Royal Palms Parkway City Council Workshop July 29, 2014. Scope of Work. Project Length: 2.2 Miles Roadway resurfacing with new four foot paved shoulders New Eastbound Left Turn Lane at Royal Palms Pkwy and Rickenbacker Drive – Improves safety and intersection capacity
E N D
Scope of Work • Project Length: 2.2 Miles • Roadway resurfacing with new four foot paved shoulders • New Eastbound Left Turn Lane at Royal Palms Pkwy and Rickenbacker Drive – Improves safety and intersection capacity • New Eastbound Right Turn Lane at Royal Palms Pkwy and Belle Terre Pkwy – Improves safety and intersection capacity • Safety improvements for path to Lehigh Trail at the intersection of Royal Palms Pkwy and Rymfire Drive • Three Rectangular Rapid Flashing Beacons (RRFB) • Median Refuge
Pedestrian Improvements • Royal Palms Pkwy & Rymfire Drive
Map Area US 1 Belle Terre Pkwy Project Start Royal Palms Pkwy Project End
Project Budget • Original Estimated Construction Budget – $900k • Proposed FY 2015 Budget - $1.33 Million • Actual Cost • Construction Bid – $1.18 million • Contingency, CEI & Misc Expenses – $150k • Total – $1.33 million