Fluor K132 (Santos) Contract – Dawson’s Bend Road

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AustStab Awards of Excellence 2013 Fluor K132 (Santos) Contract – Dawson’s Bend Road FK Gardner & Sons Pty Ltd Innovation or Excellence in Sustainability in Pavement Stabilisation Sponsored by

  2. The Project • Part of Santos’ $18.5 billion GLNG CSG venture • Consists of new roads and upgrades to existing roads at the Fairview gas fields • Dawson’s Bend is a 17km long critical road at the heart of the gas field required to provide access for the installation of infrastructure

  3. The Problem Local quarry, Burnt Gully, was no longer able to provide the required CBR 35 material Another quarry 70km away was determined as a potential new source of material The material would require crushing and transport to the site at significant cost to the client

  4. The Solution FKG undertook laboratory testing on Burnt Gully material of CBR 10 mixed with cement Results showed that a 1% cement modification could provide in excess of CBR 45 This would result in a shortened programme and reduced cost

  5. The Outcome The solution saved the client in excess of $1 million over the life of the project It meant fewer trucks on the road and a reduced carbon footprint FKG conducted FWD testing and determined a 20+ year design life FKG delivered value for money and a more sustainable result