1 / 33

Status of ITER

Status of ITER. 2 nd RCM-FENDL-3 23 rd March 2010 Michael Loughlin Office of Central Integration and Engineering ITER. ITER is the Next Step Toward a Solution based on Tokamaks. SST-1: R =1.1m, 0.22MA, 2008.

marrim
Download Presentation

Status of ITER

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of ITER 2nd RCM-FENDL-3 23rd March 2010 Michael Loughlin Office of Central Integration and Engineering ITER

  2. ITER is the Next Step Toward a Solution based on Tokamaks

  3. SST-1: R =1.1m, 0.22MA, 2008 Four New Superconducting Tokamaks will Address Steady-State Advanced Tokamak Issues in Non-Burning Plasmas EAST: R = 1.7m, 2MA, 2006 JT-60SA: R = 3m, 5.5 MA, 2014 KSTAR: R = 1.8m, 2MA, 2008

  4. RF CN European Union KO JP IN US ITER – Key Facts • Mega-Science Project among 7 Members: • China, EU, India, Japan, Korea, Russia & US • Designed to produce 500 MW of fusion power for an extended period of time with a Q of 10 • 10 years construction, 20 years operation • Cost:~5.4 billion Euros approved for construction, and ~5.5 billion for operation and decommissioning • EU 5/11, other six parties 1/11 each. Overall reserve of 10% of total.

  5. Procurement Sharing - A unique feature of ITER is that almost all of the machine will be constructed through in kind procurement from the Members with essentially every member involved in every component.

  6. Overview of the Major Development of the ITER Project

  7. ITER Organization Structure Tim Watson

  8. Staffing Status By 31 December 2009, the ITER Organization had a total of 430 staff members, comprising 291 professional and 139 technical support staff members. In addition, as of end of 2009 there were around 330 external contractors.

  9. ITER - a multicultural organization 25 nationalities

  10. The ITER Organization and the ITER Domestic Agencies

  11. Integration between IO and DAs- Basic Roles and Responsibilities - * Depending on type of specification - Functional: Functional requirements by IO and design by DAs - Detail design: Conceptual design by IO and detailed design by DAs - Build-to-print: Detailed design by IO and fabrication/shop design by DAs

  12. Main Buildings on the ITER Site A facility licensed under the French Nuclear Regulatory Authority (ASN) PF Coils winding Tokamak Cryoplant Tritium Magnet power convertor Cooling towers Hot cell • Will cover an area of about 60 ha • Large buildings up to 250m long • Large number of systems Main Office Control

  13. Status of ITER’s technical progress (highlights) Fusion gain Q = 10, Fusion Power: ~500MW, Ohmic burn 300 to 500 sec Goal Q=5 for 3000 sec Central Solenoid (6) (Nb3Sn) Cryostat (29 m high x 28 m dia.) Thermal Shield (4 sub-assemblies) Toroidal Field Coils (18) (Nb3Sn) Vacuum Vessel (9 sectors) Poloidal Field Coils (6) (NbTi) In-Vessel Coils (2-VS & 27-ELM) Correction Coils (18) (NbTi) Blanket (440 modules) Divertor (54 cassettes) Feeders (31) (NbTi) Machine mass: 23350 t (cryostat + VV + magnets) - shielding, divertor and manifolds: 7945 t + 1060 port plugs - magnet systems: 10150 t; cryostat:  820 t

  14. Magnet Energy Comparison Superconducting Magnet Energy: ~51 GJ Charles de Gaulle Energy: ~38000 t at ~150 km/hr

  15. TF Coil – Mass Comparison Boeing 747-300 (Maximum Takeoff Weight) ~377 t Mass of (1) TF Coil: ~360 t 16 m Tall x 9 m Wide

  16. TF and PF Jacketing in: CN JA US RF

  17. ITERProcurement - a Worldwide Collaboration Example: TF Coils

  18. Overview of Schedule for 2019 First Plasma ITER Construction 2022 2021 2023 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 TF Coils (EU) Case Winding Mockups Complete TF10 TF15 CS Coil CS Final Design Approved CS3L CS3U CS Ready for Machine Assembly Vacuum Vessel (EU) VV Fabrication Contract Award VV 05 VV09 VV07 Buildings & Site Construction Contract Award Tokamak Bldg 11 RFE Tokamak Assembly Start Machine Assembly Tokamak Basic Machine Assembly Start Install CS Start Cryostat Closure Ex Vessel Assembly In Vessel Assembly Assembly Phase 2 Assembly Phase 3 ITER Operations Pump Down & Integrated Commissioning Plasma Operations First Plasma

  19. 34 signed Procurement Arrangements as of 16 March 2010

  20. Procurement Arrangements (PAs) • As of 18 March 2010, there are a total of 34 signed PAs, amounting to 1243.37844 kIUA (approximately EUR 1,900 million), about 41% of the total in-kind PA value; • 19 PAs are scheduled to be signed by August 2010 for a total of 776.453 kIUA (an estimated EUR 1,186 million).

