1 / 12

GLAST CsI calorimeter status Alexandre Chekhtman, NRL/GMU (representing GLAST collaboration)

GLAST CsI calorimeter status Alexandre Chekhtman, NRL/GMU (representing GLAST collaboration). Design Ongoing work Production schedule. Institutions participating in GLAST project. USA:

martha
Download Presentation

GLAST CsI calorimeter status Alexandre Chekhtman, NRL/GMU (representing GLAST collaboration)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLAST CsI calorimeter statusAlexandre Chekhtman, NRL/GMU(representing GLAST collaboration) • Design • Ongoing work • Production schedule

  2. Institutions participating in GLAST project • USA: • Stanford University, SLAC, NASA Goddard Space Flight Center, Naval Research Laboratory, University of California (Santa Cruz), Sonoma State University, University of Washington, Texas A&M University (Kingsville) • Japan: • University of Tokyo, Institute for Cosmic-Ray Research, Institute for Space and Astronautical Science, Hiroshima University • Italy: • INFN, Italian Space Agency, Istituto di Fisica Cosmica(Milano), Univ. of Baru, Univ. of Perugia, Univ. of Pisa, Univ. Of Rome 2, Univ. of Udine • France: • LLR-Ecole Polytechnique, PCC-College de France, CENBG (Bordeaux), CEA/DAPNIA(Saclay) • Sweden: • KTH (Royal Institute of Technology), Stokholms Universitet

  3. Large Area Telescope (LAT) Design Overview Instrument 16 towers  modularity height/width = 0.4  large field-of-view Si-strip detectors: 228 mm pitch, total of 8.8 x 105 ch, thin tungsten radiators hodoscopic CsI crystal array  cosmic-ray rejection  shower leakage correction XTkr + Cal = 10 X0 shower max contained < 100 GeV segmented plastic scintillator  minimize self-veto > 0.9997 efficiency & redundant readout Tracker Calorimeter Anticoincidence Detector Shield 3000 kg, 650 W (allocation) 1.75 m  1.75 m  1.0 m 20 MeV – 300 GeV

  4. Electronics boards attached to each side. Electronic readout to connectors at base of calorimeter. Outer wall is EMI shield and provides structural stiffness as well. Each Module 8 layers of 12 CsI(Tl) Crystals Crystal dimensions: 27 x 20 x 333 mm Hodoscopic stacking - alternating orthogonal layers Dual PIN photodiode on each end of crystals. Mechanical packaging – Carbon Composite cell structure Calorimeter Module Overview Modular Design 4 x 4 array of calorimeter modules

  5. Calorimeter Technical Challenges • Imaging calorimetry to support background rejection and to improve energy measurement via shower profile correction or leakage estimation. • Longitudinal positioning in individual crystals using light asymmetry between ends of crystal • Large dynamic range (~5 x 105) with low power electronics • Divide signal into 4 ranges using dual PIN photodiode of differing areas (two ranges per diode) • Custom CMOS ASIC front end electronics • Minimize passive material and gaps in active material caused by modular design, yet survive 6g launch loads. • Carbon composite structure with individual cells for each CsI crystal. • In-flight calibration • Use cosmic rays (p – Fe)

  6. Manufacturing responsibilities • Sweden Deliverables • Receive xtals from vendor (Amcrys, Kharkov, Ukraine) 2040 xtals • Acceptance/verification tests • Ship to France • France • Assemble Crystal Detector Elements (CDEs) 2040 CDEs • Manufacture mechanical structure 18 structures • Test • Ship to NRL • Naval Research Lab • Assemble Calorimeter Module 18 modules • Manufacture front-end electronics • Integrate CDEs with structure and electronics • Test and calibration • Pre-Ship Review • Ship to SLAC for integration into LAT

  7. PIN diodes • Derived from commercial photodiodes • Customized dimensions for GLAST • Uses standard manufacturing • Implement two diodes on single carrier • Single carrier for convenience • Need large diode for low energy threshold (~2 MeV) • Want small diode large enough for ground test with muons • Use flexible interconnect to AFEE BTEM ’99 Dual PIN Diodes Hamamatsu Photonics 96 mm2 and 24 mm2

  8. Crystal-Detector Element • Combination of crystal, PIN diode, and wrapper is called Crystal Detector Element (CDE) • Careful choice of wrapper to optimize light yield • Use 3M specular reflector film VM2000 • Careful choice of bonding material for PIN diode-crystal bond • Nature of crystal (performs like oil-coated lead) makes adhesion difficult • CTE of CsI is large, while CTE of diode is small • Use DC93-500, a silicone elastomer with primer Beam test CDEs

  9. Mechanical Structure French Contribution • Carbon fiber structure • Must hold ~80 kg of CsI at 6-g acceleration with ~10 kg of supporting material • Must manage thermal expansion of CsI • Mechanical details • 96 individual carbon cells • Al top, bottom, and side plate • Bottom plate is mechanical support for DAQ, control, and power supplies • Sides support AFEE boards

  10. Electronics Design • Design • Need to cover a very large dynamic range • From threshold (~2 MeV) to 100 GeV in a crystal • Low noise (2000 electrons noise) • Low power (~20 mW per crystal end) • Limited space (8 mm thickness), match pitch of CsI crystals (28x40 mm) • Interface to Tower Electronics Module (TEM, remainder of DAQ chain) • Implementation • Use 1 custom analog and 1 custom digital ASIC to minimize power • Use 2 diodes with 2 channels each to reduce dynamic range requirement on electronics • Ranges to 200 MeV, 1.6 GeV, 12.5 GeV and 100 GeV • Use commercial 12-bit ADCs • Low dead time (20 s) • Zero suppression to reduce data volume

  11. Calorimeter Status • CDE status: • Specification and procurement of CsI crystals is in place. • Specification and procurement of dual PIN photodiode prototypes is complete • 400 photodiodes have been received. • Bonding material, DC93-500 - a silicone elastomer, has been selected • Resolves CTE mismatch between CsI and PIN diode • Crystal wrapping material is from 3M – VM2000 specular reflector film • Mechanical structure status: • Prototype mechanical structure has been produced and is undergoing testing • Electronics status: • CAL Analog ASIC (GCFE) is in its 5th iteration and being tested. • CAL digital ASIC (GCRC) first submission occurred Dec 2001 • Commercial off-the-shelf (COTS) ADCs and other components have passed radiation hardness test. • CAL analog front end electronics boards (AFEE) have been prototyped

  12. Production schedule • Engineering Module: • planned to be assembled and tested in 2002 • 130 CsI crystals for EM available now • Flight Modules: • CsI deliveries (1910 crystals): Apr 2002 – Apr 2003 • Cal module integration and tests : Nov 2002 – Dec 2003 • Instrument integration and test: Jan 2004 – March 2005 • Spacecraft integration and test: March 2005 – March 2006 • Launch: March 2006