Lafayette New Terminal Program Update March 13, 2019
LA FP&C • Coordinating with FP&C to confirm bid process and eligible items for terminal contribution • 2019 Capital Outlay Application submitted • Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application • Revised EDA grant application submitted and received decision that the application meets further consideration TSA OTA Application • Submitted Grant Application, waiting on feedback Terminal Program Update
Airlines • Working with Airlines to discuss leasable space and an agreement to buildout space in New Terminal QTA \ Ready Return • Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates • Rental cars agreement to move to Short Term Lot - completed Concessions Terminal Program Update
Enabling Demo • Demolition - Complete • AOA fencing and gates – Complete • Fill Material and Asphalt – Complete • Seeding/Sod – Complete • Substantially Complete • Reviewing completion paperwork and waiting on 45-day lien-free period • Final Acceptance - upcoming Terminal Program Update
Rental Car Quick Turn Around Facility Timeline: • Oct. 2018: Commission Approved Updated CFC • Nov. 2018: Construction Bids Due • Dec. 2018: Approved Bids • Jan. 2019: FP&C Construction Concurrence • Feb. 2019: Award Contract • Preconstruction meeting completed 2/20/19 • Apr. 2019: NTP • Feb. 2020: Construction Complete Terminal Program Update
GMP 1: Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update GMP 2: Approved 1/15/19, Notice to Proceed 1/15/19 GMP 3: Terminal Building Shell, MEP and Finishes 100% Design to complete in Feb. 2019 – Presentation in April Bidding in Mar. 2019 Approval by LAC May 2019
New Terminal Construction Update Project 1 – RTR Cable Relocation • Cable wire pulled, spliced, and FAA cutover complete • Manholes 1 through 4 set and backfilled, asphalt placement upcoming GMP1 – Project 1
New Terminal Construction Update Project 2 – RTR Facility • Duct banks for the RTR cable from the building to tower – complete • Building walls and roof trusses– complete GMP 1 – Project 2 RTR Facility
New Terminal Construction Update Project 2 – RTR Facility • RTR tower foundations – ongoing • Facility ice and water shield – ongoing GMP 1 – Project 2 RTR Facility
New Terminal Construction Update Project 3 – Terminal Foundations • Test Pile Program – installed and testing • Milling and fence moving – ongoing GMP 1 – Project 3 Terminal Foundations
New Terminal Construction Update Project 5 – Enabling Parking • Economy lot – site grading and compaction – ongoing • Short-term parking lot re-striping – completed • Substantial completion for short term parking lot (Phase 3B) GMP 1 – Project 5 Enabling Parking