Corby Weir Investigation Project. Corby Weir Investigations and significant events Background and History - Weir construction and Purpose Concerns raised by fisheries interests - environmental impact on fish populations EFP/SAP Workshops - discussions and evidence presented
E N D
Corby Weir Investigations and significant events Background and History - Weir construction and Purpose Concerns raised by fisheries interests - environmental impact on fish populations EFP/SAP Workshops - discussions and evidence presented Setting up of the Technical Working Group -> Corby Weir Investigation Project Independent Consultant appointed - Peter Walker of APEM Ltd Report on Options Appraisal Final Consultation on Options with Fisheries Interests
Weir Construction Built in 1996 to replace the weed and bridge affected site at Warwick Bridge, at a cost of approx £300,000. Corby Weir is a compound non-standard Crump weir design , not built to BS specification as it incorporates a 1 : 8 rather than 1 : 5 downstream slope for fish counter instrumentation purposes and to reduce water velocities over the weir to assist fish passage. The construction provides a static cross section and fixed bed to allow accurate monitoring of laminar flow. Its principle purpose being to provide Continuous Flow measurement and Flood forecasting Fish count data to determine migratory fish populations and influence management decisions
Concerns raised by Fisheries interests - Barrier to free movement of fish - Predation of smaller fish particularly smolts above and below the weir - Does the Fish Counter provide valuable data and how accurate is it ? Workshop discussions and evidence Short film and discussion points Salmon stocks and rod catch Fish counter validation and species apportionment Nov 2012 what Options should we consider ?
Technical working group formed First meeting Jan 14th - EA submissions of essential Hydrology requirements of CW The Hydrology team stressed that CW is a critical component in providing continuous flow data that has to be maintained for Flood forecasting and Flood warning – for Carlisle and neighbouring districts developed on the Eden Flood Forecasting model which is updated at CW giving reliable flows up to extreme flood events. This data informs the County Flood response teams and emergency services. The weir is the only fixed structure of its kind on the Eden and gives extremely accurate data. The next upstream gauging stations being Temple Sowerby and Udford (Eamont). The site also serves several functions for Water Resources management providing data for the CAMS flow calculation, a low flow alarm site, a means of assessing effects of abstraction by UU of water upstream at Cumwhinton and groundwater together with discharges above the weir. REDFA questioned whether less intrusive methods of flow measurement had been considered . Also whether the position of CW so close to Carlisle gave sufficient time warning of events. Additionally whether monitoring of severe flood events were reliable due to downstream backing up effects. REDFA stressed the need for a full and independent review of the Weir impacts on Fish Passage.
Corby Weir Investigation Project commissioned by the EA • Independent Consultant brief agreed by parties • Consultant Peter Walker of APEM Ltd appointed • Site visit and second meeting Feb 14th • REDFA and YFF presented a prepared Position Statement setting out our contentions that • the Weir presents a major obstruction to fish passage with added predation mortality • the fish counter has not provided accurate count data or species apportionment • consent for construction of the Weir from YFF/CC was reached with NRA on the • agreement that the fish counter would provide valuable data on the management of Salmonid populations • In conclusion we acknowledged that flow measurement in the vicinity of this site is essential for flood management and water resources purposes but that all options must be considered to reduce the unintended long term impact to our Fisheries and the rivers SAC designation. • This may be the only opportunity that we have to plan and bring about these improvements in the foreseeable future
Peter Walker of APEM Ltd to present a report on his findings and provide the Options Appraisal for Corby Weir at the next working group meeting. Because of the technical complexities in assessing the Flow Management requirements this date has been scheduled for March 26th Final consultation and discussions with Fisheries interests Evening meeting to be arranged 1st or 2nd week April