280 likes | 370 Views
Steve Lathrop, PacifiCorp. Panel#2: A Day in the Life of Planners/Engineers. 2008 PI T&D Users Group Meeting, Atlanta, Sept 10-12. Agenda. Area Planning at PacifiCorp Infrastructure Planning Load Duration Curves – a New View of Data Non-SCADA Asset Loads SCADA Accuracy. Area Planning.
E N D
Steve Lathrop, PacifiCorp Panel#2: A Day in the Life of Planners/Engineers 2008 PI T&D Users Group Meeting, Atlanta, Sept 10-12
Agenda Area Planning at PacifiCorp Infrastructure Planning Load Duration Curves – a New View of Data Non-SCADA Asset Loads SCADA Accuracy
Area Planning Substation, sub-transmission and non-Main Grid transmission infrastructure Future Infrastructure needs (long-range planning) Daily Operations Issues Asset load analysis Load projections Capital spending Risk-Management data
Area Planning Watch Lists
Area Planning Watch Lists
Area Planning Watch Lists
Load / Voltage Analysis Alphabet soup: Real-time Historical Projected Peak Instantaneous Average Changing ….the differentiator between these is…Time
Infrastructure Planning Area Coincident Loads Six transformers serve this area Can I accurately determine area peak load and growth?
Infrastructure Planning Area Coincident Loads—Load profiles for the six:
Infrastructure Planning Area Coincident Loads—Projected loads
Infrastructure Planning Area Coincident Loads—Add all loads coincidentally
Infrastructure Planning Area Coincident Loads—Projectedgrowth of area load
Infrastructure Planning • Load Projections • Multiple Load Duration Tool v1.1
Load Duration Curves Time-Series data converted to time-independent data Simplifies analysis Non-engineers understand it
Load Duration Curves Demonstrate peak loads, duration of peaks and how many hours load limits are exceeded
Load Duration Curves Rearrange data: load-dependent, not time-dependent
Non-SCADA Asset Loads Substation C has no electronic metering. Can I get load profile data for it? My Power Flow suggests 1 MW losses total for line sections 1-4 at peak load CIS SCADA SCADA Source
Non-SCADA Asset Loads Substation C load is approximated by: Sub C = Sub A – Sub B – Sub D – 1 MW ~ CIS SCADA SCADA Source
Non-SCADA Asset Loads Black trace is my ‘pseudo-SCADA’ load profile
Verify SCADA Accuracy Transformer appeared to be overloaded 105% loading 20-MVA loading guideline
Verify SCADA Accuracy ‘Problem’ surfaced Error ‘Tag’ built Transducer Change-out Error goes to zero
Verify SCADA Accuracy Questions? Steve.Lathrop@PacifiCorp.com