1 / 19

Week 15A - Scheduling (Chapter 15)

Week 15A - Scheduling (Chapter 15). Terminology, lead time, priority rules, theory of constraints (discussed in Capacity) , volume considerations. Volume considerations. High volume ( repetitive, continuous flow ) Flow-shop scheduling (rate based) Intermediate volume ( job/repetitive )

matt
Download Presentation

Week 15A - Scheduling (Chapter 15)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Week 15A - Scheduling (Chapter 15) Terminology, lead time, priority rules, theory of constraints (discussed in Capacity), volume considerations SJSU Bus. 140 - David Bentley

  2. Volume considerations • High volume (repetitive, continuous flow) • Flow-shop scheduling (rate based) • Intermediate volume (job/repetitive) • Mixed model scheduling • Low volume (job) • Operation scheduling (forward/backward/ midpoint) • Synchronized scheduling SJSU Bus. 140 - David Bentley

  3. Low Volume Scheduling Job Shops SJSU Bus. 140 - David Bentley

  4. Elements of Lead Time • Queue – job waiting to be worked on (jobs with higher priority are ahead) • Setup – Making the machine or workplace ready to work on a job • Run – performing the required action to complete an operation on a job • Wait – awaiting a move to the next operation / work center or the stockroom • Move (transit) – time moving to next operation / work center or stockroom SJSU Bus. 140 - David Bentley

  5. Lead time elements Queue Setup Run Wait Move |----------------|--------|------------|------|-----| SJSU Bus. 140 - David Bentley

  6. Scheduling Terminology • Operation – a discrete step or task, one of a number required to make an item • Workstation – a specific machine oremployee work space • Workcenter – a machine grouping or work grouping used for scheduling and costing • Routing – a sequenced list of operations, with associated work centers • Job – an order to produce a specific quantity of an item with a specific start and/or due date SJSU Bus. 140 - David Bentley

  7. Sequence of operations Q S R W M |-----|----|------|---|---| Q S R W M Seq 010 |-----|----|-------|---|---| Seq 020 SJSU Bus. 140 - David Bentley

  8. Loading and Scheduling • Loading – assigning jobs to work centers • Infinite vs. finite loading and scheduling • Infinite – ignored capacity constraints • Finite – considers capacity constraints • Forward vs. backward scheduling (+midpoint) • Forward – start with start date, determine due date • Backward – start with due date, determine start date • Midpoint – from current date, determine revised due date SJSU Bus. 140 - David Bentley

  9. Sequencing and Dispatching • Sequencing – determining the sequence of processing jobs at a work center • Priorityrules – rules used in sequencing (see later overhead) • Dispatchlist – authorized sequence list • Input-OutputAnalysis – monitoring the flow of work into and out of work centers to assure a steady flow and to identify problem areas SJSU Bus. 140 - David Bentley

  10. Sequencing & Priority Rules • FCFS – first come, first served • SPT – shortest processing time • EDD – earliestdue date • CR – critical ratio • (time remaining / processing time) • Time remaining = (due date – “now” date) • S/O – slack per remaining operation • ESD – earliest start date • Other – favorite customer, “hot” job, etc. SJSU Bus. 140 - David Bentley

  11. Charts • Gantt – visual (bar chart) representation of schedule and actual performance • Load – Gantt chart showing load and idle time for a machine or work center by time period • Schedule – Gantt chart showing the progress of jobs by time period SJSU Bus. 140 - David Bentley

  12. PerformanceMeasures • Job Flow Time • Time at a workstation, work center, or plant • Includes Q,S,R,W,M • Average Flow Time (group of jobs) • Sum of flow times for n jobs / n • Job Lateness • Expected due date – original due date • Makespan (group of jobs) • From start of first job to end of last job • Average number of jobs (group of jobs) • Total flow time / Makespan SJSU Bus. 140 - David Bentley

  13. Other Related Activities - 1 • Dispatching • Expediting • Queue compression • Lot splitting • Job overlapping • “Stop what you’re doing and work on this!” BAD!! • Synchronized scheduling • Timing of production meshed with use rate • Example: bakery oven SJSU Bus. 140 - David Bentley

  14. Other Related Activities - 2 • Input-OutputAnalysis • Monitoring the flow of work into and out of work centers to assure a steady flow and to identify problem areas • Reports the following: • Input for the period • Output for the period • Queue change SJSU Bus. 140 - David Bentley

  15. High Volume Scheduling Repetitive and Continuous Flow SJSU Bus. 140 - David Bentley

  16. Rate Based Scheduling • Schedule by quantity per • Month, • Week, • Day, • Shift • Limited number of items • Seek to achieve flow SJSU Bus. 140 - David Bentley

  17. Intermediate Volume Scheduling Bridge Between Job Shop and Repetitive Operations SJSU Bus. 140 - David Bentley

  18. Mixed Model Scheduling • Interspersing different models • Alternative to producing longer runs of each model • Look for: • Lowest ratio and • Most repetitive mix • Bicycle example SJSU Bus. 140 - David Bentley

  19. Service Operations • Appointment book (e.g., dentist) • Reservations (e.g., airlines) • Scheduling multiple resources • Managing capacity SJSU Bus. 140 - David Bentley

More Related