530 likes | 742 Views
Capital Budgeting. Rules for Sensible Investment Decisions!!. Cost vs. Benefits. Investment typically has two components: Outflow of cash (cost) Inflow of cash (benefits) TVM requires all cash flows to be compared at the same point in time Most convenient is time 0. Recall Forbes Example.
E N D
Capital Budgeting Rules for Sensible Investment Decisions!!
Cost vs. Benefits • Investment typically has two components: • Outflow of cash (cost) • Inflow of cash (benefits) • TVM requires all cash flows to be compared at the same point in time • Most convenient is time 0
Recall Forbes Example • Tax savings: $500,000 forever • Campaign Costs: $40 million • r = 10% • PV of Benefits: .5 mill / .10 = $5 million • Cost: $40 million • Benefit - Cost = 5- 40 = -$35 million
Forbes example... • Obviously this is a lousy investment • What you just used in analyzing this ‘investment’ proposal is NPV rule! • It turns out the NPV rule is the most sensible rule to use for evaluating projects
Examples of Capital Budgeting Projects • To open a corner latte stand • To replace replace a 486 computer used in business with a Pentium computer • To decide between a coal-fired and a nuclear fuel power plant costing $1 billion • To add 5 stories to an existing office tower • To shut down an aging factory making ball bearings
Evaluating Investments • There are many ways to evaluate investments • Among all the investment rules we will consider, NPV rule is the only rule that always gives correct answer in all situations!! • Other rules may or may not give an answer consistent with NPV rule
Net Present Value • NPV = PV of Benefits - PV of Costs • Accept project if NPV > 0 • Reject project if NPV < 0
Another Example... 0 1 2 Revenues $2,000 Expenses 1,000 Cash flow $1,000 Initial outlay ($1,100) Revenues $1,000 Expenses 500 Cash flow $500 – $1,100.00 +454.54 +826.45 +$180.99 1 $500 x 1.10 1 $1,000 x 1.102 NPV
NPV Formula • ‘r’ has many names: • ‘r’ is called the discount rate or • ‘r’ is called the required return or • ‘r’ is called the cost of capital
Computing NPV on calculator • Use the CFj key • First entry is at time 0 • Subsequent entries are time 1, 2, 3, ... and so on • make sure the cash flows have the proper signs • Enter ‘r’ as the I/YR • Use the keysThat’s it!! NPV
Another Example.. NPV = $ _______ Accept / Reject Project ?
Another Example... • The cash flows are Year Cash flow 0 -$252 1 1431 2 -3035 3 2850 4 -1000 r = 10% NPV = _______ Accept / Reject ??
Example continued... • This was an example of unconventional cash flows • Conventional Cash Flows: Only one change in sign (from + to - or vice versa)e.g. - + + + + • Unconventional Cash Flows: More than one change in signe.g. - + + - + -
Importance of NPV • NPV is the dollar value added to the enterprise • it’s the amount by which the enterprise is richer! • For public companies, NPV is the increase in total market value of equity • Managers should not take negative NPV projects since it reduces the firm value
Other Rules • Alternative rules of evaluating investments are: • Internal Rate of Return (IRR) • Payback • Discounted Payback • Profitability Index • Accounting Rate of Return
IRR Rule • IRR: the discount rate that makes NPV = 0 • Rule: Accept if IRR > required returnReject if IRR < required return
IRR and Required Return • Required return also called the ‘Hurdle Rate’ • Required return is the cost of investment funds • i.e. what it costs to borrow money or raise equity capital for investments • it is the same cost of capital ‘r’ used in NPV calculations
IRR on Calculator • Enter the cash flows as before • Use the keys • That’s it! • Without financial calculator, IRR is computed by trial and error IRR/YR
IRR Example Year Cash flow 0 -200 1 50 2 100 3 150 50 100 150 0 = -200 + + + (1+IRR)1 (1+IRR)2 (1+IRR)3 IRR = ______% Hurdle rate = 9% Accept / reject?
Another Example 1 2 3 4 5 0 6 • What is the IRR? Ans: _____ • What is the NPV if r = 16% Ans: _____ • Do IRR and NPV give the same answer? -256 +31 +128 +194 +61 +55 +108
Net Present Value Profile Net present value 120 Year Cash flow 0 – $275 1 100 2 100 3 100 4 100 100 80 60 40 NPV>0 20 0 NPV < 0 – 20 Discount rate – 40 2% 6% 10% 14% 18% 22% IRR
IRR and Unconventional Cash Flows • The cash flows are • Year Cash flow • 0 -$252 • 1 1431 • 2 -3035 • 3 2850 • 4 -1000 • IRR = ?
Example continued.... • What’s the IRR? at 25.00%: NPV = _______ at 33.33%: NPV = _______ at 42.86%: NPV = _______ at 66.66%: NPV = _______ • Two questions: • 1. What’s going on here? • 2. How many IRRs can there be?
