LHC sector tests: plans for transfer lines, injection and dump

LHC sector tests: plans for transfer lines, injection and dump. W. Bartmann, M. Barnes, C. Bracco, E. Carlier, L. Drosdal, B. Goddard, V. Kain, M. Meddahi, J. Uythoven Sector Test Meeting, 8-May-2014. O utline. Scope Preparations without beam Preparations with beam (SPS extraction, TL)

marlie
Download Presentation

LHC sector tests: plans for transfer lines, injection and dump

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC sector tests:plans for transfer lines, injection and dump W. Bartmann, M. Barnes, C. Bracco, E. Carlier, L. Drosdal, B. Goddard, V. Kain, M. Meddahi, J. Uythoven Sector Test Meeting, 8-May-2014

  2. Outline • Scope • Preparations without beam • Preparations with beam (SPS extraction, TL) • Preparations with BIS loop closed • Sector test measurements

  3. Scope of BT tests • Re-alignment of relevant parts of the machines (SPS, upstream parts of transfer lines,…) • Modifications to many systems (MKI coatings and TMR, MKD generators, etc) • Magnet settings as from last run not anymore applicable • Can use pilot for the sector test • Won’t be able to fully resemble the final trajectory • Can measure SPS extraction window, but not optimum settings for kicker and bumpers, should do with INDIV • Doesn’t make sense to set up collimators • But test functionality of all equipment and software • Can scan kicker waveforms, test TL stability, synchronisations…

  4. Preparation of sector test without beam I • MKI: • Open valves, conditioning to 55 kV, softstart • Check BETSsim input, SMP energy transmitted • Check MKI waveform logging in OASIS, IQC • Installation and commissioning of MKIs: • IP2 • Installation: wk 21; Bake-out interconnects: wk 22 – 26; Controls commissioning: wk 27 + 28; HV tests etc.: wk 29 + 30 • Tests from CCC: wk 31 - 43 • Sector test IP2: wk 44 – no problem • IP8 • Installation: wk 35 – (no access to install before); Bake-out interconnects: wk  36 – 40; Controls: wk 41 + 42; HV tests etc.: wk 43 + 44 • Tests from CCC: wk 45 – 46 • Sector test IP8: wk 47 MKI8 schedule is tight!

  5. Preparation of sector test without beam II • Magnet systems: • Heat run • Pulsing full line • Switch powering • BI systems: • Movements, acquisition, logging, fixed displays • Screens, BPM, BCT, BLM • SPS extraction region (new monitors), TL and LHC injection/extraction region • Optics • Check settings for SPS extraction, TL and LHC injection/extraction systems • Beam position on injection/dump region screens • TCDI and MKI validation knobs, 14/15 MKD extraction knob • Aperture bumps at MSI, TCDIM, MKI, Q5, D2, TCDQ • Screens matching application

  6. Preparation of sector test without beam III • Protection devices TCDI, TDI, TCLI, TCDQ, TCSP • Movement, function/range • Interlocking • Downstream TED master BIC, injection permit TT40 • Inhibit of MKE in case of MKI erratics • Radiation monitoring • Radmons, Ramses in injection/extraction region, logging • Quality checks: IQC, IPOC • Data reception and logging • Element strengths and limits (thresholds to be updated later) • Element updates, new BLMs in injection regions • New BETS interlock on MSI, TDI • To be discussed in detail • Maskable BIS input • Access to UA while MSI powered to check HW limits?

  7. Preparation of sector test without beam IV • Beam dump • Arming sequence with global BIS • LBDS settings and MCS (changes of generators) • BETSsim (Q4, MSD input) • XPOC • Waveforms, VAC, BTVDD, BPMD  need beam dumped event • BLMs – new BLMs and filters • BETS interlock TCDQ

  8. Preparation of sector test with BIS loop closed • New TSU link to BIS • Prepare inject&dump • Is time foreseen before the sector test with BIS loop closed?

  9. Preparation of sector test with beam • SPS extraction to upstream TED • Setup extraction bump without extensive aperture scan • Steer through extraction channel • Check beam on screens • Kicker (MKE) timing on OASIS  need BCT+MKE • Can the TL be tested until the downstream TED before the sector test?

  10. Sector test measurements I • SPS extraction • MKE waveform scan • Rough aperture check if not yet done • Establish downstream TL trajectory • Screens matching • Check BPM/corrector polarities (and optics) with kick response • Measure TL dispersion • Set TCDI • Check automatic setup application • Trajectory stability

  11. Sector test measurements II • Injection • Threading through injection region onto closed TDI • Set TDI, TCLI • Aperture in injection region • Orthogonal steering • MKI waveform scan (change of screen conductors, TMR aging) • MKI synchronisation • AGK synchronisation • IQC injection oscillation interlock

  12. Sector test measurements III • Beam dump • Synchronisation • Rough check of extraction channel aperture • BTVD/BTVDD image • Test 14/15 MKD knob • MKB waveform – check with ~5 pilots • MKD waveform – never tested, procedure to be set up

  13. Summary • 3-4 blocks of tests • Preparation checks • Preparation with beam until upstream TED – also downstream TED possble? • Preparation with BIS loop closed – will there be time scheduled before the sector test? • Sector test measurements • Detailed procedures on new items/tests to be established • BETS for TDI, MSI, TCDQ • MKD waveform