150 likes | 288 Views
Report on CMS Status Alan L. Stone on behalf of the CMS Collaboration. Summary from CMS Week Update on Solenoid CRaFT1. CMS Global Runs. CRUZET4 & MWGR. Cruzet4. September 10. Cruzet3. Cruzet2.
E N D
Report on CMS StatusAlan L. Stoneon behalf of the CMS Collaboration Summary from CMS Week Update on Solenoid CRaFT1
CMS Global Runs CRUZET4 & MWGR Cruzet4 September 10 Cruzet3 Cruzet2 • We had several global runs: CRUZET 3 & 4, regular midweek GRs, a first go at some data with magnetic field. • Started in first week of September with continuous 24/7 operation. • Beam monitoring online first week September. • Successful beginning at the September 10 LHC startup. • CMS shifts running continously since (40 hours of beams where CMS was always taking data w/o Tracker & Pixel). Cruzet1
Notes From The First Beam • From September 8 we ran continuously 24/7 until LHC incident of Sep 19th. • Since beginning of September we routinely readout ALL of installed CMS detectors in global runs. • All triggers are now operational (some still being improved) • Stability of running with all CMS components proved (also at high trigger rate, ran for 1 Hour at > 50 KHz, ~ 1 shift at >20 Khz) • HLT operational commissioning progressing fast: we are now running with a version which could have been used for early running at LHC, although not fully ‘stressed‘ • Beam monitoring equipment ‘appeared’ just in time but worked reliably from day 1, and are now familiar background features of the control room. • Data flow: had to adapt to ‘unforeseen’ features of real data and did so VERY efficiently: we are sure that we have not yet seen all possible features, but we are confident that ‘solutions’ would be found rapidly.
CSC “Halo Muon” Trigger Single Beams ME+ ME x TOF 2 bx Normal proton collisions (Beam-1) halo muon • LHC mode: both endcaps trigger simultaneously on IP muons • “Halo Muon” trigger: CSC Track Finder selects tracks with small • Trigger on outgoing endcap (i.e., ME for Beam-1) • Approximate timing of muons from IP • [Note: for first beams, the incoming endcap was also included in the trigger (delayed by 2bx). This is no longer true…] http://cms-project-cmsinfo.web.cern.ch/cms-project-cmsinfo/news.html
Beam Halo Event Through Both Endcaps • Single beam bunch in LHC (~2x109 protons) • Beam passes through CMS beam dump into collimators about 150m away from CMS • Beam captured several turns Run 62384 Event 56199 More event displays are stored athttp://www.nuhep.northwestern.edu/~schmittm/CMS/TEMP/event_displays/ • Synchronous “splashes” of muons + stuff • Synchronous muons approximately parallel to beam
Ramping The Solenoid (1) • 3T test on 29-30 August (Fri/Sat) • Fringe field: • Balconies in UXC: much local variation, values up to 350 Gauss (local shielding for Tracker cooling pumps worked) • USC (S1&S2): ~50 Gauss at the wall falling to 20 G at far end of rack row • Some concern that elevator failure may be result of fringe field First Solenoid ramp since 2006 (MTCC) when detector was above ground Fast dump 55-deg temp rise & 3-day recovery
Ramping The Solenoid (2) Sep 16 & 18 Sep 8 CMS magnet tests on Mon Sep 8th. Problems appeared just below 3T, with HF (Forward HCAL), associated detectors and shielding closed. Field-induced effects on elevator, access system, instrumentation near LHC triplets. Field-induced relative movements of the HF, collar shielding and CASTOR table, leading to risk of affecting beampipe support.
Ramping The Solenoid (3) • Mitigation of fringe field effects by securing affected areas during beam-off access periods [See above examples]. • Additional position and field-measuring equipment added. • Two additional beam tests on Sept 16th (up to 1.7T) and Sept 18th (up to 2.8T) with hall probes & watchers. • Movement and distortion of CASTOR, risking contact with beampipe. • Likely due to radial magnetic forces on unbalanced half-cylinder. • Decision to remove CASTOR. HF- must stay off for now. • Parallel work to secure CASTOR table, cradle, collar shield & I-beams. • Beam pipe to atmospheric pressure (Neon). • Magnet tests resumed on Thur (Oct 9th).
Solenoid at 3.8 Tesla! • Magnet test reached 3.8T on Friday Oct 10th at 15h • It was found that the HF was attracted 10-15 mm to the IP, but with no danger to the beam pipe. • CRAFT1 begins on Monday (Oct 13th) with two days of 0T pedestal runs. • The remaining two weeks will proceed with 3.8T cosmic runs • Aside for a VIP day on Oct 21st.
October Schedule 3.8T. 3.8T, 300M events, All detectors, 24/7 0T pedestals
Goals & Outlook • Test of operation in full 3.8 T field with all subsystems. • Work on Central DCS and DSS interfaces and functionality. • Storage manager stability . • RPC endcaps: late delivery of supplies and current drawn in one wheel. • Validation & commissioining of Jet Trigger. • Gain operational experience with Tracker and Pixel Front End Detectors. • They have accumulated fewer hours than the rest of the experiment. • There were off for beams. • Consolidate running at High rates (> 50 KHz) for day-long operation. • More automatic central control • Anticipation of an overall reduction of the total number of shifters for next year. Currently >20 per shift. • Coherent and consistent error reporting and error handling across subsystems. • Define, practice and document precisely our operations procedures. • Accumulate 300 Million triggers with cosmic tracks . Should allow us to find enough hard muons not too far off from the beam line in permit a good alignment and calibration of our detector. • CMS is now a working experiment.
HF & Collar/CASTOR Shielding Closure +end -end