An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Monitoring Based Commissioning at CSU San marcos

  2. Overview • Campus Overview • State of the Campus - Before MBCx • MBCx – A First Attempt • Lessons Learned • The Second Round – Refining the Process • Persistent Scorecards – with and without • The Final Buildings – Pushing the Envelope

  3. Campus Overview • Over 12,000 students currently attend the 304-acre campus • 1.5 million Sq. Ft. of conditioned space • 960,000 Sq. Ft. on Central Plant • Master planned for 3 million Sq. Ft. and 25,000 students • 240 HP Hot Water Plant (previously 640HP) • 2,500 ton chiller plant - Primary variable flow • 16,000 ton hour TES tank • 80% of Campus CHW Distribution is Most Open Valve • Maxed out – currently accepting donations

  4. The Campus

  5. State of the Campus –Before MBCx • Campus Had a Higher BTU/SF Usage Than Other CSU Campuses • Higher Percentage of Lab Buildings Than Other CSU Campuses • Kellogg Library Experiment • Flaws of New Building Commissioning at The Time • Contractor Pays Commissioning Agent • No Proper Air Balancer • Contractors and Project Managers Did Not Take Recommendations From Campus or Commissioning Agent

  6. MBCx – A First Attempt (2007) Buildings • Kellogg – 3 Years Old • Craven – 15 Years Old • University Hall – 9 Years Old Many Measures Identified • Economizers Failed • Sensors Not Calibrated • Valves Leaking By

  7. Lessons Learned • Metering • Installing New Meters and Calibrating Existing • Data Acquisition • Bandwidth Issues With Energy Management System • Open Source Protocol was Necessary (BACNET) • Implementation Man Hours/Materials • Invest and Respond Timely

  8. Results 21% Energy Reduction $147,000/year in savings 2.2 Year Simple Payback* *After Utility Incentives

  9. The Second Round (2010) Buildings • Academic Hall - 18 Years Old • Science Hall 1 - 18 Years Old • Science Hall 2* - 9Years Old • University Commons - 18Years Old *Building Originally Not Commissionable Findings • A Few Valves Leaking By • Sensors Out of Calibration • Supply Air Temperature Resets • Static Pressure Resets

  10. Second Round Results 14% Energy Reduction $76,141/year in savings 1.3 Year Simple Payback* *After Utility Incentives Should have won Best Practices Award

  11. Continuous commissioning – With and Without Continuous Commissioning for Buildings • Minimizes drift • Identifies measures to maintenance staff • Identifies new energy efficiency measures • Savings calculations, cost analysis, and simple payback provided to campus when measures are identified

  12. Continuous commissioning

  13. Continuous commissioning – With and Without The Campus had a lapse in continuous commissioning services from June 2012 to July 2013. During this time period, campus energy usage increased approximately 3% year over year.

  14. The Final buildings (2013-14) Pushing the envelope Buildings in Progress • Markstein – 7 Years Old • Arts – 9 Years Old • Central Plant – 5 Years Since Retrofit First Observations • Very Few Sensors Out of Calibration • Economizers are Functioning Properly • All Units Have Supply Air Temperature and Static Pressure Resets

  15. Pushing the envelope What Measures Can Be Implemented • Demand Control Ventilation with Existing Occupancy Sensors • Included in newest Version of Title 24 • Reprogram Resets to Account for Problem Zones • Duct Sealing • Central Plant Reprogramming

  16. Thank you for your time!