An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IMO - Metering

  2. HONI Temporary Dispensation • HONI applied for and received temporary permission from MC for the 383 meters that seal expire during 2003 • The temporary dispensation is for a year • Conditions apply e.g. agreement between the purchaser and the seller

  3. Seal Expiry - Market Rules • The expiry date of the seal period has not changed • At seal expiry under the MR, the following happens: • The Transitional MSP function ends • The metering installations loose their registration with the IMO • Metering installations have to be in compliance with the MR

  4. MSP Function • With the transitional MSP role ending, MMPs will need to get a new MSP and sign an agreement • MR require that MMPs have an MSP and a signed agreement • Registered MSPs see IMO website • No agreement means non-compliance • All non-compliance will be investigated by the IMO

  5. Metering Installations - Loss of Registration • At seal expiry, metering installations registered under Alternative Metering Standard, loose their registration • Per MR the IMO cannot settle with meters not registered • Proposed MR 249 - still to be ruled on by the Technical Panel & the IMO Board - will allow these meters to be used for settlement purposes

  6. Metering Installations - Compliance • At seal expiry, metering installations registered under the Alternative Metering Standard, must to be upgraded to compliant • Installation of a single conforming main meter - ITs as is - is now in compliance with the MR • Proposed MR 249 will allow the 2003 temporary dispensation meters to be used until the end of 2004. • Metering will have to comply by 31 Dec 2004.

  7. ITs non- MC type approved • ITs that do not have MC type approval do not meet the MR • To satisfy the MR - MMPs will have to first satisfy MC • Have your MSP check your ITs • MC type approved • Accuracy class (ITs with lesser accuracy will attract a correction factor after May 2006)

  8. Challenges Ahead • Approx. 300 meters seal will not be changed this year • Approx. 400 meters expire next year - 700 meters need to be changed in 2004 • Getting the meters changed is a challenge to MSPs • Audits - the IMO will continue to audit metering installations