1 / 5

WP4 Face to Face #6, Oxford 14 th July 2011

WP4 Face to Face #6, Oxford 14 th July 2011 . Welding summary Richard French – The University of Sheffield. Welding progress – materials. 316L in 1/8” programme complete – to write up. 316L in 2.0mm OD – back burner but will fit in

malo
Download Presentation

WP4 Face to Face #6, Oxford 14 th July 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WP4 Face to Face #6, Oxford14th July 2011 Welding summary Richard French – The University of Sheffield

  2. Welding progress – materials • 316L in 1/8” programme complete – to write up. • 316L in 2.0mm OD – back burner but will fit in • CP2 Ti in 1/8” 70% done – need to collate NDT and DT results, double check and write up. • CP2 Ti in 2.275mm OD – there are problems and some are more fundamental than others.

  3. Weld system update • Original M200 procurement spec – met the baseline of 316L Stainless Steel in 1/8” with a wall thickness of 0.22mm which has been met. • M200 failed before outside upgrade week at Oxford. Mechanical problems fixed and CPU problems also fixed. New software was not so good. Repeated trips to Warrington to callibrate the weld system to the old settings. This is now done (5th July) and working correctly. • New software ready in September – patches made to fix some pretty serious problems found. Big error from manufacturers to release. Cost us at least 3 months, revisiting old measurements and verifying weld programmes. • Collets are now made (custom from Sheffield workshop) for 2.275mm OD tube – • Can’t get a weld procedure to work yet. Power control has not been as good as previous software allowed. This supposedly fixed with recalibration – not tested. • Have tried 5 electrode types, now altering tip angles. • Main show stopper is weld head is only suitable for 3mm to 28mm OD – NOT 2.2mm!! This is causing havoc for RPM and arc gaps.

  4. New weld head trials Weld head is a one-piece unit. It is very solid and the clamping mechanism gives significantly better alingment than the Swaglok product. Welds 1/8” equally well in 316L and CP2 Ti. Have to make some proper tests (NDT DT)as visual inspection not telling me anything. Will reference with previous welds from M200 + 5H head combo. • “Borrowed” a Fronius weld head. • Problems are this head has analogue encoder, M200 uses digital. Made a TTL to analogue conversion box. Made power plug conversion lead. Something unmentionable done to product ID. Dimensions are very similar to the smaller 4H weld head. This is significantly more robust and the encoder and power delivery system is significantly more advanced. Arc of clamping head could be a problem. 3x more expensive than 4H

  5. Way forward • 2nd weld system procurement discussed at RAL on 13th July. RF, TJ, JN, IW. • Tests will be made with a new 4H weld head and the M200 supply. Will this be any better for welding the small OD (2.275mm) Ti tube. • Test pieces have been sent to 3x orbital welding manufacturers. • Responses expected in Sept. • Procurement decision after evidence and testing.

More Related