colorado Contractors Association. Also, RFTA is hoping to generate excitement for this upcoming construction project and gather input on the construction procurement process. • Introductions – Mike Hermes (RFTA) • Project Presentation and Overview – Craig Friesen (M. Baker Corp) • Construction Assumptions – Robert Manzanares (HNTB) and Nick Senn (SGM) • Construction Constraints – Robert Manzanares (HNTB) and Nick Senn (SGM) • Construction Procurement –Collina Washington (RFTA) • Closing Remarks
VelociRFTA BRT Project Introduction • The proposed BRT service will utilize the existing 40‐mile Colorado State Highway 82 (SH 82) corridor between Glenwood Springs and Aspen • The proposed BRT service consists of nine stations, seven of which are located at existing RFTA local or express service stops, two new park and ride lots, and the expansion of one existing park and ride lot • As part of transit service priority (TSP) elements, queue jump lanes and signal priority for transit buses will be provided at key intersections • The proposed BRT project, through nearly a decade of study, emerged as a viable and preferred solution to reduce transit travel times, improve mobility, and enhance transportation capacity in order to reduce congestion on SH 82 in the Roaring Fork Valley
BRT Project Status • The project is currently at 60% design with final design scheduled to be completed in early 2011. • RFTA intends to advertise the project in early 2011 • Notice to proceed for construction is anticipated to occur in early to mid 2011. • Construction phasing will be a challenge on this project due to the multiple locations along the 40 mile corridor (see SH 82 Corridor Map on the following slide), and the fact that RFTA will need to remain operational during construction • Waiting for the FONSI from the FTA to begin acquiring properties
SH 82 Corridor Map – Including Station Sites and Transit Priority Locations
BRT Design • Highway Improvements • Upgraded traffic signals and signal priority • Queue by pass lanes • Standard CDOT tapers at on-line stations • Pedestrian safety improvements (recommendations in progress)
BRT Design Station Program • Shelter • Ticket vending • Seating areas • Enclosed waiting • Lighting • Bicycle Storage • Covered/uncovered • Outside Seating • Landscaping • Trash and Recycling • Optional Elements • Parking • Restroom Facilities
Station and Platform Concepts Design Fits into context of the Valley – Warm and Inviting – WOW – Cohesive Rider Experience
Standard Station – Single Shelter • El Jebel – Up and Down Valley • Willits – Up and Down Valley • Basalt – Up and Down Valley • AABC – Up and Down Valley • Buttermilk – Up and Down Valley
Standard Station – 1.5 Shelter • Carbondale
Standard Station – Double Shelter • Glenwood Springs • Brush Creek
Glenwood Springs/27th Street Retaining Wall Blake Avenue Asphalt Asphalt Conc. Retaining Wall Conc. 27th St. S.H. 82
Glenwood Springs/27th Street • Double station • Double restroom • 40 covered bike parking • Proposed park and ride (51 spaces) • Approximate Quantities • 10,000 Sq. Ft. Retaining Wall • 2,500 Sq. Yds. Conc. Pavement • 2,200 Tons HMA • 2,300 L.F. Curb and Gutter • 700 Sq. Yds. Colored Conc. Pavement • 700 Sq. Yds. Sidewalk • Construction Constraints • Construction any time of year • Might be able to close 27th • Maintain access to properties on Blake • Maintain Sidewalk access on S.H. 82
Carbondale Park and Ride Village Rd. S.H. 133 Conc. New Rt. Turn Lane (HMA) Trail
Carbondale Park and Ride • 1.5 station • Double restroom • 40 covered/12 uncovered bike parking • Adjacent to existing park and ride(93 spaces) • Approximate Quantities • 1,450 Sq. Yds. Conc. Pavement • 100 Tons HMA • 1,400 L.F. Curb and Gutter • 800 Sq. Yds. Colored Conc. Pavement • 150 Sq. Yds. Sidewalk • Construction Constraints • No Construction 11/1 to 4/15 • Construct S.H. 133 Widening 1st • Close Park and Ride during Const. • Maintain Trail access during Const.
El Jebel Up Valley Station Down Valley Station E. Village Rd. S.H. 82 Slurry Seal Asphalt Sopris Village Rd.
