1 / 25

UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee

UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee. UCN Shielding Requirements. General Layout of Shielding Structure Inner layer of Steel Outer layer of Concrete. A.Trudel calculations (TRIUMF Safety Group) 40 m A, 500 MeV protons stopping in W target

Download Presentation

UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UCN Beamline Shielding, Target & Remote-Handling UCN CDR (Sept/2010) L.Lee

  2. UCN Shielding Requirements General Layout of Shielding Structure Inner layer of Steel Outer layer of Concrete A.Trudel calculations (TRIUMF Safety Group) 40 mA, 500 MeV protons stopping in W target Assumes 0.5 m empty space around target (no moderator) Plot shows the shielding needed to reduce dose to 3mSv/hr outside

  3. Shielding Costs Original Cost Estimate (CFI prop): Concrete $ 900 k Steel (radioactive) $ 200 k (66%) Steel (new) $ 700 k (33%) Staging/Installation $ 20 k Total $1820 k Vendor Quotes: Concrete $1251 k Steel (radioactive) $ 360 k (66%) Steel (new) $ 480 k (33%) Staging/Installation $ 20 k Total $2111 k Latest UCN Layout Latest UCN Layout: Concrete $ 834 k Steel (radioactive) $ 240 k (66%) Steel (new) $ 320 k (33%) Staging/Installation $ 20 k Total $1414 k Above estimates based on bulk volume estimates+20% contingency More detailed layout TRIUMF Design Office (A.Prorok)

  4. UCN Concrete Shielding UCN Steel Shielding Extent of existing Shielding Wall Detailed Layout of UCN Shielding (1st Iteration)

  5. UCN Shielding – Layer 1 Concrete shielding blocks – Yellow Steel shielding blocks – Black/Silver

  6. UCN Shielding – Layer 3

  7. UCN Shielding – Layer 5

  8. UCN Shielding – Layer 7

  9. UCN Shielding – Layer 9

  10. UCN Shielding Structure 4’ x 6’ x 18’ Concrete shielding blocks (on-hand, outside “Electronics” Trailer) Reuse existing concrete blocks from M11/M13  1836 ft3 ~50 m3

  11. Shielding Costs from 1st Iteration Layout 1st Iteration UCN Layout: Concrete $ 445 k Steel (radioactive) $ 485 k Steel (new) $ 240 k Staging/Installation $ 20 k Total $1190 k Possible Cost Savings: • “Skyshine” dose limits are higher  remove uppermost 2 layers of shielding (?)  savings of ~ 22%  $225 k • Reuse existing steel from magnets  possible savings  $ 75 k Total savings  $300 k If above savings can be implemented, total cost for shielding  $890 k 2nd Iteration Layout  Possible further improvements in “blocking” efficiency

  12. Spallation Target & Remote-Handling System • Initial startup at 2 mA (500 nA time-averaged) • Target cooling and residual activity  not a major issue • RCNP @ 1 mA  radiative cooling found to be adequate • residual activity  very low • At higher currents 40 mA (10 mA time-averaged)  Require Target Cooling •  Water-cooling vs Helium-cooling • Model target after elements from existing designs at BNL, KEK, TRIUMF • Budget: $30k • Residual Activity & Remote-Handling • Retract target into a shielded cask • TRIUMF Remote-Handling specialists consulted  do-able at $100k • Target failure  Transfer to Horizontal transport flask (e.g. 2C-STF flask) and crane to existing Hot Cell facility • Prior to installation at TRIUMF (recent initiative with RCNP) • Spallation Target & RH system  use at RCNP • RCNP: 2mA to 10mA (instantaneous) • Ideal opportunity to test system and resolve Cooling/RH issues

  13. Target Design Model target after BNL target • BNL target • Pt target (segmented) coupled to Copper base • Water-cooled base • Heat load ~ 2kW (time-avg)  TRIUMF people involved in design of this target • UCN target  Tungsten alloy (HeavyMet) target; d~5 cm, L~11-14 cm • Coupled to water-cooled base (Cu?) • Heat load ~ 5kW (time-avg) • Water flow rate ~10 L/min to remove instantaneous heat load

  14. Flexible Shaft (remote-control cables) Driveshaft (detachable) Pb-Shielded Cask 20K D2O Rack & Pinion System He Pb-Shielded Shutters 80 cm 300K D2O Beam Target Cooling Block Coolant Lines Rails/Bearings Bellows Remote-Handling System (Upstream Withdrawal) Pb-Shielded Cask and Target Mounting System

  15. Water-Cooling Setup for 1AT1/T2 Target Ladder Bellows & Coaxial water lines on Target Ladder Custom seals TRIUMF M/Shop

  16. Target in Retracted Position  Retract Target into Cask • Access UCN cryostat OR Prep for Target Removal

  17. Target Removal/Disposal  Relocate Target + Cask to external (horizontal) transport Flask  Crane to Meson Hall Hot-Cell facility External Transport Flask (e.g. 2C-STF flask)

  18. Costs & Human Resources Summary • More details in main Resources & Timeline Section • Possible reduction in Human Resources requirements: RCNP (Tgt), Acsion (Tgt, Shielding)

  19. Schedule: Shielding and Target/RH Overview of Main Milestones (details in Resources & Timeline Section) Shielding: Final design mid-2012 Procure shielding mid-2012  mid-2014 Install Base layer mid-2013  Dec/2013 Install remaining layers mid-2014  mid-2015 Target & RH system: Receive Target @ TRIUMF: Mar/2014 Install Target @ TRIUMF: May/2014

  20. The End

  21. Shielding Costs ORIGINAL (“With PIF”) UCN Layout NEW (“No PIF”) UCN Layout Shielding Budgets Original cost estimate (total)  $1820 k (from CFI proposal) Vendor Quotes: Concrete $1251 k Steel (radioactive) $ 360 k (66%) Steel (new) $ 480 k (33%) Staging/Installation $ 20 k Total $2111 k Latest UCN Layout: Concrete $ 834 k Steel (radioactive) $ 240 k (66%) Steel (new) $ 320 k (33%) Staging/Installation $ 20 k Total $1414 k

  22. UCN Shielding – Layer 2 (Base Layers)

  23. Water-cooling vs Helium-cooling Water Cooling Helium Cooling Good cooling efficiency Low cooling efficiency  high flow velocities req. “Conventional” technology Greater Technical & Regulatory (ASME) complexity Activation of water Low Activation Leaks  Contamination Risks Low Contamination Risks Boiling of Coolant Two Water-cooled targets (1AT1 & 1AT2) in operation “near-by” Water-cooling infrastructure already available

  24. Spallation Target Calculations from Safety (A.Trudel) indicates target activity level after 10 years of irradiation will still be a factor of ~5 below the A2 transport limit • A stopping target of tungsten bombarded with 100 uA of 500 MeV protons. • Blue arrows correspond to 1, 5 & 10 years of irradiation. • Shown below the arrow is the total activity as a fraction of the A2 transport limit. • The inventory of activity in the target at ten years is at approximately one fifth of the A2 transport limit for Type A packages.

More Related