  21. PAs to be signed by August 2010 according to the IPS

  22. PAs to be signed by August 2010 according to the IPS

  23. PAs to be signed by August 2010 according to the IPS

  24. ITER Schedule Following First Plasma: Path to DT in 2026 FirstPlasma ITER Commissioning and Operations 2019 2020 2021 2022 2023 2024 2025 2026 2027 Hydrogen Operations & Coil Commissioning Shutdown First Plasma Commission Install In-Vessel Equipment, ECRH & ⅓ Diagnostics Hydrogen Operations Tritium Plant Full DT Throughput Install Blanket, Divertors,1st NBI, ICRH? & ⅓ Diagnostics Shutdown Install 2nd-NBI, & ⅓ Diagnostics Commission H & He Operations Pre-Nuclear Shutdown Tritium Plant Ready for Nuclear Operation Neutron Diagnostic Calibration All H&CD Fully Commissioned Hydrogen Operations DD & Trace DT Operations Full DT 500 MW Fusion Attempt

  25. The IO works towards finalizing a full set of baseline documents by the end April (scope, schedule, cost); Scope is set in 2008. Schedule agreed as working basis in March 2010; Resource loading of IPS for the IO is ongoing; The acceptance of the ITER baseline towards a commonly agreed upon schedule is a huge step forward, since every party is committed to a common plan. What is Next?

  26. Present ITER Construction Site Future Tokamak Complex JWS 2 JWS 3 The creation and improvement of 106 kilometres of access roads from Fos harbour to Cadarache will be finished by February 2010. 1

  27. Itinerary of ITER Components = Itinerary of ITER Components ITER Site

  28. The Roadmap Beyond ITER upgrade,construction Operation Today’s expts. Des. Construction H D DT 2nd DT Op. Phase ITER Test/Optimise Blanket Design Construction Qualify DEMO Materials Optimise Materials IFMIF Design Construction Initial Operation Reliability demo DEMO Concept Design Construction Op. Alternative Confinement Schemes Commercial Power Plants

  29. Summary • It took almost four years to re-baseline ITER and have a common understanding of the real cost of ITER. In the parties and for the IO. • The baseline decision by Council in June 2010 will set the real trigger for all countries to now move at the same pace. • We still have lots of things to improve, technically, managerially and also in interfacing with industry partners.

  30. ITER Licensing Process • Accordance with French regulations ITER is a “basic nuclear facility” (Installation Nucléaire de Base, INB) e.g. labs, fuel plants, not fission reactors. Compliance with international standards of safety (IAEA) • Licensing process: • Safety options report submitted and reviewed 2002 • Series of informal technical meetings with the authorities (ASN) and their technical advisors (IRSN), 2006 – 2008. • License application documents were submitted January 2008 • Request for authorisation (Demande d’Autorisation de Création, DAC), including Impact Study • Preliminary Safety Report (Rapport Préliminaire de Sûreté, RPrS) • Examination of files submitted in January 2008 • Authorities (ASN & IRSN) reviewed our files for acceptability • In July 2008, they requested detailed additional information in the files • DAC and RPrS are now being updated, for re-submission in 2010 • Next: Public Enquiry. Then examination by panel of independent experts (Groupe Permanent) to advise ASN.

  31. Current status (October 2009) • All RPrS chapters and Impact Study are in first draft • Some require completion with the outcome of safety analyses in progress, or design information from baseline documents to be fixed • Many annexe documents completed • Translation into French under way • Reviews of RPrS to be held October – December, by technical ROs, Safety Control Division (“second level” check), and in review including external experts - English version to be finalized by end of 2009 • Translation in French and final checking • Submission expected end of February 2010 • Should lead to issue of decree allowing “creation” of facility. • Further processes will follow to obtain authorisation for commissioning and start-up.

More Related