NPV Profile - Multiple IRR Problem NPV $0.06 $0.04 IRR = 25% $0.02 $0.00 ($0.02) IRR = 66.6% IRR = 33.3% IRR = 42.8% ($0.04) ($0.06) ($0.08) 0.2 0.28 0.36 0.44 0.52 0.6 0.68 Discount rate
Problem 1 with IRR Rule • IRR Rule does not always give a clear answer with unconventional cash flows • In the above example, there are multiple IRRs • The accept/reject decision in the example depends on required rate of return
Another Problem with IRR Year 0 1 2 3 4 Project A: – $350 50 100 150 200 Project B: – $250 125 100 75 50 If the projects are mutually exclusive (i.e. can take one or the other, but not both), which project to take?
Decision with mutually exclusive projects • IRR Rule does not always give a correct answer with mutually exclusive projects • In the above example, it seems we would prefer Project ________ (higher IRR)
Mutually Exclusive… (contd.) • But always take the project with higher NPV!! • If r = 5%, then accept project A • If r = 14%, then accept project B
IRR, NPV, and Mutually Exclusive Projects Net present value $ 160 Project A 140 120 100 80 Project B 60 40 NPV A >NPV B 20 0 – 20 – 40 – 60 NPV B >NPV A – 80 Discount rate % – 100 0 2% 16% 20% 24% 10% 6% IRR A < IRR B Crossover rate
Cross-over Rate • the discount rate that makes NPV of two projects equal • the interest rate at which you are indifferent between two mutually exclusive projects
Finding Crossover Rate • Take difference between cash flows of two projects and find IRR (of these incremental cash flows) Year 0 1 2 3 4 Project A: – $350 150 120 150 200 Project B: – $250 125 100 75 165 Difference: –$100 25 20 75 35 IRR (difference) = _______ %
Another example • Find the crossover rate of these two projects • Answer: _________
IRR - Criticisms • Not a measure of dollar value added • Does not consider the scale of the project • Interim cash flows are assumed to be reinvested at the IRR which is unrealistic • Does not give correct answer when • you have mutually exclusive project • unconventional cash flows
Payback Rule • Measure of the length of time until the sum of future cash flows equals the initial investment • Time it takes to get you money back • Accept: if payback period is less than some pre-specified benchmark
Payback Example • The cash flows are • Year Proj. A Proj. B • 0 -$100 -$100 • 1 90 15 • 2 15 90 • 3 10 10 • 4 10 20 Payback = 2 yrs
Problem with Payback Year Proj. A Proj. B 0 -$100 -$100 1 90 15 2 15 90 3 10 100 4 10 2000 Payback rule ignores these cash flows Although both projects have the same payback, Proj. B is clearly superior
Payback Rule - Criticisms • It does not take into account time value of money (i.e. no discounting of cash flows) • Payback rule ignores all the cash flows that occur after the payback period • Required payback benchmark is arbitrary
Discounted Payback • Length of time until present value of future cash flows equals the intial investment • avoids the time value criticism of simple payback rule • Accept if discounted payback less than pre-specified benchmark • Does not avoid other criticisms of payback rule
Disc. Payback Example • The cash flows are • Year Proj. A PV (r=10%) • 0 -$100 -$100 • 1 90 81.82 • 2 15 12.40 • 3 10 7.51 • 4 10 6.83 discounted payback = 3 years
Discounted Payback - criticism • Incorporates time value in decision in contrast with simple payback, • It still ignores all cash flows occuring after the required payback period • Benchmark is still arbitrary BUT
Profitability Index • Ratio of PV of benefits to PV of costs • “Bang for the buck” • Rule: Accept Project if PI > 1Reject project if PI < 1
P. I. Example • P. I. = ______ =________ 200 • Interpretation: NPV of $0.204 is added for each $1 of investiment.
Problems with P. I. • As with IRR, it does not consider the scale of the project. • Not a measure of total $ value added to firm • With mutually exclusive projects, P. I. can give wrong rankings
Another Example • Although Proj. A has higher P. I., Proj. B should be accepted because NPV is higher
Average Accounting Return • Measure of avg. accounting profit divided by avg. accounting value of investment:A. A. R. = avg. net income avg. book value of invest. • Accept if AAR > benchmark returnReject if AAR < benchmark return
A. A. R. Example • Average net income: • Year • 1 2 3 • Sales $440 $240 $160 • Costs 220 120 80 • Gross profit 220 120 80 • Depreciation 80 80 80 • Earnings before taxes 140 40 0 • Taxes (25%) 35 10 0 • Net income $105 $30 $0 • Average net income = (105 + 30 + 0)/3 = $45
Example continued • Average book value: • Initial investment = $240 • Average investment = ($240 + 160 + 80 + 0)/4 = $120 • (or) = $240/2 = $120 • Average accounting return (AAR): • Average net income $45 • AAR = = = 37.5% • Average book value $120
Problems with AAR • Does not use cash flows • Ignores timing of income • Pre-specified benchmark is arbitrary
Summary • Of all the rules considered, NPV consistently gives the correct answers • Other rules may or may not give the same answer as NPV • Decisions based on NPV rule are always correct!