CV/2006/01 – Ping Ha Road Improvement Works

Presentation for PM Meeting Date: 24 July 2008. Progress Sheet pile installation at northern slow lane is in progress and will be completed by early next week. Installation of drainage pipe is about 35.8% completed (total 2,700m).

margo
Download Presentation

CV/2006/01 – Ping Ha Road Improvement Works

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation for PM Meeting Date: 24 July 2008 • Progress • Sheet pile installation at northern slow lane is in progress and will be completed by early next week. • Installation of drainage pipe is about 35.8% completed (total 2,700m). • Two bays of Channel D were completed. Rebar fixing for base slab of D11 & D13 is in progress. • Construction of dwarf wall is about 21.7% completed (total 1,600m) • Alternative proposal to delete H-pile foundation of Noise Barrier is formally submitted. A meeting was held on 31 July 2008 among CEDD, HyD, GEO, CSHK, Jacob to discuss technical part of the alternative proposal. Basically all the concerns from GEO and HyD were addressed. • Problem • MOS for H-pile material • CEDD’s Late reply to RFI, CSF, MSF CV/2006/01 – Ping Ha Road Improvement Works

  2. Presentation for PM Meeting Date: 24 July 2008 Drainage, Earth, Landscape & Structural Works

  3. Presentation for PM Meeting Date: 24 July 2008 Channel D & Tin Ying Road Temporary Works