El Jebel • Single shelter • Single restroom (up valley) • 20 covered/20 uncovered bike parking • Proposed park and ride (113 spaces up valley) • Existing CDOT underpass • Approximate Quantities • 700 Sq. Yds. Conc. Pavement • 2400 Tons HMA • 2,300 L.F. Curb and Gutter • 400 Sq. Yds. Colored Conc. Pavement • 900 Sq. Yds. Sidewalk • Construction Constraints • No Construction 11/1 to 4/15 • Construct Park and Ride 1st • Lane closures during off peak times • Maintain Ped. access during Const.
Willits Pedestrian Underpass by Others Up Valley Station S.H. 82 Down Valley Station
Willits • Single station • Underpass by others • Approximate Quantities • 700 Sq. Yds. Conc. Pavement • 750 L.F. Curb and Gutter • 450 Sq. Yds. Colored Conc. Pavement • 100 Sq. Yds. Sidewalk • Construction Constraints • Dependent on Funding • Lane closures during off peak times
Basalt Park and Ride Down Valley Station Up Valley Station S.H. 82 Basalt Ave. New Parking Asphalt
Basalt Park and Ride • Single station • Existing (235) and proposed (120) park and ride • 30 covered/18 uncovered bike parking • Approximate Quantities • 800 Sq. Yds. Conc. Pavement • 2,500 Tons HMA • 2,700 L.F. Curb and Gutter • 400 Sq. Yds. Colored Conc. Pavement • 400 Sq. Yds. Sidewalk • Construction Constraints • No Construction 11/1 to 4/15 • Construct Park and Ride 1st • Lane closures during off peak times • Maintain Ped. access during Const.
Brush Creek Location of temp. Bus Loop Intersection Improvements Existing Parking Lot New Platform in Same Location as Existing S.H. 82 Owl Creek Rd. Widening for Bus Only Left Turn Lane
Brush Creek • Double station • Double restroom • 10 covered bike parking • Existing park and ride (200) • Approximate Quantities • 3,500 Sq. Yds. Conc. Pavement • 1,200 Tons HMA • 2,000 L.F. Curb and Gutter • 1,000 Sq. Yds. Colored Conc. Pavement • 200 Sq. Yds. Sidewalk • Construction Constraints • No Construction 11/1 to 4/15 • Construct Bus Loop 1st • Temporary Bus Loop in back Parking Lot • Maintain Egress into Park and Ride at all times
AABC – Pitkin County Airport Down Valley Station Airport Rd. Up Valley Station S.H. 82
AABC – Pitkin County Airport • Single station • 16 uncovered bike parking • Approximate Quantities • 1,600 Sq. Yds. Conc. Pavement • 900 L.F. Curb and Gutter • 400 Sq. Yds. Colored Conc. Pavement • 400 Sq. Yds. Sidewalk • Construction Constraints • No Construction 11/1 to 4/15 • Put Temp. stops on Frontage Rds. • Lane closures during off peak times
Buttermilk Down Valley Station Up Valley Station S.H. 82 Buttermilk Rd.
Buttermilk • Single station • 16 uncovered bike parking • Approximate Quantities • 1,000 Sq. Yds. Conc. Pavement • 400 L.F. Curb and Gutter • 400 Sq. Yds. Colored Conc. Pavement • 200 Sq. Yds. Sidewalk • Construction Constraints • No Construction 11/1 to 4/15 • Lane closures during off peak times
Funded by the Federal Transit Administration (“FTA”) Fixed Price Contract May be defined by task orders due to multiple locations and multiple construction periods (to be determined) “Best Value” Procurement Request for Proposals, not Invitation for Bid Factors other than cost taken into consideration Two-Step Procurement (to be determined) Step 1 - Pre-Qualification Step 2 - Bid or Cost Proposal Bonding Requirements Bid Bond (5%), Performance Bond (100%) and Payment Bond (100%) Very Small Starts A Section 5309 Capital Investment Grant Program PROCUREMENT OVERVIEW
PROCUREMENT REQUIREMENTS Prime required to perform 20% of the overall work on project Since project federally funded, no local preference given Adherence to the following requirements: Davis-Bacon Act Buy America Suspension & Debarment List Lobbying Prohibition Disadvantaged Business Enterprises Other FTA requirements Prime Contractor must be CDOT Pre-Qualified
THANK YOU • Send your comments to brtconstruction@rfta.com • No responses will be given • Check www.rftabrt.com for project updates... • Thanks for your interest and your time.