120 likes | 375 Views
Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Mechanical Integration Ken Fouts kfouts@slac.stanford.edu. Key I&T Requirement Documents. Requirements Definition Key to Successful I&T. I&T Process Procedures.
E N D
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Mechanical Integration Ken Fouts kfouts@slac.stanford.edu
Key I&T Requirement Documents Requirements Definition Key to Successful I&T
I&T Process Procedures Document Detailed Procedures for use in I&T
Roadmap to ACD Integration and Test Install Flight PDU LAT-DS-02563 Install EM GASU LAT-DS-02563 Safe to Mate Flight Cables for PDU/GASU/ACD LAT-PS-07575 Bond Downspout Heatpipes and Fitcheck X-LAT Plate LAT-PS-04911 Complete Grid Thermal Control Installation LAT-DS-01580 Install Instrumentation Accels and TC’s LAT-DS-02563 16 Tower CPT w/ACD ACD Integration LAT-PS-07240 16 Tower LAT Optical Survey LAT-MD-00895 16 Tower CPT Critical steps have been identified and are in the current I&T plan
MGSE • LAT-DS-6958 ACD Lift Fixture • Fit-check complete with ACD simulator • Proof tested per LAT I&T AIDS #1588 LAT I&T ACD lift fixture fabrication and check-out complete.
Hardware Summary Hardware is in-place to support the current plan
Risks Risks have been anticipated and plans put in place to mitigate them
Summary • Current plan is to maintain two shift operation. • Utilize weekends maintain schedule. • Procedures, Drawings, MGSE and Flight Hardware in place to support current Phase 0 plan. • Additional subsystem personnel have been identified to support LAT I&T Operations. LAT I&T is ready to proceed with ACD integration