1 / 13

Inventory Models

Inventory Models. Production Lot Size Models. PRODUCTION LOT SIZE MODELS. In a production lot size model, we are a manufacturer, trying to determine how much to produce (the production lot size) during each production run. Like the EOQ model with Q = the production lot size except:

marged
Download Presentation

Inventory Models

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Inventory Models Production Lot Size Models

  2. PRODUCTION LOT SIZE MODELS • In a production lot size model, we are a manufacturer, trying to determine how much to produce (the production lot size) during each production run. • Like the EOQ model with Q = the production lot size except: • We are producing at a rate P/yr. that is greater than the demand rate of D/yr. • Otherwise run process continuously and sell items as fast as they are produced • Inventory does not “jump” to Q but builds up to a value IMAX that is reached when production is ceased

  3. What is the maximum inventory and the average inventory per cycle? • Length of a production run = Q/P • During a production run • Amount Produced = Q • Amount Demanded = D(Q/P) • IMAX = Q - D(Q/P) = (1-D/P)Q • Average inventory = IMAX/2 = ((1-D/P)/2)Q

  4. The production increases the inventory at a rate of P. T1 Demand accumulation during production run The inventory increasesat a net rate of P - D Length of Production Run = Q/P IMAX= Q – Q(D/P) = Q(1 – D/P) Maximum inventory: IMAX The demand decreases the inventory at a rate of D. Production Lot Size Model – Understanding the inventory profile Demand accumulation during production run = DT1 = D(Q/P) = Q(D/P) Production Lot Size = Q = PT1

  5. PRODUCTION LOT SIZE -- TOTAL ANNUAL COST • Q = The production lot size • CO = Set-up cost rather than order cost =$/setup • Number of Set-ups per year = D/Q • Average Inventory = ((1-D/P)/2)Q • Instantaneous set-up time/infinite time horizon TC(Q) = CO(D/Q) + Ch((1-D/P)/2)Q + CD

  6. OPTIMAL PRODUCTION LOT SIZE, Q* TC(Q) = CO(D/Q) + Ch((1-D/P)/2)Q + CD

  7. EXAMPLE-- Farah Cosmetics • Production Capacity 1000 tubes/hr. • Daily Demand 1680 tubes • Production cost $0.50/tube (C = 0.50) • Set-up cost $150 per set-up (CO = 150) • Holding Cost rate: 40% (Ch = .4(.50) = .20) • Since demand is 1680 per day and the production rate is 1000 per hour: • D = 1680(365) = 613,200 • P = 1000(24)(365) = 8,760,000

  8. OPTIMAL PRODUCTION LOT SIZE

  9. TOTAL ANNUAL COST TOTAL ANNUAL COST = TC(Q) = TV(Q) + CD TV(Q) = CO(D/Q) + Ch((1-D/P)/2)Q = (150)(613,200/31,449) + .2((1-(613,200/8,760,000))(31,449)/2) = $5,850 TC(Q) = TV(Q) + CD = 5,850 + .50(613,200) = $312,450

  10. OTHER QUANTITES • Length of a Production run = Q*/P = 31,449/8,760,000 = .00359yrs. = .00359(365) = 1.31 days • Length of a Production cycle = Q*/D = 31,449/613,200 = .0512866yrs. = .00512866(365) = 18.72 days • # of Production runs/yr. = D/Q* = 19.5 • IMAX = (1-(613,200/8,760,000))(31,449) = 29,248

  11. REORDER (SETUP) POINT ANALYSIS • The reorder point (actually the setup point) and safety stock determination are not affected by the calculation of Q*. • It is found in the same way as before: • r* = LD + SS if demand is constant over lead time • r* is found using service levels if demand varies during lead time

  12. Using the Template Optimal Values Enter Parameters Production Lot Size Worksheet

  13. Review • Production Lot Size Models find the amount to produce per production run • P > D, else optimal solution is to run machine continuously • Same as EOQ exceptIMAX= Q(1-D/P) • Length of a production run = Q*/P • Length of the production cycle = Q*/D • Reorder (setup) point analysis is not affected. • Use of template